Professional Documents
Culture Documents
Tender is an offer which incorporates the sum of money, time and other conditions required to carry
out the contract obligations in order to complete a project or a part of it consisting of specified works.
OR
The Tender is an offer in writing to execute some specified work or to supply the materials rates within
fixed time under certain conditions of agreement between the contractor and the department or owner
or any party
Necessity of Tender
• Lower bids that may be obtained due to competition among the contractors.
• Selection of contractors can be made based upon their experience in their line.
• Personal interests, prejudices, preferences, Partiality can be avoided by calling for tenders.
Processing of works
• Following are the stages in planning, sanctioning and execution of work.
(a) Inclusion in Procurement Plans
(b) Preparation of Preliminary Project Report (PPR)
(c) Administrative Approval
(d) Preparation of Detailed Project Report (DPR) & Detailed Estimates
(e) Technical Sanction
(f) Appropriation of funds
(g) Preparation of Tender documents
(h) Call of Tenders and Award of Work
(i) Execution of works
(j) Monitoring of works and Quality Assurance
• Background of the work/ project justifying the need for the work
• Details of scope of the project
• Availability of auxiliary services like roads, power, water, solid & liquid waste disposal
system, street lighting and other civic services shall be ensured.
• Preliminary estimated cost
• Time of the completion
• Environmental impact assessment (EIA)
• Cash flow : This will show year-wise requirement.
Administrative Approval
• For every work, it is necessary to obtain, in the first instances the concurrence of the
competent authority of the administrative department requiring the work. The formal
acceptance of the proposals by the authority is termed as Administrative Approval of the
work.
• It is duty of the engineering department requiring the work by the administration to obtain
the requisite approval to it.
• An approximate estimate and such preliminary plans are necessary to explain the proposals
are submitted by an engineering department to the administration to obtain administrative
approval to take up the work within the sanctioned amount.
• After receiving the administrative approval, detailed drawings, design and the estimated
cost etc. are prepared by the engineering department and submitted to the administrative
department for sanction.
Technical Sanction
Technical sanction to detailed cost estimates shall be accorded by the Works Committee so as to ensure
that proposals are structurally sound and that the estimates are accurately calculated based on
adequatedata.
Appropriation of funds
Before taking up the execution of work it shall be ensured that proper funds are available to meet out
the expenditure on the work.
Prequalification of Contractors :
Registration of contractors:- The contractor must get himself registered in the departments (
Government - govt. Contractor) for which he is interested to take up works.
Government contractors are entitled to do govt. jobs if awarded.
Contractors are classified according to the registration and registration fees and depending on
this they can undertake works up to certain amount.
Sometimes works are awarded on the basis of quotations invited from a group of ‘selected
tenderer’ (a group of known reputed contractors) who are considered suitable for that job. This
method is known as ‘pre-qualification’ and saves a lot of time.
In the advertisement itself it must be mentioned that only contractors having experience in the
particular work should submit the tender.
To get a contractor to be registered under certain class, he has to apply to the competent
authority.
The application should contain the following documents:
1. Current income tax certificate
2. Work certificates for all the works performed during the
last three years and those in progress
3. Solvency certificate for an appropriate amount
4. Attested copy of deed of partnership and power of attorney on stamp paper if needed
5. Application in duplicate with all documents
6. Attested photos of all the partners if any
▪ In relation to the public works, following catogories of contractors are generally enlisted or
building and roads
o For sanitary installations and water supply
o For electrical and air conditioning
o For furniture.
▪ Contractors at B and C must process valid plumbing and electrical licence
▪ Each of them is expected to have machinery and equipment required for the job
▪ Their qualifications are further adjudged from
o Professional ability to understand and implement the contractual obligations and
subsidiary instructions given by the engineer in charge of the department.
o Their financial resources
o Capacity to control labour, especially by a way of regular payment of fair wages and
observance of labour regulations
o Their zeal for maintaining reputation and integrity
Publicity of Tenders :
▪ Wide publicity shall be given to the Notice Inviting Tender.
▪ Tenders must be invited in the most open and public manner possible, by advertisement in the
Press and by notice in English/Hindi and regional language of the concerned District.
▪ The Notice Inviting Tender shall also be placed on the website of the Ministry/Department
Format of an ideal Tender Notice :
▪ Name of the Project.
▪ Name & Address of the Company floating the tender.
▪ Name of work, materials or services.
▪ Place of work location.
▪ Approximate estimated cost of work.
▪ Earnest Money.
▪ Period of completion.
▪ Date on which the Tender Document sale commences
▪ Date and time up to which tender documents can be obtained.
▪ The cost of tender documents.
▪ The date and time up to which the tenders to be submitted and are to be opened.
▪ Specification.
▪ Eligibility Criterion.
▪ The designation of the officer who accept the tender
Sample Copy of Tender Notice(PWD) :
Pre-bid conference
• A supplier or contractor may request a clarification of the tender documents from the procuring
entity within a reasonable time prior to the deadline for the submission of tender. The procuring
entity shall respond within a reasonable time, so as to enable the supplier or contractor to make
a timely submission of its tender.
• At any time prior to the deadline for submission of tenders, the procuring entity may for any
reason, whether on its own initiative or as a result of a request for clarification by a supplier or
contractor, modify the tender documents by issuing addendum
Evaluation of bids
• The procuring entity may ask suppliers or contractors for clarifications of their tenders in order
to assist in the examination, evaluation and comparison of tenders.
• No change in a matter of substance in the tender, including changes in price and changes aimed
at making an unresponsive tender as responsive shall be sought, offered or permitted.
• The procuring entity shall correct purely arithmetical errors that are discovered during the
scrutiny of tender. The errors will be corrected by the procuring entity as follows.
(a) If rates in words does not tally with rates in figure then the rate which correspond to the
amount in words shall be taken as correct.
(b) If the amount of an item is not worked out by the contractor or it does not correspond with
the rates written either in figure or in words then the rate quoted by the contractor in words
shall be taken as correct.
▪ After the correction of the error as above, the procuring entity shall give prompt notice of any
such correction to the supplier or contractor that submitted the tender.
▪ If the bidder does not accept the corrected amount, the bid will be rejected and the earnest
money may be forfeited
▪ The procuring entity may regard a tender as responsive only if it conforms to all requirements
set forth in the tender documents.
▪ The procuring entity shall not accept a tender if the supplier or contractor that submitted the
tender, is not qualified and if the tender is not responsive.
▪ The procuring entity shall evaluate, prepare comparative statement of tenders and compare the
tenders that have been accepted in order to ascertain the successful tender in accordance with
the procedures and criteria set forth in the tender documents. No criteria shall be used that has
not been set forth in the tender document. The successful tender shall be the tender with the
lowest price
▪ Information relating to the examination, clarification, evaluation and comparison of tenders
shall not be disclosed to suppliers or contractors or to any other person not officially involved
in the examination, evaluation or comparison of tenders except to the extent required under law.
Letter of intent
▪ Client identifies the agency to whom the work is to be awarded and issues a letter of intent
asking the bidder
o To deposit the performance guarantee say ( 5% of award value)
o Mobilise and commence work. ( date of commencement is mentioned in LOI)
▪ Performance guarantee is released after the issue of completion certificate by the client ( if the
performance , time etc during the execution is found satisfactory.
Mobilization advance
• In respect of certain specialized and capital intensive works, mobilization advance normally
limited to a maximum of 10% of estimated cost of work may be allowed to contractor at the
specified rate of interest.
• The advance shall be against a Bank Guarantee of a scheduled Bank for full amount of advance.
• Recovery of such advances shall be made by deduction from contractor’s bills as specified in
the contract.
• First Installment of fifty percent of total mobilization advance shall be paid after the agreement
is signed and upon submission of performance guarantee for full amount as specified.
• 2nd installment of twenty five percent of total mobilization advance will be paid after the setting
up of site office and site laboratory, complete mobilization of plant and machinery, scaffolding
& shuttering materials etc.
• The Balance twenty five percent of total mobilization advance shall be paid on completion of
10% of work in terms of cost and after the contractor has fully mobilized the work at site.
SECURED ADVANCE
• The contractor, on signing an indenture in the form to be specified by the Engineer-in- Charge,
shall be entitled to be paid during the progress of the execution of the work up to 90% of the
assessed value of any materials which are in the opinion of the Engineer-in-Charge non-
perishable, non-fragile and non-combustible and are in accordance with the contract and are
adequately stored and/or protected against damage by weather or other causes.
• When materials on account of which an advance has been made under this sub-clause are
incorporated in the work, the amount of such advance shall be recovered/deducted from the
next payment made under any of the clause or clauses of this contract.
• The contractor shall construct suitable go-down at the site of work for safe storage of the
materials against any possible damages due to sun, rain, dampness, fire, theft etc. at his own
cost.
• The decision of the Engineer- in-Charge shall be final and binding on the contractor in this
matter.
• No secured advance, shall however, be paid on high-risk materials such as ordinary glass, sand,
petrol, diesel etc.
Suspension of works
• The contractor shall, on receipt of the order in writing of the Engineer-incharge, suspend the
progress of the works or any part thereof for such time and in such manner as the Engineer-in-
charge may consider necessary for any of the following reasons.
i) On account of any default on part of the contractor, or
ii) For proper execution of the works or part thereof for reason other than the default of the
contractor, or
iii) For safety of the works or part thereof.
• The contractor shall, during such suspension, properly protect and secure the works to the extent
necessary and carry out the instructions given in that behalf by the Engineer-in-charge.
• If the suspension is ordered for reasons (ii) and (iii) as above.
1. The contractor shall be entitled to an extension of the time equal to the period of every such
suspension plus 25% for completion period. No adjustment in contract price will be allowed
for reasons of such suspension.
2. In the event of the Contractor treating the suspension as an abandonment of the Contract, he
shall have no claim to payment of any compensation on account of any profit or advantage
which he may have derived from the execution of the work in full.
Bonus
• A bonus clause is a clause in a contract that rewards the contractor for doing more than
the letter of the contract; particularly, to finish the job early.
• It is in apposition to a penalty clause where the contractor loses by providing less than
the letter of the contract, or providing it later than agreed.
• The aim of a bonus clause whereby the contractor wins by getting more money for
finishing early.
• Normally, tenders shall be invited with reference to a pre-determined period of
completion of works. Provision of incentives for completion of work before schedule
should be sparingly made after careful assessment of tangible benefits therefrom and
disclosed in the tender documents in clear monetary terms
Liquidated damages
• Generally liquidated damages are agreed upon sum of money to which government or
owner entitled in the event the contractor fails to perform as directed in the contract.
• This provision explicitly states that for each calendar day the work remains
uncompleted after the final completion date stated in the contract, the contractor shall
pay certain amount to the owner.
• In case of delay in completion of the contract, liquidated damages should be levied at
a specified rate of the contract value, subject to a maximum of 10% of the contract
value.
• The penalties proposed for identified lapses must be disclosed in the tender
documents in clear monetary terms.
• Bonus:
1% of the contract value per month subject to a maximum of 5% of contract value.
• Liquidated Damages:
For repair works costing up to Rs. 10 Lakh - 1% of the contract value per week and
for all other works 0.5% of the contract value per week of delay subject to a
maximum of 10% of contract value
Measurement and payment
• Measurement of work done shall be taken in accordance with the relevant standard method of
measurement published by the Bureau of Indian Standards (BIS) and if not covered by the
above, other relevant Standards/practices shall be followed as per instructions of the
Engineer-in-Charge.
• Measurements of all items having financial value shall be recorded in Measurement books
and/or level field books so that a complete record is obtained of all works performed under
the contract.
• Measurements shall be taken jointly by the official designated for the purpose and the
contractor.
• In case the contractor or his authorized representative does not attend to the joint
measurements at the prefixed date and time after due notice, the measurements taken by the
Engineer-in-Charge or his representative shall be final and binding on the contractor.
• If the contractor objects to any measurements, a note to that effect shall be made in the
Measurement Book / Log Book and signed and dated by both the parties.
• No work shall be covered up or put out of view without the approval by the Engineer-in-
Charge and recording of measurements and check measurement thereof duly accepted by the
contractor.
• The contractor shall provide full opportunity to the Engineer-in-Charge or his representative
to examine and measure all works to be covered up.
Payments
• Intermediate bill shall be submitted by the contractor every month for the work executed on
basis of recorded measurements.
• Running on account bill/bills for the work executed/ materials supplied in accordance with the
work order/ contract shall be prepared on the basis of detailed measurements recorded as
described and processed for payments.
• The work executed as covered by the bill/bills after deducting the amount already paid, the
security deposit and such other amounts as may be deductible or recoverable in terms of the
work order/ contract.
• Extra items of work executed will be paid on specific written authorization of GM of the
company or Staff Officer (Civil) of the Area provided that the value of such extra items of
work when added together is not more than 10% of the contract value.
• Balance amount on account of excess quantity and extra items of work executed shall be paid
after the deviation estimate / revised estimate regularizing the extra items and excess
quantities of work is sanctioned by the competent authority of the company with the
concurrence of the Finance Department of the company.
• The payments shall be released against the final bill subject to all deductions which may be
made on account of materials supplied, water supply for construction, supply of electricity
and any other dues payable by the contractor to the company.
Breach of contract
Contracts are made for being performed. But there are certain circumstances when one of the parties
does not perform his part of the contract. Non performance is called breach of contract
Types of breaches :
1. Actual breach
2. Anticipatory breach
1. Actual breach :
• On due date either of the party refuses the performance of the contract.
• Refused party is liable to pay damages to the other party.
Example : Suppose ‘A’ agrees to supply 1000 units of materials to ‘B’ at 100 Rs each. On due
date A refused to supply goods. Now ‘A’ is liable to pay damages to B. Suppose on due date
market value of the materials raises to 120 Rs/unit, ‘A’ has to pay extra 20 Rs/ unit to ‘B’. i.e.
1000X20=20000 Rs
2. Anticipated breach :
• When a promisor refuses to perform his promise leading to an anticipatory breach of
contract he can either:
Treat the contract as canceled and file a suit against the other party for damages arising from
the breach. This suit can be filed immediately without waiting until the date of performance
specified in the contract.
OR
Choose not to cancel the contract but treat it as operative and wait until the time of
performance has passed before holding the other party responsible for the damages caused
due to non-performance. However, he will need to keep the contract alive for the benefit of all
parties involved.
Example for anticipatory breach :
Suppose ‘A’ is supposed to supply 1000 units of materials to ‘B’ at 100 RS/unit om 30th Nov.
Now on 10th oct. A refused to supply materials to B (before due date), B has two options:
1. To terminate the contract immediately : suppose on 10th oct the price of materials is 125 Rs
/ unit, A is liable to pay extra 25 Rs/unit (i.e. 25x1000=25000 Rs) to B.
2. To keep contract alive :
Case i : On 30th Nov (On due date) if price of material increases to 140 Rs/ unit, then A is liable to
pay extra 40 Rs/ unit (1000x40=40000 Rs) to B.
Case ii : On 30th Nov ( on due date) if the price of material reduces to 80 Rs/unit, the B is bound to
accept goods at 100 Rs/ unit from A.
• In first stage dispute shall be referred to Area GM or GM/HoD. If difference still persist
the dispute shall be referred to a committee constituted by the owner. The committee
shall have one member of the rank of Director of the company who shall be chairman of
the committee.
• If differences still persist, the settlement of the dispute shall be resolved in the following
manner:
✓ Disputes relating to the commercial contracts with Central Public Sector Enterprises /
Govt. Departments / State Public Sector Enterprises shall be referred by either party
for Arbitration to the PMA ( Permanent Machinery of Arbitration ) in the department
of Public Enterprises.
✓ In case of parties other than Govt. Agencies, the redressal of the dispute may be
sought in the Court of Law.
Contract management
✓ Contract management or contract administration is the management of contracts made
with customers, vendors, partners, or employees.
✓ The personnel involved in contract administration required to negotiate, support and manage
effective contracts are often expensive to train and retain.
✓ Contract management includes negotiating the terms and conditions in contracts and ensuring
compliance with the terms and conditions, as well as documenting and agreeing on any
changes or amendments that may arise during its implementation or execution
✓ It can be summarized as the process of systematically and efficiently managing contract
creation, execution, and analysis for the purpose of maximizing financial and operational
performance and minimizing risk.
VALUATION
Valuation is the technique of estimating or determining the current fair price or value of a property
such a building, a factory or other engineering structures of various types, land etc.
Purpose:
Definitions
• Gross income : total income or reciept from all sources without deducing outgoings
necessary for taxes, maintenance, collections charges.
• Net income : this is the saving or amount left after all outgoings, operational and
collection expenses from the gross income
net income = gross income – outgoings
• Outgoings : outgoings are the expenses which are required to be incurred to maintain
revenue of the building.
The various outgoings are :
1. taxes: municipal tax, property tax, wealth tax etc
2. Repairs:
3. Management and collection charges : An agent collects rent for big buildings . Charges
varies from 4 to 5 %. This include investigation of petty complaints and supervising
petty repairs. Does not include liftman charges, sweeper, pump attendant, electric
charges for common lights etc
4. Sinking fund : it’s amount which has to be kept aside at fixed intervals of time (say
annually) out of gross in come so that at the end of useful life of building or property,
fund should accumulate to the initial cost of property
5. Loss of rent : the property may not be kept fully occupied in such a case, a suitable
amount from gross rent should be deducted under outgoings
6. Miscellaneous : electric charges for running lift, pump, for lighting etc.
• Scrap value : it is the value of dismantled materials. For a building when its life is over,
dismantled materials such as steel, brick, timber etc will fetch certain amount which is
scrap value of building. On rare occasions, scrap value may be zero or sometimes
negative when the cost of dismantling becomes more than scrap value.
• Salvage value : value at the end of its useful life without being dismantled. This is
generally accounted by deducting the depreciation from new cost.
• Depreciation : decrease or loss in the value of property due to structural deterioration,
use, life wear and tear, decay and obsolescence.
Comparison of scrap value and salvage value :
2. Scrap value is counted in the calculation of 2. Ordinarily the salvage value factor in the
depreciation of property at the end of useful calculation of depreciation is omitted.
life.
3. Scrap value of an asset is merely sale of 3. Salvage value deposition may take the form
scrap. of a sale of the asset to a purchaser who will
continue to use it for the function for which it
was originally designed
• Market value : amount which can be obtained at any particular time from the open
market if property is put for sale. The market value differ from time to time depending
on the demand and supply
• Book value : Amount shown in account book after allowing necessary depreciations.
The book value of a property at a particular year is the original cost minus amount of
depreciation up to the previous year. The book value will go on reducing year to year
and at the end of utility period of the property, the book value will be only scrap value.
Comparison of book value and market value:
2. The value may be higher during 2. The value cannot be higher during
subsequent years due to increase in price subsequent years due to increase in price
index index
3. The value may be constant for a period 3. The value cannot be constant, rather there
is a gradual fall
6.Depends on demand and supply, 6. Not variable due to its demand and
development of area supply, development of area
• obsolescence : the value of the property or structures become less by becoming out of
date in style, in structure, in design etc and this is termed as obsolescence.
• An outdated building with massive walls, arrangement of rooms not suited in
present days and for similar reasons, become obsolete even if it is maintained
very good condition and its value becomes less.
• An obsolescence may be due to as such progress in arts, changes in fashion,
changes in planning ideas etc
• Obsolescence may be
1. internal obsolescence due to
✓ Poor , odd or eccentric original design
✓ Change in kind of construction
✓ Change in utility demand
2. External obsolescence :
✓ poor original location
✓ Change in the character of district
✓ Specific detrimental influences such as due to construction of factories, stock
yard, traffic locations and noises etc
✓ Zoning laws.
• Annuity : is the annual periodic payments for repayments of capital amount invested
by a party.
• Capital cost : it is the total cost of construction including land, the original total
amount required to posses a property. It is the original cost and does not change
• Capitalized value : It is the sum or amount, the interest on which at highest prevailing
rate would be equal to net income of the property. To know the capitalized value of
property, it is required to know the net income from the property and the highest
prevailing rate of interest.
• Year’s purchase: it is the capital sum required to be invested iorder to get annuity of
Rs. 1 at certain rate of interest.
100 100
Year’s purchase = 𝑅𝑎𝑡𝑒 𝑜𝑓 𝑖𝑛𝑡𝑒𝑟𝑒𝑠𝑡 = 𝑖
Where
S = total amount of sinking fund to be accumulated
n = No. of years required to accumulate sinking fund
i = rate of interest in decimal (ex : 7% = 0.07)
I = annual instalment required
Depreciation :
Depreciation may be defined as the decrease or the loss in the value of a property due to
structural deterioration, use, life wear and tear, decay and obsolescence. the value of a property
or a building is gradually reduced due to its use, life, wear and tear etc and a certain percentage
of total cost may be allowed as depreciation to determine the present value.
The value of a property can be calculated after deducing the total amount of depreciation from
the original cost.
Types of depreciation:
1. Physical depreciation :
i. Wear and tear from operation
ii. Decrepitude i.e. action of time and elements.
2. Functional depreciation :
i. Inadequacy or suppression
ii. Obsolescence
3. Contingent depreciation:
i. Accidents due to negligence, elements and structural defects
ii. Diseases (parasites, pollution of water etc)
iii. Diminution of supply (natural gas, water etc)
Methods of calculating depreciation:
1. Straight line method:
In this method the property is assumed to lose value by a constant amount every year
and thus fixed amount of original cost is deducted every year, so that at the end of utility
period, only the scrap value is left.
𝐶−𝑆𝑐
Annual depreciation =
𝑛
where C = original cost
Sc = scrap value
n= life of property in years
2. Constant % method:
In this method, the property is assumed to lose its value annually at constant percentage
of its value (or book value)
𝑆𝑐
The percentage rate of annual depreciation, P =( )1/𝑛
𝐶
Where C is the original cost
Sc = scrap value
n=life of property in years
By constant percentage method, at the end of first year, the value of the property = C
(1-P), at the end of the second year = C(1-P)2 and so on
The above formula does not hold good when Scrap value Sc= 0
3. Sinking fund method:
In this method, the depreciation of the property is assumed to be equal to annual sinking
fund plus + interest on the fund that year.
𝑖
Annual sinking fund to provide for Re 1/- in ‘n’ years = (1+𝑖)𝑛−1 = x say
(1+𝑖 𝑛 )−1
An amount of Rs 1/- per annum in years = = 𝑦 𝑠𝑎𝑦
𝑖
Therefore rate of depreciation in years in “n” years = x+y %
I = rate of interest expressed in decimal.
4. Quantity survey method :
In this method, the property is studied in detail and loss of value (1 + 𝑖)due to life ,
wear and tear and decay, obsolescence etc worked out. Only experienced valuer can
workout amount of depreciation and present value of a property by this method.
Difference between depreciation and obsolescence :
Valuation of building :
• Valuation of building depends on type of building its structure, durability, size,
shape, width, width of roadways, quality of materials used in construction etc.
• A building located in market area will have higher value than similar building
in residential area.
• The building area having sewer, water supply and electricity will have high
valuation
• The valuation of building is determined by working out its cost of construction
at present day rate and allowing suitable depreciation.
• Before valuation, the age of building should be obtained from record or by
enquiries from visual inspection and its future life should be ascertained.
The following are the methods of valuation :
1. Rental method valuation
2. Direct comparison with capital value
3. Valuation based on profit
4. Valuation based on cost
5. Development method of valuation
Factors which affect value of property:
1. forces of demand and supply : few buyers as compared to a number of number of
properties available in a locality will result in lowprices for the property and vice versa
2. rise in population : rise in population due to growth of new industries will result in
heavy demand for land, building and properties
3. cost of construction : the present cost of construction affects the value due to rapid
change of price index in comparison with rate of depreciation
4. rent control act : the value of a property is calculated from its probable income through
rent. But rental value of a tenanted property in areas subjected to rent control act may
not reflect the value of similar property unencumbered by rents as rents are artificially
freezed while price of land, labour and building materials have been increasing
continuously, this may cause slump in property values.
5. the imposition of control of prices of building materials : this will cause violent
fluctuations in prices of building materials and the values of buildings may vary by an
appreciable amount from time to time
6. improvement of public schemes: the taking up of any public service scheme, like sewer
line, waterlines, means of transport etc to an area lacking in modern amenities will tend
to make the area more attractive and will be closely followed by an increase in land
values
7. interest on schedule banks or government securities : by lowering the schedule bank
interest or the government security, higher may be money available for investment in
property and vise-versa
8. abnormal condition: due to increase in conditions like riots, war trend etc. value may
drop and remain so for a considerable period.
Mortgage :
Cost :
• Cost means the original cost of construction and can be known after accounting all day
to day expenditure from the very planning stage till the construction is completed
• The cost of an old building becomes less due to its age and changes in fashion
• For valuation, cost of old building is worked out from the present cost of construction
of such a new building less the calculated amount of loss of building due to wear and
tear.
• But infact the cost may not be the actual cost of construction for such type of new
building.
• This is an estimate prepared by calculating quantities of various items from the
measurement of existing old building and multiplied by the present unit cost of item
concerned.
• From the estimated cost, a calculated amount is deducted according to the age of
building.
Difference between cost and value:
o Occupational lease :
o Sublease :
A leaseholder may render subbase of his leasehold property to the persons subject to terms
and conditions in the original lease and allowed by the local regulations or court of law. In
this case, the original leaseholder is named as “assignment of lease” and the sublease holder
is called “sublease”
o Life lease :
when the duration of the property is given until death of a person or persons this is called
life lease
o Perpetual lease:
when the lease of a property is given for number of years providing the condition that lease
is renewed time to time ( renewed after the agreement period is over), even for endless time
according to the desire of the lease holder such type of lease is called perpetual lease.
Valuation of land:
Valuation of open land may be done by any of the three methods as and where applicable.
a. Comparative method
b. Belting method
c. Hypothetical building schemes
a. Comparative method : the simplest and most direct method of valuation is direct
comparison. The method is based on instances of other sales with dates of open
comparative like lands in the neighbourhood. So there are two main factors based on
which this method is based
• Sale prices : sale prices should be recent so that there is no rise in value of land during
intervening period of comparison
• This method is based on based on comparison of like to like. Properties may be similar
but each property is unique so that they can never be like. However the value of
particular plot by analysing the following factors:
i. Situation : value of land which is situated in the business and commercial locality
will be higher than lands which can be only used for residential purposes. Land near
closeness to schools will have higher value than slum areas due to existence of
bustees, factories, burning ghat etc.. The comparative value of land may be adjusted
by comparing expected rent per sq m for such variation of locations
b. Belting method of valuation :
c. Hypothetical building schemes :