PART 3
• TOPIC: CONTRACT
IMPLEMENTATION
TOPIC OUTLINE :
• Advance Payment
• Progress Payment/Billings
• Suspensionof Work
• Extension of Contract Time
• Variation Orders
• Final Payment
• Liquidated Damages
• Retention
• Other Topics
Advance Payment
• The PROCURING ENTITY shall, upon a written request of the
Contractor which shall be submitted as a contract document,
make an Advance Payment to the Contractor in an amount not
to exceed fifteen percent (15%) of the total Contract Price, to be
made in lump sum or, at the most, two installments according to
a schedule specified in the Instruction to Bidders and other
relevant Tender Documents, to wit:
advance payment
• The Advance Payment shall be made only upon the submission by the
Contractor to and acceptance by the PROCURING ENTITY of an
irrevocable standby letter of credit of equivalent value from a
commercial bank, a bank guarantee or a surety bond callable upon
demand, issued by a surety or insurance company duly licensed by the
Insurance Commission and confirmed by the procuring entity.
Note:
•The Government
•The Contractor
The Government may suspend the work
wholly or partly due to:
On any of the following grounds, the PROCURING ENTITY shall have
the authority to suspend the Works, wholly or partly by written order
for such period as may be deemed necessary:
• Where the reason given by the Contractor to support its request for
time extension is bad weather, particularly rainy/unworkable days
whose actual number as verified by the PROCURING ENTITY’s
Representative does not exceed the expected average number of
such days for the particular month in the vicinity of the Site as
stated in the SCC; the said expected number of days is based on
the records of the Philippine Atmospheric Geophysical and
Astronomical Services Administration (PAGASA), and was already
considered by the DPWH in determining the Contract Time during
the detailed engineering and the preparation of the Bidding
Documents (BDs) for the project.
No extension of Contract Time shall be
granted to the Contractor on the
following grounds (Cont.):
• All contracts executed in accordance with the Act and this IRR shall
contain a provision of liquidated damages which shall be payable by
the contractor in case of breach thereof for the procurement of
infrastructure projects in an amount as above-mentioned.
• Contract Completion
• Acceptance
• Taking Over
• As-Built Drawings
Contract Completion