You are on page 1of 2

From Experience

how did you do that ?

Reinforced Concrete Tank Design


By Mark W. Holmberg, P.E.
Analysis

E
Reinforced concrete tanks have been used
for water and wastewater storage and treatment
Analysis of reinforced concrete slabs
for decades. Structural engineers are asked

R
and walls is a complex finite element
to design a variety of square, round, and
exercise. ACI 350 suggests three de-
oval reinforced concrete structures that may
sign aids that can simplify the analysis
be above, below, or partially below ground.

U
of liquid containing tanks:
Design of reinforced concrete tanks requires
Rectangular Concrete Tanks,
attention not only to strength requirements, t
righ Association, Figure 1: Commerce WWTP Aeration Screen, Walkway and
Portland Cement

T
but also to crack control and durability. The
1994Copy Hoist Bridge.
challenge for the structural engineer is to de-
Circular Concrete Tanks
sign concrete liquid containing structures that Details

C
Without Prestressing, Portland
will resist the extremes of seasonal temperature Proper detailing of reinforcing and joints
Cement Association, 1993
changes and a variety of loading conditions, has as much to do with durability of a liquid
Concrete Manual, U.S. Department of

e
U
and remain watertight. containing structure as properly applying the
Reclamation, 8th edition, 1981
Design and construction of the Bear Creek

n
The two Portland Cement Association (PCA) provisions of ACI 350 and correctly analyzing

i
Waste Water Treatment Plant (WWTP) Ex-
publications include coefficients for calculating the structure. End fixity of a section affects

R
pansion located in Hampton, Georgia and the

z
moments, shears, tension, and deflection for location and magnitude of maximum moments,
Commerce Georgia WWTP are used to illus-
a variety of aspect ratios and end conditions and joint location affects the amount of mini-

T
trate code requirements, tank analysis, design

a
of plate and circular elements. Engineering mum shrinkage and temperature reinforcing
details, and construction of liquid containing
judgment of the designer is required to select required. The PCA design tables include both

g
reinforced concrete tanks.

S
the proper design tables, detail sections to fixed and hinged base conditions. The com-

a
resemble the boundary conditions selected mentary states that either extreme is rarely
Code Requirements and recognize that ideal boundary conditions achieved in the field. The detail in Figure 2 is
are rarely achieved in the field. In addition, the typical for a hinged base condition and was

m
ACI 350-06 Code Requirements for Environ-
mental Engineering Concrete Structures extends engineer must recognize conditions, beyond used in several of the Bear Creek WWTP
the basic ACI 318 Building Code Requirements the limitations of the PCA data, that require structures. A compression type waterstop was
for Structural Concrete with additional service- special analysis. installed near the inside face of the wall. A
ability requirements for crack width control Liquid containing tanks often support heavy PVC bulb type waterstop is not practical at this
due to flexure, shrinkage of concrete, and tem- equipment requiring special design of equip- location due to the location of slab reinforcing.
perature movement. The commentary of ACI ment support and surrounding walls. The Prior to completing the Bear Creek WWTP
350 makes it clear that ACI 318 requirements structural engineer must obtain vertical and structures wall details, it was determined that
alone will not produce watertight structures. ACI vibration loads of equipment, and design for the maximum allowable length between con-
350 serviceability requirements include: possible restraint of temperature movement of struction joints would be 50 feet, and that
Reduced working load stresses, and supporting concrete. Grade 60 reinforcing steel would be specified.
requirements for size and spacing of Figure 1 is an example of equipment that Figure 3, from the PCA Circular Concrete Tanks
reinforcement restrains or induces temperature movement in Without Prestressing noted above, is a useful aid
Increased minimum reinforcement for the reinforced concrete structure. for proportioning shrinkage and temperature
temperature and shrinkage movement, reinforcing based on joint spacing. ACI 350
which is dependent on the grade notes that concrete sections over 24 inches
of reinforcing steel and the length thick must have shrinkage reinforcing at
between shrinkage dissipating joints each face based on a 12-inch thick section.
Waterstop requirements at all joints
Concrete mix design requirements Concrete
Increased cover requirements Specifying and supplying a concrete mix
compared to ACI 318 that minimizes shrinkage is critical to the
Commentary suggestions for use of durability of liquid containing structures.
shrinkage compensating concrete Concrete shrinkage is dependent on several
per ACI 223 factors, including cement content and aggre-
Properly designed, specified, and detailed gate. To insure that design assumptions are
structures applying the requirements of the valid, the engineer should specify shrinkage
ACI 350, along with engineering judgment requirements (0.04% to 0.03%), and that
and quality construction, should have a the concrete supplier provide shrinkage test
useful life of 50 to 60 years. results prior to approving the mix design.
Figure 2: Hinged Base Detail. Where large tank walls or slabs are required

STRUCTURE magazine 22 July 2009


bility of the structure. Almost all form systems
require through-wall form ties that create po-
tential for leaks, and weak planes where cracks
may occur. Proper concrete mix design and
appropriate add mixtures will assure that
concrete is easily consolidated. Proper cur-
ing of concrete will reduce the potential for
shrinkage cracking.
Figure 4 shows small temperature/shrinkage

E
cracks in the Bear Creek WWTP Aeration
Basin Tank wall located at form tie holes. The

R
contractor injected the cracks and applied
a specified waterproofing membrane to the
inside of the tank walls.

U
Figure 3: Minimum Temperature and Shrinkage Conclusion
t
igh of ACI 350 design require- Figure 4: Tank Wall Cracks at Tie Hole.

T
Reinforcement. y r
Proper application
p
Co
ments, appropriate structural details, properly
without expansion joints, shrinkage compen-
Mark W. Holmberg, P.E. is Vice President

C
sating concrete may be specified; however, the specified and supplied concrete, and quality
construction will assure long life for reinforced and Civil Manager for Heath & Lineback
structural engineer must account for concrete
concrete tanks that will be subjected to harsh Engineers, Inc. in Marietta, Georgia. Mark is
expansion movement.

e
U
environmental and use conditions. The structural also a member of the STRUCTURE Editorial
ACI requirements for hot and cold weather
engineer and the contractor must work together Board, representing CASE. He can be reached

n
concrete placement must be specified because

i
to produce reinforced concrete liquid containing at mholmberg@heath-lineback.com.
construction of a large project can take place

R
tanks that are as watertight as possible.

z
over a year or more. One concrete mix design
will not be adequate for all pour conditions.

T
Project Team
Construction

g a
Process Design Engineer and Construction Observation Stevenson & Palmer Engineers, Inc.

S
Structural Engineer Heath & Lineback Engineers, Inc.
Formwork, concrete placement and curing

a
Contractor Choate Construction
are obviously critical to the quality and dura-

m ADVERTISEMENT For Advertiser Information, visit www.structuremag.org

Your clients want bigger windows and


larger door openings. You want enough

When the design hits a wall,


wall space to make your designs work.
Our Steel Strong-Wall shearwalls
provide both. Available in widths as

make sure its ours. narrow as 12 inches, our engineered


and pre-manufactured walls have
some of the highest allowable loads
in the industrybetween two and
three times higher than our original
Wood Strong-Wall shearwalls. And
our Steel Strong-Wall shearwalls have
multiple uses, including standard
single-story, balloon framing and two-
story applications. For strong, reliable
and code-compliant shearwall solutions,
look to Simpson Strong-Tie to keep
your projects moving.

For additional information visit Balloon Framing


www.strongtie.com or call (800) 999-5099. Assembly

2009 Simpson Strong-Tie Company Inc. SSW09-S

Now 2006 IBC Code-Listed (ICC-ES ESR-1679)


SSW09_S_7_1-2x4_3-4.indd 1 STRUCTURE magazine 23 July 2009 6/12/2009 4:16:21 PM

You might also like