Professional Documents
Culture Documents
Of Construction Projects
➢ Introduction
➢Case – Reports
➢Contract Administration
➢Prebid Meeting
➢ Conditions of Contract
➢ Quality Control
Introduction
• Budget sanction.
• Land acquisition
• Feasibility
• Investigation.
• DPR
Introduction
• Technical sanction.
• Bidding process based on standard
procurement norms. In transparent and fair
manner.
• Contract administration and management.
• Defects liability period.
• Alternative disputes resolution.
Introduction
• Road works are done by M/s. XXXXXXXX and Utilities are done
by M/s XXX
• Utility Crossings, Storm water drain is also incorporated in the
works. Power duct is also included in these works which got
delayed in road packages.
• Lack of coordination between two working groups even though
XXX is the agency involved in both works.
• EPC agency – M/s. XXX took long time in finalizing the designs as
the designs are complex in nature, depending upon the layouts
and clash analysis of various utilities.
Case Report-2
• Administrative
• Legal
• Technical Particulars, Specifications, Quality,
Drawing
• Communication-Correspondence
• Authority
• Financial Instruments
Contract Administration - Role
• Workmen-Health-Safety
• Statutory Compliance
• Risk Management
• Documentation
• Precedence –Schedule-Drawing-PS-Code
• Hierarchy
Contract Administration - Role
• Standards
• Protocol
• Reporting
• Governance
• Transfer/Handing Over/Occupancy
• Defects Liability
Contract Administration - Role
• Regulation
• Dispute Resolution
• Appellate Authority
• Jurisdiction
• Methods
• Registers
Contract Administration - Stages
• Appraisal
• Sanction
• DEPMC – Investgn.-DPR-Procurement-
Construction-DLP-Arbitration
• Construction Contract – Site Enabling-Execution-
DLP
• JV/Consortium/Collaboration/Coordinated Works
Contract Administration - Stages
• Owners Engineer
• Program Management
• Independent Engineer
• QC-QA
• Facility Management
Contract Administration - Functions
• Minutes of Meeting
• Notice of Virtual Completion
• Extension of Time – EOT With Costs, Without
Costs, With Penalty
• Renewal of Bank Gaurantees
• Contract Signing authority
• Contract Operating authority
Contract Administration - Functions
• Owners Engineer
• Independent Engineer
• Project Manager
• Risk & Cost Contract
• Claims & Settlement
• De-Scope
Contract Administration - Functions
• Deemed Termination
• Nominated Subcontract in EPC
• Design Approval in DB Contract
• Deviation from Design Brief
• Intermediate Mile Stones & LD cause
• Incentive Clause for early Completion
Contract Administration - Functions
➢Name of Project
➢Scope of Work
➢Period of Completion
▪ Gist of Contract
▪ Conditions of Contract
ISSUE OF TENDER DOCUMENTS
a. Safety Code
b. Health Code
c. Insurance Cover
d. Labour Laws
e. Quality Check
▪ Credentials
ISSUE OF TENDER DOCUMENTS
▪ Arbitration
▪ Bill Of Quantities
▪ Drawings
ISSUE OF TENDER DOCUMENTS
PRE BID MEETING
▪ Scope of Work
▪ Rates
▪ Payments
▪ Performance Guarantee
– PF & ESI
– Labor License
CONDITIONS OF CONTRACT
▪ Access to Work
– Any of the Consultants, Specialist Consultants,
Representatives of Consultants and the Employer shall at all
reasonable time have free access to the work-spots,
workshops, factories or other places from where materials are
being procured or manufactured for the Contract. And also
they shall have access to any place where the materials are
lying or from which they are being obtained. The Contractor
shall give every facility to them and their representatives
necessary for inspection and examination and test of the
materials and workmanship. The work during its progress can
also be inspected by Technical Examiner
CONDITIONS OF CONTRACT
▪ Dismissal of Workmen
▪ Time of completion
• (a) the day two weeks from the date of issue of work
order;
▪ Assignment
▪ Sub Contractors
▪ Sub Contractors
▪ Measurements of Works
– Wherever not specified in the Schedule of Quantities or
elsewhere, the mode of measurements shall be in accordance
with the latest brochure issued by the Indian Standards
Institution of ‘Method of Measurements of Building Works’.
– Should the Contractor not attend or neglect to send such
agent, then the measurements taken by the Employer shall be
final and binding and the Contractor has no right to question
such measurements and calculations.
CONDITIONS OF CONTRACT
If the Contractor
▪ Statutory Regulations
▪ Statutory Regulations
▪ Quoted Rates
▪ Quoted Rates
▪ Extra Items
▪ Extra Items
▪ Testing of Materials
▪ Site Registers
▪ Permissions
▪ No Payment
SAFETY CODE
SAFETY CODE
working neighborhood.
CONDITIONS OF CONTRACT
it is in use.
place of work.
Consultants.
CONDITIONS OF CONTRACT
Contractor.
HEALTH CODE
HEALTH CODE
▪ Drinking Water
▪ Land
INSURANCE POLICY
– Fire
LABOUR LAWS
LABOUR LAWS
QUALITY CHECK
– Quality of not only the finished items but also the quality of each
ingredient of the component has to be checked. If any defect is
noticed, it shall be removed / rejected and relied / replaced with the
cost of the contractor.
CONDITIONS OF CONTRACT
QUALITY CHECK
– All the materials, which are received to site for the purpose of
execution of the project, are to be checked for their quality and
suitability. The materials shall be conformed to the specifications
incorporated and shall be as per the Codes and Standards.
– Frequency and periodicity of the tests for each item and material
shall be as per the codes and standards. All the concerned tests
shall be conducted if the batch number, source of receipt, brand of
item etc. is changed. The Contractor on demand shall carry out
additional tests and / or additional number of tests.
REGISTERS
– The transactions made in the Project site in respect
of Execution shall be maintained in the form of
Registers.
– Day wise and item wise transactions along with
cumulative figures shall be maintained in respect of
each item of work and material.
CONDITIONS OF CONTRACT
REGISTERS
– 5. Register of Abnormally Hi/Low rates & up to date quantities paid in running bills
– 6. Deviation Statement
– 11. Consumption of Anti termite, Water Proofing chemical, Bitumen, Lead, Mastic Pads, etc.
ARBITRATION
Thank You
ANY QUESTIONS ?
Please Mail to suryapp@yahoo.com
(or)
Call me +91 93933 48484