Professional Documents
Culture Documents
Engineering Practice
API STD 521 [1] guidelines can be used corresponding to larger diameter pipes [1] are for pressure equipment, and
to determine the wetted surface area. associated with process equipment or equations mentioned in API STD 2000
Table 1 is a consolidated guideline for 1015% of the calculated wetted area [7] are for atmospheric and low pres-
wetted surface area to be considered, is to be considered in calculating the sure tanks. The box above provides a
based on available Refs. [1, 5 and 6] total wetted surface area for fire. summary of the key equations based
and engineering practices. Engineer- 2. Determination of heat absorp- on the API standard.
ing judgment, however, will be needed tion rate. Various empirical equations 3. Determination of latent heat of
by the design engineers in evaluating to calculate the heat absorption rate, vaporization. Before determining
the surface area exposed to fire. Q, are available in the literature; the the final relief rate, the engineer has
Since the associated liquid-filled appropriate equation based on appli- the important task of determining the
piping will also contribute to vapor cable conditions needs to be used. The latent heat of vaporization of the con-
generation, either the surface area equations mentioned in API STD 521 tained liquid.
44 CHEMICAL ENGINEERING WWW.CHE.COM JANUARY 2010
Engineering Practice
For equipment containing a single 4. Determination of relief rate. After calculated by following equation.
component liquid, the latent heat determining the of heat input, Q, the
of vaporization can be easily deter- relief rate, W, can be easily calculated P
mined based on relieving conditions. based on following simple equation: T1 1 Tn (8)
Pn
The relieving conditions are the re- Q
W 3, 600 (6)
lieving pressure and corresponding L Equipment that is internally insulated
boiling temperature. and contains a single phase (above
However, for vessels containing Equipment containing gases, critical point) at relieving conditions
multi-component liquids, determin- vapors or supercritical fluids has to be treated in the same manner
ing an accurate value of latent heat As mentioned above, the heat trans- as the equipment containing gases.
of vaporization is quite difficult. For fer between equipment walls and the
such vessels, composition of liquid and contained fluid is very poor when the Equipment containing
vapor changes as the lighter fractions contained fluid is a gas, vapor or su- low liquid inventory
evaporate early during fire. Relief rate percritical fluid. This results in a very -PXMJRVJEJOWFOUPSZ FRVJQNFOU DBO
and ultimately the relief device size rapid temperature rise in the equip- be defined as the equipment in which
calculation that is based on initial ment walls causing equipment failure all the contained liquid could vapor-
latent heat and other physical prop- due to heat stress even before the in- ize within 15 to 20 min. If the vessel
erties is not always conservative, ternal pressure reaches the set pres- pressure when the last drop of liquid
so a time-dependent model is recom- sure of a pressure-relief safety valve. vaporizes is less than the device set
mended by API STD 521 [1]. Section 5.15.4.1 of API STD 521 [1] pressure, then the relief load to be
With computer simulation programs clearly indicates that the pressure re- considered is based on the procedure
readily available to todays process de- lief device does not provide sufficient for gas filled equipment. However, if
sign engineers, latent heat of vapor- protection from equipment rupture. the vessel pressure when the last drop
ization can be easily and accurately The other means of protection for such of liquid vaporizes is more than relief
determined if proper care is taken vessels are as follows [1 and 13]: device set pressure, the relief load to
during the use of these programs. t$PPMJOHUIFFRVJQNFOUTVSGBDFCZB be considered will be the maximum of
Further information on getting con- water-water deluge system relief load calculated based on consid-
servative properties, including latent t1SPWJEJOH BVUPNBUJD WBQPS EFQSFT- ering liquid filled or gas filled vessel.
heat of vaporization with step-by step surizing systems Refs. [13 and 14] can be consulted for a
vaporization, can be found in Refs. t-PDBUJOHFRVJQNFOUTVDIBTUPFMJN- more detailed description and the re-
[6 and 15]. One simplified and fairly inate or reduce the effect of fire quired equations for such vessels.
conservative approach is to determine t*OTUBMMJOH FYUFSOBM GJSFQSPPGJOH
the relief device area, considering that insulation Equipment containing
the vessel is filled with a single com- t6TJOHSFMJBCMFGJSFNPOJUPSJOHTZTUFN high boiling liquids
ponent each time, and selecting the and a rapid-action fire-fighting team This equipment behaves similar to
maximum relief area among them. Even though it is unlikely that a that containing gases, and a pressure
This approach is widely used for mul- pressure relief device will protect the relief device is not likely to provide
tipurpose vessels typically used in equipment, the empirical equation to sufficient protection from equipment
pharmaceutical industries. determine the relief rate as suggested rupture. In order to protect equipment
In case computer simulation pro- by API STD 521 [1] for this type of in this situation, the design tempera-
grams are not available, Figure A.1. equipment is as follows: ture must be higher than the boiling
from API STD 521 [1] can be used for 1.25 temperature of the contained liquid at
single component paraffins, mixtures Aa Tw
T1 relieving pressure. This is very rare,
W 2.77 MP1
of paraffins that have slightly different T11.1506 (7) and hence, other means of protection
relative molecular weights, isomer hy- need to be used, as discussed above
drocarbons, aromatic compounds and This equation is modified to suit the for gas filled equipment. The relieving
cyclic compounds. The vapor pressure unit system used in this article and capacities, however, are determined
in this figure is the relieving pressure is based on various assumptions that based on thermal expansion if the
of the system, and correspondingly the need to be consider before using it. vessel is liquid full, and a procedure
relieving temperature and latent heat The temperature Tw is the recom- similar to those explained above are
is to be determined based on the aver- mended maximum wall temperature, adopted if the vessel is not liquid full.
age molecular weight of components. $
'
UIBUDBOCFVTFEGPS Refer to API STD 521, section 5.14 [1]
In case of relieving conditions near carbon-steel plates. The exposed sur- for calculating the relief load due to
the critical region, the latent heat of face area, A', is calculated in the same hydraulic expansion of liquid.
vaporization approaches zero as sen- way as the wetted surface area earlier,
sible heat dominates. For such condi- based on possible source of fire. Mixed phase relief
tions API STD 521 [1] suggests using a Relieving conditions in this case One of the significant problems that
minimum latent heat value of 115 kJ/ are the relieving pressure, as defined a process engineer needs to deal with
kg (50 Btu/lb) as an approximation. earlier, while relieving temperature is is to design the relief system in pres-
CHEMICAL ENGINEERING WWW.CHE.COM JANUARY 2010 45
Data:
Placement . . . . . . . . . . . . . : Horizontal
Vessel type . . . . . . . . . . . . : Cylindrical with
Engineering Practice ellipsoidal ends
Insulation . . . . . . . . . . . . . : None
Vessel radius R . . . . . . . . : 2.5 m
Vessel length (TL-TL) L . : 10.0 m ND 8 in. Sch 40
Vessel elevation. . . . . . . . : 1.0 m length 5.0 m
ent contingency for single phase (vapor the height between
Maximum initial liquid
or liquid) or for mixed phase (vapor- the vessel nozzle on Level H . . . . . . . . . . . . . . : 3.0 m
PSV-01
6Q8
liquid). Generally a mixed phase flow which relief valve is Fluid . . . . . . . . . . . . . . . . . . : Benzene
requires a larger relief area than vapor mounted and the liq- Relief valve set
or liquid phase flow. Traditionally it has uid level. If the fill pressure Ps . . . . . . . . . . : 3.5 barg
Vessel design ND 6 in. Sch 40
been assumed that relief is generally a level at relieving con- pressure PD. . . . . . . . . . : 3.5 barg length 1.5 m
vapor phase relief in the present con- ditions is above the
tingency. However, it has been found calculated minimum
that relief can be two-phase relief de- free-board height, V-01
pending upon the following factors: venting is to be consid-
1. Nature of liquid. It is the foamy ered as mixed phase 5m
3m
or non-foamy behavior of the liquid venting. The following
that results in the possibility of hav- equations from Ref.
ing mixed phases during pressure re- [10] are used to cal-
lief. It has been observed that relief culate the minimum
from non-foamy liquid is generally a free-board height. 10 m
1m
vapor phase relief. API STD 521 [1]
also says that a relief system need not
be designed for two phases for non-
foamy systems. However, it is not pos-
sible to predict the foamy behavior of (9) FIGURE 1. The vessel and data for Example 1
liquid from mere physical properties;
hence the conservative approach is to In this equation Ue is the entrainment EXAMPLE CALCULATIONS
consider the liquid as foamy whenever velocity known as the Kutateladze Two examples are illustrated here, one
there is doubt. A few guidelines to entrainment velocity [11] and is for a vessel containing liquid and an-
classify liquid as foamy are as follows: calculated from Equation (10). PUIFS GPS WFTTFM DPOUBJOJOH HBT $PN-
t-JRVJET IBWJOH WJTDPTJUZ HSFBUFS mercial simulation software is used to
than 100 cP generate the properties required. The
t-JRVJEDPOUBJOJOHTVSGBDUBOUT (10) absolute barometric pressure for both
t%JSUZMJRVJETDPOUBJOJOHTPMJET problems is assumed to be 1.0132 bar.
t.VMUJDPNQPOFOU MJRVJET XJUI XJEF
range of boiling points Fire duration Vessel containing liquid
t$IFNJDBMMZSFBDUJOHMJRVJET One of the aspects that has not been The first example concerns a horizon-
t-JRVJE XJUI NPSF UIBO POF MJRVJE discussed much in the standards is tal vessel containing benzene. The di-
phase the need to consider the duration of mensions and other data needed for
2. Initial fill level. Even though a fire and the present contingency to- UIFDBMDVMBUJPOBSFTIPXOJO'JHVSF
liquid might be non-foamy, it has been gether. Based on the duration for a fire Determination of wetted surface
observed that if the initial fill level fighting team to take an action against area. Ref. [12] is used to determine
in the vessel is above a certain level, present contingency, the fire duration the wetted surface area of partially
pressure relief can be mixed phase. can be ignored if vessel pressure at filled vessels. The wetted surface area
So far there are no well defined stan- the end of this duration is not going to of shell is given by
dards available above which mixed- reach the relief-valve set-pressure.
phase relief is to be considered. Guide- The duration for the fire fighting
lines as provided in Ref. [8] however team to take an action will depend (11)
can be used for non-reactive systems upon the complexity of the plant and
for low-pressure storage tanks. A con- should not be more than 1520 min
servative approach is to consider the [13]. This duration is based on the
two-phase relief when initial liquid fact that an un-wetted steel plate, 25 = 88.61 m2
level is above 20% for foamy liquids mm (1 in) thick, takes about 12 min to The wetted surface area of the two
and above 80% for non foamy liquids. SFBDI $
'
BOE NJO UP elliptical heads is given by Equation
However, small vessels having diam- SFBDI$
'
XIFOUIFQMBUF
TFF CPY
Q
XIFSF F is the
eters less than 3 m do require more is exposed to an open fire [1]. Hence, fractional liquid level (= H/2R) and E is
free board height. present contingency can be eliminated the eccentricity of the elliptical head (=
.BOZ SFGFSFODFT BSF BWBJMBCMF GPS for those vessels having vessel pres- 0.866 for the common case of a 2:1 el-
predicting the possibility of mixed sure at the end of 20 min, well below lipse). Entering the values into Equa-
phase behavior. One of the simplest the relief device set pressure. This du- tion (12) gives 31.10 m2. The wetted
approaches is as explained in Ref. [9]. ration of 20 min needs to be confirmed area for the vessel is therefore 88.61 +
This is based on calculating a mini- and mentioned in the relief system N2. The wetted area for
mum free-board height, h, which is design basis. the piping is assumed to be 10% of the
46 CHEMICAL ENGINEERING WWW.CHE.COM JANUARY 2010
Relief flowrate TABLE 5. EXAMPLE 2 DATA
43,000 Placement Vertical
38,000
Relief rate, kg/h
157
172
186
190
194
198
201
214
218
222
226
228
240
0
20
40
60
80
120
140
156
Time, min
Vessel elevation 2.0 m
Fluid Air
FIGURE 2. Simulation results for Example 1 showing the relief rate over time when
the vessel is engulfed in an external fire Relief valve set 7.5 barg
pressure, Ps
Equation 12 Normal operating 5.5 barg
pressure, Pn
Normal operating 35C
temperature, Tn
Maximum wall tem- 593C
perature, Tw
calculated wetted area, or 11.97 m2, so Determination of relief rate. Input- 2RL = 2(1)(6) = 37.70 m2
the total wetted area is 119.71 + 11.97 ting the values obtained above into The exposed surface area of heads is
= 131.68 m2. Equation (6), the relief rate, W, is the area of a sphere
Determination of heat absorption W = 3,600 Q/L
rate. Assuming that the facility has = 3,600 [(2,363.1)/347] 4R2 = 4(1)2 = 12.57 m2
adequate drainage and a fire fighting = 24,516 kg/h The exposed surface area for piping,
system in place and the vessel is de- A commercial simulation program is again assuming 10% of calculated
signed for 3.5 barg pressure, Equation available to simulate the vessel en- wetted area, is 5.03 m2. Therefore, the
(1) can be used here to determine the gulfed in external fire. Figure 2 is total wetted surface area is
heat input, Q: the vent flowrate for the above men-
tioned vessel with respect to time 37.70 + 12.57 + 5.03 = 55.29 m2
Q = 43, 200 F Aws
0.82
using such a program. This program Determination of relieving condi-
Q = 43,200 (1)(131.68)0.82 works in rating mode, and hence, the tions. The relieving pressure, P1 is
= 2,363,144 W details of safety relief valve and in-
1.21 x Ps (21% overpressure)
= 2,363.1 kW let-outlet piping as shown in Figure
= 9.075 barg
Determination of the latent heat of 1 are used to get the profile plotted
vaporization. Latent heat of vapor- in Figure 2. The relieving temperature, T1 , is de-
ization is obtained through commer- termined from Equation (8) to be
cial simulation software at relieving Vessel containing gas T1 = (P1/Pn)Tn
conditions, which are as follows. The data for this second example are = [(9.075 + 1.0132)/(5.5 + 1.0132)]
Relieving pressure = P1 listed in Table 5. (35 + 273.16) = 477.3 K = 204.1C.
= 1.21 Ps (21% overpressure) Determination of wetted surface
= 4.325 barg area: Equations from Ref. [12] are The relief rate, as determined from
Relieving temperature = T1 again used to determine the exposed Equation (7), is
= 145C (from simulation program) surface area of vessels. The exposed W = 2.77[28.84 (9.075 + 1.0132)]1/2
Latent heat of vaporization = L surface area of shell is the area of a {55.2[(593 + 273.16) 477.3]1.25/
= 347 kJ/kg (from simulation) cylinder with radius R. (477.3)1.1506}
W = 3,733 kg/h.
References: 9. Fauske, H. K. Properly Size Vents for Non-
reactive and Reactive Chemicals, Chem. Eng. Edited by Gerald Ondrey
1. Pressure-Relieving and Depressuring Sys- Prog., February 2000.
tems, ANSI/API Standard 521, 5th ed., Janu-
ary 2007. 10. Epstein, M., others, The Onset of Two-Phase
Venting via Entrainment in Liquid-Filled
2. Fisher, H. G., others, Emergency Relief System Storage Vessels Exposed to Fire, J. Loss Prev. Author
design using DIERS Technology, AIChE, 1992. Process Ind., 2 (1), p. 45, 1989. Santosh Arvind Katkar is
3. Sizing, Selection, and Installation of Pres- 11. Kutateladze, S. S., Elements of the Hydro- a process engineer at Jacobs
sure-Relieving Devices in Refineries, Part-I, dynamics of Gas-Liquid Systems, Fluid Me- Engineering Group Inc. (29,
API Standard 520, 8th ed., December 2008. chanics Soviet Research, 1, p. 29, 1972. International Business Park
4. Flammable and Combustible Liquids Code, #03-01, Acer Building, Tower
12. Doane, R.C. Accurate Wetted Areas for Par- A, Singapore 6009923.
NFPA 30, 2008 ed. tially Filled Vessels, Chem. Eng, December Phone: +65 6890 4967; Fax:
5. Ludwig, E. E. Applied Process Design, Vol- 2007, pp 5657. +65 6899 1619; Email: San-
ume 1, 3rd ed., Gulf Publishing, 1995. 13. Wong W. Y., Improve the Fire Protection of tosh.Katkar@jacobs.com). He
6. Wong W. Y., Fire, Vessels and Pressure Relief Fire Vessels, Chem. Eng., October 1999, pp. has over 8 years of experience
Valves, Chem. Eng., May 2000, pp. 8492. 193196. in petroleum refining, petro-
7. Venting Atmospheric and Low-Pressure 14. Mofrad S. R. others, Designing for Pressure chemical and other process
Storage Tanks, API Standard 2000, 5th Edi- Release during Fires Part 1, Hydrocarbon industries with leading engineering organiza-
tion, April 1998. Process, November 2007, pp. 6567. tions such as Fluor Daniel India and Lurgi India.
8. Fisher, H. G., and others, Protection of Storage 15. Mofrad S. R. et. al. Designing for Pressure He earned his M.Tech from Indian Institute of
Tanks from Two-Phase Flow due to Fire Expo- Release during Fires Part 2, Hydrocarbon Technology (Delhi) and B.Tech from University
sure, Process Safety Progress, July 1995. Process, December 2007, pp. 117121. Department of Chemical Technology (Jalgaon).