Professional Documents
Culture Documents
I
n the oil and gas industry, pressure the potential damage mechanisms and
integrity of a large horizontal vessel integrity is a major concern. After obtaining accurate results from non-
NGL (Natural Gas Liquid) internal and external inspections various destructive inspections. The methodology
vessel has been developed. anomalies or defects can be reported and used in this analysis consisted of five steps,
repairs could be required in order to restore viz.
The general analysis a pressure vessel to its original condition. (A) Creating a qualitative risk matrix and
procedure, stress analysis The first question for an engineer, operator selecting equipment that required a
or manager is: can we keep operating at this deeper analysis;
and remaining useful life
evaluation are described.
Recommendations for
dealing with anomalies
detected during assessment
are also presented. The
methodology employed can
be applied to other, similar,
pressurised vessels in the
oil and gas, chemical and
petrochemical plants.
Figure 1 The
methodology steps
Step A: Qualitative Risk Ranking Figure 3 Stress diagram of a large horizontal pressure vessel
In this first part a qualitative risk
analysis of the pressure equipment needed were assessed. To calculate the consequence was performed. The normal operational
to be performed. This would result in of a failure category basic safety aspects were pressure, operation temperature, liquid and
the deletion from the analysis of much reviewed, such as the volume enclosed, the shell weight were considered for the stress
equipment due to the low risk presented toxicity, risk of fire and explosion. In the analysis (see Figures 4, 5 & 6 ).
and some equipment would be considered case discussed here the large horizontal NGL
for other types of analysis. The rule of pressure vessel required a deeper analysis. Pressure vessel data
thumb was that 20% of the equipment Material: A516 Gr 70 N
would account for 80% of the risk, so the Step B: Assessment Thickness: 70 mm
idea was to focus on that vital 20%. In this Once the risk of equipment had been Insulated: Yes
particular study the qualitative risk presented determined qualitatively a deeper analysis Length: 31.000 mm
by equipment was calculated following the could be required or not, depending on the Diameter: 5.000 mm
standard specification from API 580 and API risk level assessed. A detailed analysis was
581 'Risk Based Inspection' [1,2], where the carried out for this particular pressure vessel.
risk is defined as the product of likelihood In this part of the procedure three technical
and consequence, e.g. aspects were reviewed, i.e.
Mechanical behaviour of the large
Risk = Likelihood x Consequence horizontal pressure vessel
v(a stress analysis)
For this analysis the large pressure Potential damage mechanisms
vessel had a low chance of suffering a failure, Maintenance strategy
but the consequences (fire and explosion)
were high, so the risk was medium. Figure 2
shows the qualitative risk of the equipment. Mechanical behaviour analysis
of the large horizontal pressure
vessel
Figure 4 Finite element model of pressure vessel.
The aim here was to
5 [Operating pressure 2.3 Mpa (23 bar)]
identify all critical sections
of the equipment: where
RISK the maximum stress was
4
High located; what types of stress
Probability
A key first step in managing the Type of damage Damage Behaviour Non destructive Inspection
safety and reliability of equipment is to mechanism technique effectivity
identify and understand the relevant damage External Loss CUI General, UT spot thicness Fairly effective
mechanisms. Correct identification is very Thickness Internal corrosion localized, pitting measurements (50%)
important when applying the risk-based Insulation visual
approach to the maintenance of process inspection +
equipment. The NDT technique employed thermography
needs to be appropriate to the nature of the inspection if
damage mechanism and its failure mode. water entrance is
Information on this may be found in API suspected
Recommended Practice RP 571, which
covers situations encountered in the refining Surface- Overload due to Visible Visual inspection Highly effective
and petrochemical industry in pressure breaking flaw and process condition deformation and liquid (90%)
vessels, piping, and tanks, and which deformation penetrant on
categorises the failure mechanisms as follows saddle support
[4] (high stress
Mechanical and metallurgical failure concentrations
Uniform or localised loss of thickness location)
High temperature corrosion
Environmental assisted cracking quantifying each potential damage Ultrasonic thickness measurements
In this part of the procedure material mechanism (identified in the previous step) and UT Scan B
construction, type of process fluid, design via non-destructive testing. Accuracy of the
construction practices (welding process, non- results was a key factor, so qualified and Internal ultrasonic thickness
destructive manufacturing report, codes) and trained personnel are required on site. measurements and Scan B were carried out on
operational condition are analysed. the large horizontal pressure vessel. Ultrasonic
Maintenance strategy
Once potential damage mechanisms
were identified a maintenance strategy based
on in-service and out-of-service (internal)
inspection was proposed (see Tables I and II).
Scan B is a technique
in which the results are
presented on a screen
type B, in which the
thickness cross-section
can be visualised.
Using this type of
ultrasound technique,
performed from
inside the equipment,
corrosion under
insulation (CUI)
could be detected
without removal of
insulation. a) Pitting corrosion in the bottom b) Pitting corrosion
A corrosion
rate of 0.04 mm/year
was determined from
ultrasonic thickness
spot measurements,
which also indicated
that there was no
corrosion under the
insulation (see Figure 7
bottom right opposite).
Liquid penetrant
inspection
Liquid
c) Pitting corrosion in the joint d) Pitting corrosion in the bottom
penetrant testing is
a non-destructive
method of revealing Figure 9 Pitting corrosion in the bottom of the pressure vessel
discontinuities that
are open to the
surfaces of solid and essentially non-porous detecting and examining a variety of surface life of a component. A damaged component
materials. A wide spectrum of flaws is flaws, such as corrosion, contamination, in may be acceptable at the present time, but
detectable regardless of the configuration the surface finish, and surface discontinuities its remaining life must be established. This
of the workpiece and regardless of flaw on joints. Visual inspection is also the assessment is needed to establish inspection
orientations. For this particular case liquid most widely used method for detecting intervals and a basis for reliability-based
penetrant inspection was focused on the and examining those surface cracks which inspection (RBI) and it will help to
weld seam located on the shell, between the are particularly important because of their determine the risk priorities relative to other
saddle supports (see Figure 8) and looking relationship to structural failure mechanisms. plant that needs to be opened during the
for anomalies that can develop in-service or In this case an internal visual next turnaround.
during the erecting phase. inspection was carried out. During the For this particular case the remaining
internal inspection pitting corrosion in the life was calculated as recommended in API
bottom of the pressure vessel was detected 510 and pitting corrosion was evaluated as
Visual inspection (see Figures 9 (a), (b), (c) and (d) above). recommended in Chapter 6 of API 579 [5,
Visual inspection is a non-destructive 6]. Figure 10 shows the anticipated future
testing technique that provides a means of thickness reduction.
RL T actual T min
< 70.52 mm < 67.2 mm
83 years
CR 0.04 mm / year
Where
CR = Corrosion Rate
RL = Remaining Life Step 2: Determining the wall thickness
Tinitial = initial wall thickness (mm) (The as- used in the assessment using the equations
new thickness at first measurement)
Tactual = thickness (mm) measured during t c t rq < FCA
most recent inspection
Tmin = minimum thickness required t c 70.42 < 1.27 69.15 mm
by pressure or structural load, Figure 11 Pitting chart Grade 2. Actual damage state.
computed at the design stage
68 Thickness if
1. Rwt > 0.2 True (see Step 5)
67 2. RSF > RSFa True (see Steps 8 and 1)
Remaining life 83 years For the case concerned the pitting damage
66 Minimum was acceptable for the actual operating
Allowable condition, i.e. the MAWP of 4.4 Mpa.
65 Thickness
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 Step E: Root Cause Analysis (RCA)
The purpose of RCA is to identify and
Years understand the basic root of problems that
affect the equipment performance and its
Figure 10 Wall thickness reduction of large pressure vessel integrity. By understanding how anomalies
can originate these failures, or re-occurrence
of such problems in similar plant, can be
Fitness for service assessment
Step 3: Locating area on the component avoided in future. For this reason it is very
In this part of the procedure pitting that has the highest density (number of important, during pressure vessel inspection,
corrosion damage was evaluated applying pits) of pitting damage (using photographs to analyse every sign or evidence that can be
the Level 1 assessment procedures of Chapter including a reference scale). tested in laboratory.
6 of the API 579 code [6] which can be For the analysis reported here a
utilised to evaluate metal loss from pitting Step 4: Determining the maximum pit sample of corrosion product was taken from
corrosion. Pitting is defined as localised depth the pressure vessel bottom and subjected to
metal loss, and can therefore be characterised X-Ray diffraction analysis (which explores
by a pit diameter and a pit depth. The Level wmx 1 mm the sample's crystal structure). Sample results
1 procedure is simplified in that it does not are shown in Table III and Figure 12.
account for the orientation of the pit-couple
with respect to the maximum stress direction. Step 5: Determining the ratio of
Results are conservative and based on pitting remaining wall thickness
charts.
t c
FCA < wmx 69.15
1.27 < 1
Rwt 1.0039
Step 1: Determining the following
parameters
tc 69.15
D = inside diameter of equipment, Step 6: Determining the Maximum
5000 mm Allowable Working Pressure for the
Loss = thickness loss, 0.38 mm component using the Step 2 thickness
(70.8 70.42)
FCA = future corrosion allowance, 1.27 mm
RSFa = allowable (non-dimensional) 2 = S = tc 2 = 163 = 69.15
MAWP( Mpa ) 4.4 Mp
Remaining Strength Factor, 0.9 2 = Rc
t c 2 = (2500
1.27
0.38)
69.15
Trq = wall thickness (mm) measured at the
time of assessment