You are on page 1of 1

    Client:  Petroleum Developement Oman

MARMUL CONTRACTING & TRADING COMPANY LLC. Mobilization Plan for Earthworks PDO North Oman - 24-May-14

Qarnalam
Activity ID Activity Name Original Planned Planned Month
Duration Start Finish 8
1 2 3 4 5 6 7
Mobilization Plan for Earthworks PDO North Oman - Qarnalam 173d 15-Dec-14 05-Jun-15 05-Jun-15, Mobilization Plan for Earthworks

Mobilization of Contract Key & Core Personnel 18d 15-Dec-14 01-Jan-15 01-Jan-15, Mobilization of Contract Key & Core Personnel
A1000 Notification for Key & Core Personnel 1d 15-Dec-14 15-Dec-14 Notification for Key & Core Personnel
A1010 HSE Tr aining for All Personnel 14d 16-Dec-14 29-Dec-14 HSE Tr aining for All Personnel
A1020 Mobilization of HSE Trained Per sonnel 14d 19-Dec-14 01-Jan-15 Mobilization of HSE Trained Per sonnel
A1030 PDO Assessment for Key & Core Personnel (If Required) 7d 26-Dec-14 01-Jan-15 PDO Assessment for Key & Core Personnel (If Required)
PDO Approval for Industrial & Residential Facilities 23d 02-Jan-15 24-Jan-15 24-Jan-15, PDO Approval for Industrial & Residential Facilities
A1040 Internal Inspection for Existing Industrial & Residential Facilities 4d 02-Jan-15 05-Jan-15 Internal Inspection for Existing Industrial & Residential Facilities
A1050 Renting / Leasing the Industrial & Residential Facilities 2d 06-Jan-15 07-Jan-15 Renting / Leasing the Industrial & Residential Facilities
A1060 Renovation of the Rented Leased Facilities 7d 08-Jan-15 14-Jan-15 Renovation of the Rented Leased Facilities
A1070 Arranging Water, Electricity & Waste Management from PDO 7d 15-Jan-15 21-Jan-15 Arranging Water, Electricity & Waste Management from PDO
A1080 PDO Inspection for the Renovated Facilities 2d 22-Jan-15 23-Jan-15 PDO Inspection for the Renovated Facilities
A1090 PDO Approval for the Inspected Facilities 1d 24-Jan-15 24-Jan-15 PDO Approval for the Inspected Facilities
Contract HSE & Quality Plans 8d 02-Jan-15 09-Jan-15 09-Jan-15, Contract HSE & Quality Plans
A1100 Submission of Contract HSE Plan 1d 02-Jan-15 02-Jan-15 Submission of Contract HSE Plan
A1110 Submission of Contract Quality Plan 1d 02-Jan-15 02-Jan-15 Submission of Contract Quality Plan
A1120 PDO Review of Submitted Plans 6d 03-Jan-15 08-Jan-15 PDO Review of Submitted Plans
A1130 Getting PDO Approval for the Reviewed Plans 1d 09-Jan-15 09-Jan-15 Getting PDO Approval for the Reviewed Plans
Mobilization of Vehicle, Plant & Equipments 133d 16-Dec-14 27-Apr-15 27-Apr-15, Mobilization of Vehicle, Plant & Equipments
A1140 Procurement/ Hiring of Vehicle, Plant & Equipments 120d 16-Dec-14 14-Apr-15 Procurement/ Hiring of Vehicle, Plant & Equipments
A1150 Fixing PDO Specifications 120d 16-Dec-14 14-Apr-15 Fixing PDO Specifications
A1160 Internal Inspection for the Vehicle, Plant & Equipments 120d 21-Dec-14 19-Apr-15 Internal Inspection for the Vehicle, Plant & Equipments
A1170 Mobilization of Inspected EVPs 120d 23-Dec-14 21-Apr-15 Mobilization of Inspected EVPs
A1180 PDO Inspection for the Vehicle, Plants & Equipments 120d 27-Dec-14 25-Apr-15 PDO Inspection for the Vehicle, Plants & Equipments
A1290 Getting PDO Approval for Inspected EVSs 120d 29-Dec-14 27-Apr-15 Getting PDO Approval for Inspected EVSs
A1300 Dispatch to Site Locations 120d 29-Dec-14 27-Apr-15 Dispatch to Site Locations
Mobilization of Construction Crews 172d 16-Dec-14 05-Jun-15 05-Jun-15, Mobilization of Construction Crew
Assigning Construction Crews 120d 16-Dec-14 14-Apr-15 14-Apr-15, Assigning Construction Crews
A1190 HSE Tr aining for the Constr uction Crews 120d 16-Dec-14 14-Apr-15 HSE Tr aining for the Constr uction Crews
A1200 Recruting / Hiring PDO Approved Permit Holders & Applicants 15d 31-Dec-14 14-Jan-15 Recruting / Hiring PDO Approved Permit Holders & Applicants
A1210 Assigning Crews for Individual Location / Activities 120d 16-Dec-14 14-Apr-15 Assigning Crews for Individual Location / Activities
Dispatching Construction Crews 162d 26-Dec-14 05-Jun-15 05-Jun-15, Dispatching Construction Crews
A1230 Earth Work Crews for Qarnalam Field 7d 26-Dec-14 01-Jan-15 Earth Work Crews for Qarnalam Field
A1240 Structure Work Crews for Qarnalam Field 7d 02-Jan-15 08-Jan-15 Structure Work Crews for Qarnalam Field
A1250 Earth Work Crews for Musallam Field 7d 04-Feb-15 10-Feb-15 Earth Work Crews for Musallam Field
A1260 Structure Work Crews for Musallam Field 7d 11-Feb-15 17-Feb-15 Structure Work Crews for Musallam Field
A1270 Road Work Crew for the Contract 7d 30-May-15 05-Jun-15 Road Work Crew for the Contract
A1280 Civil Crew for Concrete Precast Yard 7d 15-Jan-15 21-Jan-15 Civil Crew for Concrete Precast Yard
Engineering & Construction 7d 26-Dec-14 02-Jan-15 02-Jan-15, Engineering & Construction
A1310 Start of Engineering Activities 0d 26-Dec-14 Start of Engineering Activities, 26-Dec-14
A1320 Start of Construction Activities 0d 02-Jan-15 Start of Construction Activities, 02-Jan-15