Daily Activities Report 8-11-2017 PDF
Daily Activities Report 8-11-2017 PDF
Piping Activity
1 Continues weld stub tube 1 joint. 1 Start Tube Instaiiation fit up and weld (RHS top) 4 joint = team D 1 Continues tube RH fit up & weld inside boiler (LHS top) 6 joint
2 Continues Tube Instaiiation fit up and weld (RHS top) 8 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 6 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 6 joint
3 Continues cut on RH tubes inside of boiler (RHS top) Finish 3 Continues cut on RH tubes inside of boiler (Front left top) 30 joint 3 Continues cut on RH tubes inside of boiler (Front left top) 30 joint
4 Continues cut on RH tubes inside of boiler (Front left top) 50 joint 4 Continues tube RH fit up & weld inside boiler (LHS top) 6 joint 4 Start tube RH fit up & weld inside boiler (Front top) 4 joint (from middle first)
5 Continues tube RH fit up & weld inside boiler (LHS top) 8+4 joint 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top)
6 Continues spare part tube laydown area & Stock tube (for fit up Tube RHS/LHS top) 6 Continues machine beveling tube RHS/LHS top. 6 Continues machine beveling tube RHS/LHS top.
7 Continues machine beveling tube RHS/LHS top. 7 Preparation plate Try to fit up gride support LHS No.A06-14700-1101A (68 - 71) 7 Try to fit up gride support LHS No.A06-14700-1101A (68 - 71)
Total 59 59 37