Professional Documents
Culture Documents
R/3-System Release Enterprise 4.7: TPLM30
R/3-System Release Enterprise 4.7: TPLM30
Author:
Stefan Kroeger
TPLM30
September 2003
Case Study
Plant Maintenance
Instructor Guide
SAP AG TPLM30 Case Study
Contents:
SAP Contact(s)................................................................................................................. 3
Course Details .................................................................................................................. 3
Duration............................................................................................................................ 3
Course Materials and Other Materials ............................................................................... 3
Country-Specific Units ...................................................................................................... 3
Course Instructor Profile ................................................................................................... 3
Level of Knowledge Required ........................................................................................... 3
Training System................................................................................................................ 3
Work in IMG (Customizing) ............................................................................................... 3
User ID and Passwords for instructor ................................................................................ 3
User ID and Passwords for course participants ................................................................. 3
CATTs and Example ABAPs............................................................................................. 3
Technical Hints ................................................................................................................. 3
1. General Introduction ..................................................................................................... 3
2. Background information on Sport Motorcycle AG .......................................................... 3
3. Description of Sport Motorcycle AG Group .................................................................... 3
4. Basic Data in the System .............................................................................................. 3
5. Requirements in the Subject Areas ............................................................................... 3
Page 2
SAP AG TPLM30 Case Study
SAP Contact(s)
Walldorf
Stefan Kroeger
Ruediger Keilbach
Michael Wieland
Course Details
Duration
5 days
Case Study – 4 days
Monday, 10.00 to 17.00
Tuesday - Thursday 9.00 to 17.00
Certification – 1 day
Friday – depending on local schedule
Country-Specific Units
None
Page 3
SAP AG TPLM30 Case Study
Training System
Client
Only one client needed – all participants work in the same client
Data Required
Most data within Plant Maintenance will be created by participant during case study
Data within Materials Management required in Plant Maintenance (plants, storage locations,
materials, BOMs etc.) will be created by participant during case study
Data within Financial Accounting and Controlling (Controlling area, cost center, company code etc.)
will not be created by participant but rather used as offered by the IDES system. A hint is given for
every implementation step about which data to use.
Technical Hints
None
Page 4
SAP AG TPLM30 Case Study
General introduction
Background information on Sport Motorcycle AG
Description of Sport Motorcycle AG Group
Basic data in the system
Requirements in the subject areas
Maintenance Organization
Management of Technical Objects
Maintenance Processing
Preventive Maintenance
Controlling in Plant Maintenance
Optional (Reporting and analyses)
Note:
As participants work as project teams – and therefore at their own pace – there is no fixed
schedule for the different steps within the case study.
However, all project teams must have finished their work until mid-day of day four so that
presentations can take place in the afternoon of day four.
Page 5
SAP AG TPLM30 Case Study
Day One
Approximate Contents: Units and Topics
Times
Including
Exercises
30 min General Introduction
Background information concerning Sport Motorcycle Inc.
Day Four
Approximate Contents: Units and Topics
Times
Including
Exercises
until mid-day Implementation of requirements of Sport Motorcycle in the system - continued
Day Five
Approximate Contents: Units and Topics
Times
Including
Exercises
Certification
Page 6
SAP AG TPLM30 Case Study
1. General Introduction
Course Objectives
The course has two objectives:
1. Prepare junior consultant for his/her later work within a case study that allows
him/her to set up business processes in plant maintenance according to customer
requirements
2. Prepare junior consultant for certification
Page 7
SAP AG TPLM30 Case Study
General
Plant Maintenance
Cost center for technical
4110 Technical assets
objects
Class for oil pumps ED113 (class type 002 – equipment class)
Materials Management
Page 8
SAP AG TPLM30 Case Study
C1 - as new
Valuation types for refurbishment C2 - refurbished
C3 – defective
Page 9
SAP AG TPLM30 Case Study
Maintenance Organization
In this section it is essential to define the necessary plants with the required settings
and practice again the relationship between maintenance plant and planning plant.
As the definition of plants and storage locations has mainly to do with materials
management, the required steps and settings are available to participants.
Also, it is essential that the required work centers are defined with the necessary
settings and are assigned to the right plant.
Page 10
SAP AG TPLM30 Case Study
Equipments ?
BOMs ?
The following list contains the sequence of steps for creating a new plant and a
new storage location as areference for the instructor.
As the creation of plants and storage locations is not part of the PM courses the
instructor can give hints to participants. However, this should not be
demonstrated from the start. Participants should rather work on this
requirement first.
Page 11
SAP AG TPLM30 Case Study
Page 12
SAP AG TPLM30 Case Study
Maintenance Processing
In this section maintenance processing has to be set up according to the requirements
of Sport Motorcycle. That means that notification processing as well as order
processing has to be defined.
The maintenance processing part consists of the following parts:
- create new notification type ##
- assign necessary paramters to new notification type ##
- create new order type IH##
- assign necessary paramters to new order type IH##
- make existing order type (PM04 - refurbishment) available in the new planning
plant
- complete parameters for order type PM04 in the new planning plant
If questions arise in this part, the instructor guide of standard course PLM315 can be
used as a reference.
In more detail, the following data have to be created by participants:
Page 13
SAP AG TPLM30 Case Study
Page 14
SAP AG TPLM30 Case Study
Preventive Maintenance
In this section preventive maintenance has to be implemented according to the
requirements of Sport Motorcycle.
The central issue here is to properly schedule different maintenance plans.
In more detail, the following objects have to be created and the following
customizing steps have to be performed:
Page 15
SAP AG TPLM30 Case Study
Controlling in Maintenance
In this section the settings for costing and settlement of an order have to be made
according to the requirements of Sport Motorcycle.
This has to be done both for the new order type IH## as well as for order type PM04
(refurbishment).
Page 16
SAP AG TPLM30 Case Study
Page 17