Evacuation of Executive Corridor for IOM

Work done detail:


1. Shifting of Room no. 36 to Room no. 51

2. Shifting of Medical Record Files from Room 56 to Room 36

3. Shifting of Chairman Office Room 64 to Room 56

4. Shifting of Executive Secretary Office Room 63 to Room 57

5. Shifting of Maroof Trust Offices room 61, 62 to Room 59

6. Shifting of Lab Record from Room 68 to Silver Oaks in 2 trips

7. Shifting of Azam Sahab belongings from Room 66 to Silver Oaks in 3 trips

8. Shifting of Silver Oaks Record to Potohar Builders

9. Shifting of Living room items from Room 65 to Room 49

10. Shifting of Room VC Office, Room 69 to Room 1

Resources Utilized Source Qty Cost


House Keeping Staff MIH 2 for One day N/A
Shahzore Vehicle Silver Oaks For 2 days N/A
Labors Outsourced 3 for 2 days 4200
@700/day

Kindly Release the amount of Rs. 4200/- which has already been paid to

the labors