19 Masigla St., Quezon City, PH 1100 NGCP ZAPOTE SUBSTATION EXPANSION PROJECT
T: 02-928-5513 www.jeddtech.com
A. GENERAL INFORMATION
PROJECT NAME DATE OF TESTING
NGCP ZAPOTE SUBSTATION EXPANSION PROJECT MARCH 18, 2017
CLIENT NAME PROJECT OWNER
NATIONAL GRID CORPORATION OF THE NATIONAL GRID CORPORATION OF THE
PHILIPPINES PHILIPPINES
SUBSTATION NAME CLIENT P.O. NO.
230kV LAS PIAS SUBSTATION
TEST EQUIPMENT USED PROJECT ID NO.
CMC-256 plus
CT AND VT RATIOS
SECONDARY VOLTAGE AND CURRENT INJECTOR IED (4000:5 CT and 2000:1 PT reading)
INPUTS
Voltage Voltage Voltage Voltage kV kV kV kV
INJECTED
(25%) (50%) (75%) (100%) (25%) (50%) (75%) (100%)
SECONDARY VOLTAGE AND CURRENT INJECTOR HMI (4000:5 CT and 2000:1 PT reading)
INPUTS
Voltage Voltage Voltage Voltage kV kV kV kV
INJECTED
(25%) (50%) (75%) (100%) (25%) (50%) (75%) (100%)
SECONDARY VOLTAGE AND CURRENT INJECTOR IED (4000:5 CT and 2000:1 PT reading)
INPUTS
Ampere Ampere Ampere Ampere
INJECTED
(25%) (50%) (75%) (100%) (25%) (50%) (75%) (100%)
SECONDARY VOLTAGE AND CURRENT INJECTOR HMI (4000:5 CT and 2000:1 PT reading)
INPUTS
Ampere Ampere Ampere Ampere
INJECTED
(25%) (50%) (75%) (100%) (25%) (50%) (75%) (100%)
TESTED BY WITNESSED BY
SIGNATURE SIGNATURE
NAME NAME
Christopher R. Pabia Mike Alren M. Montes
POSITION POSITION
Testing and Commissioning Engineer Engineer SL, MTD-A, MRSS
SCADA, Power Automation
COMPANY COMPANY
JEDD TECHNOLOGIES CORP. NATIONAL GRID CORPORATION OF THE PHILIPPINES
DATE DATE
March 8, 2017 March 8, 2017
TESTED BY
SIGNATURE
NAME
Nathaniel B. Burgos
POSITION
Testing and Commissioning Engineer
SCADA, Power Automation
COMPANY
JEDD TECHNOLOGIES CORP.
DATE
March 8, 2017