Professional Documents
Culture Documents
of Puerto Rico
Electrical Utilities
Agenda
Overview of PREPA
Capital Investment Program
• Transmission and Distribution
• Power Generation
Fuel Diversification Initiatives
• Natural Gas Projects
• Environmentally Friendly Projects
Conclusion
Questions
Overview of PREPA
PREPA is One of the Largest Public Utilities in the
United States
4
The System Includes Extensive Transmission & Distribution
and Significant Generation Capacity
2,992
(56%)
1,312
(24%)
MW
PREPA Maintains Excellent Business Relationship with
its Cogenerators
EcoEléctrica, L.P.
• Commercial operation: March 2000
• Contracted capacity of 507 MW
• Contracted guaranteed availability at 93%
– Actual availability was 93.4% for FY 2006
– Actual availability was 92.9% for FY 2007
AES
• Commercial operation: November 2002
• Contracted capacity of 454 MW
• Contracted guaranteed availability at 90%
– Actual availability was 93.5% for FY 2006
– Actual availability was 91.8% for FY 2007
Overview of Capital Projects
PREPA Has a $2.3 Billion Capital Investment Program
500 80.8
67.9
400 139.5 81.5
77.6 41.1
47.7 82.9
300 79.4
117.6 77.8
200 114.5 117.3
334.2 94.4
100 210.9
155.9 141.2 159.7
0
2008 2009 2010 2011 2012
G e n e r a t i o n T r a n s m i s s i o nD i s t r i b u t i o n O t h e r s
During the 2nd Quarter of 2007, PREPA completed the largest financial
transaction in its history. We issued $2.4 billion in the US tax-exempt bond
market to secure:
• $643 million to finance the Capital Investment Program
• Savings of $106 million from refinancing bonds
Transmission System Investments Will Improve Energy
Transfer and Reliability
New 115 kV
Line
Reconstructed 115
New 230 kV
kV Line
Line
Major Transmission and Distribution Projects
Accommodate Growth and Increase Reliability
230 kV lines ($mm)
Projects Cost Status
South Coast to Manatí $15.0 Study
South Coast – Cambalache $ 52.0 Study
South Coast – Aguas Buenas $ 65.0 Construction
Sabana Llana – Yabucoa $ 56.0 In Operation
Total $188.0
Gas insulated substation construction ($mm)
Projects Cost Status
Central Palo Seco $ 50.0 Construction
Luis Muñoz Marín Airport $3.9 Acceptance Test
Isla Grande Transmission Center $ 24.0 In Operation
Martin Peña Transmission Center $ 20.0 In Operation
Total $97.9
Underground systems construction ($mm)
Projects Cost Status
Fernandez Juncos – Phase II $8.0 Study
115 kV Circuit $175.0 Construction
Condado underground Project $3.2 Civil Construction
“Ponce en Marcha” – Phase II $17.0 Construction
“Ponce en Marcha” – Phase I $22.0 In Operation
Fernandez Juncos – Phase I $8.9 In Operation
Total $234.1
San Juan Underground 115 kV Circuit Mitigates Against
Disaster Events
Fifth Stage
COVADONGA Completion Date: TBD
PALO SECO Status: Under evaluation.
STEAM PLANT Route and environmental
ISLA GRANDE analysis started
165 VIADUCTO
5
SAN JUAN 2
Third Stage STEAM PLANT MARTIN Second Stage
Completion Date: October 2007 PEÑA Completion Date: Feb. 2008
Status: Partial Acceptance Test 22 22 HRTC Status: Construction—Contract
Awarded in June 2003. Awarded in April 2003.
167 23
Percentage Complete: 99% Percentage Complete: 90%
17 18
BTC 2 First Stage
1 Completion Date: October 2007
Fourth Stage 21 Status: Acceptance Test
Completion Date: Nov 2007 Awarded in May 2003.
174
Status: Acceptance Test MTC Percentage Complete: 99%
52
Awarded in September 2004. 20
Percentage Complete: 98%
• First four stages cost $175 million, including the cost of studies and design
• FEMA to provide funding of $75 millions
• Incorporates cross-linked polethylene cables (lessens environmental exposure)
Significant Power Generation Investment To Accommodate
Growth and Reliability
SAN JUAN COMBINED CYCLES
• Two units of 232MW each
• Expected completion date: December 2007
• Conversion to natural gas: 2010
8.00
• Long-term plan calls for
6.00
proportionate use of fuel oil,
4.00 natural gas and coal with
2.00 the incorporation of
0.00
renewable and alternate
Year energy sources
Fuel Oil No. 6 - PREPA Fuel Oil No. 2 - PREPA
Natural Gas - DOE Coal - DOE
Reference: EIA-Energy Review, PREPA
Fuel Oil
Fuel Oil Fuel Oil
73.1% 32.0%
49.7% Natural Gas
33.0%
Natural Gas
37.5%
Coal
Coal Natural Gas Renewables &
Coal 33.0%
13.6% 12.8% Renewables & Alternate
Renewables & Alternate 12.3%
Sources
Alternate Sources 2.0%
Sources 0.5%
0.5%
* Natural gas will substitute light oil which has a higher price.
In Addition to Natural Gas, PREPA is Also Considering Coal
and Renewable Energy Projects
• New 400 MW generating base plant located in Mayagüez – expected
start-up using natural gas in fiscal year 2013-14
• 3rd Priority - Gas pipeline to western plants: Gas turbines and 400MW
new plant
Peñuelas→Arecibo
Peñuelas→Arecibo
• Qualified personnel
• Markers
• Inspection (PIG launcher and PIG receiver)
• Control Room, Metering stations
• ROW limited to minor agricultural products
PREPA Is Also Evaluating Renewable Energy Projects
WIND ENERGY
• PREPA completed negotiations with two wind
farm developers for 40 and 50 MW projects
• Expected completion date: 2010
BIOMASS
• A biodiesel study in selected PREPA turbines
is in progress
• PREPA is evaluating waste-to-energy projects