Professional Documents
Culture Documents
https://www.copyright.com/ccc/basicSearch.do?
&operation=go&searchType=0
&lastSearch=simple&all=on&titleOrStdNo=0264-6811
Unitisation and
Redetermination:
Right or Obligation?
By Michael Polkinghorne*
This article deals with the issue of unitisation, the process by which licensees
of oil and gas reserves in a fieldstraddling different licences pool their individual
interests in return for an interest in the overall unit (which is then operated by
a single company on behalf of the group).' In many of these arrangements,
there is a subsequent opportunity for the parties to modify the relevant
participations by way of equity redetermination.
One thing the AIPN Study has demonstrated is the marked manner in
which the legal framework for unitisation varies from one country to
another. Thus, while the industry is developing its own ways and means to
deal with unitisation, in many countries the underlying legal framework is
still in its infancy.
This leaves a substantial degree of uncertainty, notably where the parties
are in fact unable to agree on whether, and if so how, to unitise. As will be
seen, it is highly unlikely that a given state's legal or regulatory framework
will provide much support or guidance on the issue. This means that - as
current practice confirms - it is really for the parties to agree as much as
they can in advance. And if not handled properly, the old truism that
arbitrations are illustrations of cases where there were too few lawyers at the
beginning of a contract and too many at its end could clearly apply.
Some questions, of course, arise before any agreement can be negotiated,
particularly where even the need to unitise is not known at the time of the
relevant petroleum agreement's conclusion. It is important to know what
right the state possesses to compel unitisation, and the means by which it
may do so. Extra care must be taken where there is a state partner to a
potential unitisation. If the neighbouring block is vacant, it may be critical
to determine whether the existing developer has any priority right to exploit
the same, or whether the state or its national oil company (NOC) possesses
such a right. And where a state has legislative or regulatory power to compel
unitisation, questions can arise as to the identity of the final arbiter of any
disputes arising out of the negotiation of the relevant agreement: the state,
its courts, an expert or an arbitral tribunal.
And once an agreement is finalised, the parties need to consider how
and when they can revisit the agreed terms. Contracts frequently provide
for redetermination of the parties' ownership interests, but provision needs
to be made for the situation where they cannot agree. Should they go to
expert determination, arbitration or both? If there is no provision for
redetermination, it is still important to know whether a party can nevertheless
seek redress where the parameters of the initial arrangement are found to
be wildly awry of the new situation.
3 See also Bede Nwete, 'Mitigating Redetermination Problems in Unitised Hydrocarbon Fields'
(2005) 9 IELTR 228.
Algeria
Algeria has recently brought on to its books a new Hydrocarbons Law, which
does in fact deal with this question.' On the issue of unitisation, one finds
article 49 obliging the 'Contractor ... to use those methods enabling an
optimal conservation of the Fields'. However, a more important, express
provision can be found in article 54, which states:
'In the event of a Field declared commercial extending over at least
two Areas subject to distinct contracts, the concerned contractors,
following notification by the National Agency for the Development of
Hydrocarbon Resources (ALNAFT), must draw up a joint plan for
development and Exploitation of the Field. Such plan shall be designated a
"unitization plan". It shall be submitted to the National Agency for the
Development of Hydrocarbon Resources (ALNAFT) for approval.
In the event of the contractorsnot agreeingon the unitization plan six (6)
months following notification of the National Agency for the
Development of Hydrocarbon Resources (ALNAFT), for the purpose
of preparing a unitization plan, or if the National Agency for the
4 To the extent that no express provision exists, one could look for indirect guidance or
obligation through, for example, legal or regulatory provisions on conservation. As the
AIPN Study put it, where 'broader provisions on conservation [exist], unitisation is arguably
required when necessary to prevent waste' (p 18). One writer has suggested that rules relating
to health safety and the environment may provide the state with implicit authority to compel
unitisation as well (Nwete, n 3 above, at 229).
5 Loi No 05-07 du 19 Rabie El Aouel 1426, correspondant au 28 avril 2005, relative aux
hydrocarbures.
7 One would, of course, hope that the potential for unitisation has been sorted out in existing
arrangements, which in many respects should be grandparented under art 101 of the
Hydrocarbons Law, but one can readily see the potential for confusion here.
8 It should be noted that, in an Ordinance dated 29 July 2006, there is a proposal to modify
this clause to state: 'In all cases in which SONATRACH is a participant, the international
arbitration procedure will involve only these entities other than SONATRACH.' This looks
highly problematic, notably when we consider that the new Ordinance provides
SONATRACH with the right to take at least a 51 per cent (hence controlling) interest as
part of this new 'reform'. The author would like to thank Mostefa Trari-Tani, Maitre de la
Conference at the Oran Law Faculty of Algeria, for his reflections in this regard.
9 Emphasis added. The original French version reads as follows:
'Tout diff~rend, opposant l'agence nationale pour la valorisation des ressources en
hydrocarbures (ALNAFT) au contractant, n de l'interpr~tation et/ou de l'excution du
contrat on de l'application de la pr~sente loi et/ou des textes pris pour son application,
fait l'objet d'une conciliation pr~alable dans les conditions convenues dans le contrat.
En cas d'6chec de la procedure de conciliation, le diffrend peut tre soumis Al'arbitrage
international dans les conditions convenues dans le contrat.
Cependant, quand SONATRACH - S.P.A. est le seul contractant, le diff~rend est rgl
par arbitrage du ministre charg6 des hydrocarbures.
Le droit alg~rien, notamment ia pr~sente loi et les textes pris pour son application,
sont appliques au r glement des diffrends.'
10 One could even envisage the potentially problematic situation where the parties have -
and apply - their rights to arbitrate but at the same time are obliged to implement the
expert's plan (which 'shall come into force' according to art 54). A party's only recourse
here may be reference to a national court for a stay of implementation of the expert's
plan.
Russia
In Russia, the position concerning unitisation is in many respects less clear
than in Algeria.
The Subsoil Law is silent on this issue, and hence contains no requirement
to unitise. The Regulations on the Licensing of Subsoil Use, 2 on the other
hand, do address this issue. An informal translation of the relevant provisions
provides as follows:
'6.2. Licenses for subsoil exploration certify the right to carry out
prospecting and evaluate mineral deposits and facilities used for the
construction and operation of underground structures that are not
related to the extraction of minerals.
11 While this phrase is somewhat limitative, there remains scope for broadening the reference
by virtue of art 58's inclusion of matters concerning 'the application of this Law'.
12 Law No 3314-1 dated 15July 1992.
6.3. Licenses for the extraction of minerals grant their holders the
right to the exploration and development of deposits and to the
processing of mining and related waste, unless otherwise stated in the
license.
Such licenses may be issued with respect to the development of an
entire mineral deposit or its separate part. The development of a single
field by several subsoil users must be carried out on the basis of an agreed
technologicalscheme preventing the inefficient use of subsoil. The activities
of the different subsoil users shall be coordinated, according to their
decision, by one of the enterprises, whom the other enterprises entrust
with the functions of a coordinator. The said condition shall be specified
in the licenses for the right to develop such deposit.' (Emphasis added.)
This suggests that an agreed technological scheme must be in place and
that one of the users must be appointed as a coordinator. If no scheme is in
place, development cannot, presumably, take place.13
It further appears that an existing developer's right to seek extension of
a licence area exists where the relevant adjacent block is vacant (but note
that the language appears to fall short of an absolute right).
In addition, and as some writers have pointed out:
'One should also note that Clause 5.8 of the technological document
form (applicable both to technological schemes and to exploration
projects) attached to the 'Rules for the Preparation of Technological
Project Documents for the Development of Oil and Gas Deposits' (RD
153-39-007-96) specifies that in the event a deposit is developed by several oil
and gas-producingcompanies, the technical and economic indicators of
the recommended development option are to be stated separately for
each company. This requirementmay be interpretedas an obligationfor these
companies to jointly submit development options within the set of project
documents (technological scheme and exploration project).'14
13 For a more detailed discussion, see AA Bardin and S V Dubyrin, 'Concerning Regulation
under Russian Federation Legislation ofJoint Development by Several Subsoil Users of a
Single Deposit of National Resources' (2005) 6 Mineral Resources of Russia (original in
Russian).
14 Ibid, at 5 (emphasis added).
Contractual scheme
It is largely as a result of the uncertainties mentioned above that the issue of
unitisation is dealt with (and best dealt with) in the petroleum agreement
itself. Frequently, model or negotiated agreements contain an undertaking
by the developer to unitise on the occurrence of joint ownership of a
common reservoir, but the reference in many of these cases is quite cursory.16
In these circumstances it appears critical to pay heed to the following
issues:
(1) It is necessary to identify the 'trigger event'. In other words, on what
event does the obligation to unitise arise? The most common example
is if a hydrocarbon-bearing structure extends into another contract area
(the situation can be complicated, of course, if the other developer has
no obligation to unitise), although in some countries the issue comes
to a head for consideration where fields within a contract area require
17
joint operation to be rendered commercial.
(2) One must consider the nature of the obligation to negotiate. How long
must a period of negotiation last, for example, before other measures -
state intervention, expertise or arbitration - arise? In light of doubts in
many common law jurisdictions as to the enforceability of undertakings
to negotiate, care always has to be taken to have a clear cut-off point
after which the relevant default post-negotiation mechanism/measure
clicks into place.
(3) Attention should be given to the factors to be taken in account in any
negotiation. Apart from the three arguably 'standard' considerations -
prevention of physical waste, prevention of economic waste and
protecting correlative rights 18 - other factors could include health, safety
another calling for a national of the relevant state, with a certain number
of years' experience and bearing dual qualifications ... 22);
" what happens if the parties fail to agree on an expert (ie who then decides
for them?);
* the basis on which the expert should act (ie as arbitrator or expert, with
all that this entails);
" the issues that the expert will decide;
* whether the expert's decision is binding and, if not, on what basis it can
be challenged; and
* who will pay for the expert.
As a starting point, one should again assume that - subject to indirect support
- local law will be of little assistance.
This would be particularly problematic where no right to a
redetermination exists in the unitisation agreement. 24 The question arises
as to whether a party can nevertheless force the other to a redetermination.
22 We found three such individuals, one of whom was on the arbitral tribunal and the other
two of whom had already given advice to each of the parties.
23 Redetermination can be described as the process by which previous unit or tract costs and
production are subsequently reapportioned or reallocated between parties to an unitisation
agreement based on new data on reservoir characteristics and properties.
24 One question arises here: can an expert entrusted with the task of making an initial
determination provide for redetermination subsequent to his or her ruling? Should this
issue be raised in the expert's terms of reference?
Domestic law may have something - but not much - to say. Under common
law, the notion of frustration appears highly unlikely to assist, although one
could argue the common or civil law doctrine of mutual mistake may have a
role to play in revisiting the initial determination. The problem, of course,
is that usually the parties know full well that the solution imposed at the
outset may be arbitrary, but take a position in the full knowledge that the
result may aver arbitrary in the future.
It is worth querying whether certain legal systems - such as those following
Dutch law - could permit a claim based on hardship.25 This notion seems
the most likely (albeit limited) candidate to compel redetermination, even
if one often needs to remember that solving one party's hardship is not an
answer if itjust creates hardship for the other. It is submitted that the grounds
for asserting hardship in the case of a redetermination may be easier to
establish than applications for revision in the case of long-term power
purchase agreements or gas sales agreements where readjustments sought
as a result of, for example, the failure of end markets have traditionally
been resisted. The reason for this (although much will obviously turn on
the facts of any given case) is that a redetermination involves a redistribution
of both cost and benefit.
That is not to say that such a course is a straightforward one. A number of
modern unitisations forego the right to a redetermination and so any recent
unitisation agreement that is silent on the issue could readily be construed
as one in which the parties have considered the issue and elected not to
maintain this right. Such a finding of assumption of risk could well nigh
end the debate.
Contractual scheme
One turns to the case where the parties have in fact addressed the issue of
redetermination, which is the product of the parties' recognition that, at
the time of a unitisation, much of the relevant accumulation is to a certain
extent unknown and unpredictable. Rather than waiting until more reservoir
information becomes available (and some can frequently only become
available during development), the parties hence choose rather to agree a
certain share with the knowledge that either party may seek a reallocation
of costs and production once more is known.
25 For example, Indonesia's Civil Code appears to allow courts or tribunals to intervene in
circumstances where the circumstances have changed to such a degree as to render
performance unconscionable (see discussion in Himpurna CaliforniaEnergy Ltd v PT
PerusahoanListruik Negara (December 1999) 14 Mealey's ArbitrationReport pp A1-A58).
This being said, the industry's experience with redetermination has been
a painful one in terms of time, costs and relations. 26 For this reason, there is
a discernible trend away from redetermination with some recent unitisations
avoiding them altogether.
The obvious concern is that of time and cost: the Prudhoe Bay
redetermination, for instance, cost the partners millions of dollars in legal
and experts' fees. And the stakes can, of course, be high, notably where a
field is marginal or where a party has entered into a long-term partnership
to meet commitments that may be threatened by loss of production-share.
Other problems arise from technical issues, of which there are a myriad.
Interpretation of the data is frequent; the writer has seen disputes over the
tools to be employed to collect the data. In addition, many issues arise once
a redetermination has been finalised. Some of these are discussed briefly
below. As it is hoped can be seen, the issues can quickly become very, very
complex.
Accordingly, matters that may warrant contractual attention in a
redetermination include the following:
" the 'trigger' for any redetermination exercise, as well as the number and
timing of such redeterminations;
* agreeing a common database (in other words, which raw data will be
supplied from the unit area and made available);
" a cut-off date after which no new data will be allowed;
• if a redetermination is to occur, what figures will be given to depreciation
and/or any uplift on the amount redetermined;
* whether any redetermination is retroactive or not;
* adjustments to take account of price differences for the product when
allowing a party 'catch-up' on past production, including possible
consideration of after-tax values at the time of original production as
compared to those at the time of adjustment (parties frequently avoid
this tortuous exercise);
" whether the operator can be removed if the new proportions cross an
agreed threshold;
What if a party is unhappy with the state for one reason or another but it
appears to have come to the end of the road in terms of contractual or
27 Ross, n 20 above.
28 See Art 20.2(D) of the AIPN Model Agreement.
29 See Pennzoil v Ramco, n 27 above, where the entire battle was over whether the relevant
dispute was covered by an arbitration clause or not.
30 An example of one such clause is found in Art 11.2(c) of the United States-Russian
Federation bilateral investment agreement (BIT), which reads: '[e] each Party shall observe
any obligation it may have entered into with regard to investments of nationals or companies
of the other Party.'
31 Article 5 of the United States' model BIT, which reads' [ejach Party shall accord to covered
investments treatment in accordance with customary international law, including fair and
equitable treatment and full protection and security,' is elaborated such that 'fair and
equitable treatment' 'includes the obligation not to denyjustice ... in accordance with the
principle of due process'.
32 In spite of the somewhat uniform language of fair and equitable treatment clauses, it is
difficult to distil the exact content of this obligation; hence, no clear objective standard
exists against which the behaviour of a state can be gauged. This is evident in the fact that,
regardless of its ordinary meaning, Art 1105(1) of NAFTA was subject to varying
interpretations by arbitral tribunals and to an interpretative declaration stipulating that
fair and equitable treatment is limited to the 'minimum standard of treatment of aliens'.
33 Tecnicas Medioambientales Tecmed SA v Estados Mexicanos (ICSID Case No ARB (AF)/00/2
(2003) Award dated 29 May 2003).
34 CME Czech Republic BV (The Netherlands)v The Czech Republic (Partial Award of 13 September
2001).
situations where a foreign investor feels hard done by when dealing with a
state in the context of a potential unitisation." Cases could vary from the
imposition of participating shares by a state agency, refusal to implement
an agreed unitisation or discrimination generally in favour of an NOC or
other local partners.
Thirdly, there is the issue of expropriation. Expropriation clauses are
among the more lengthy of the general provisions in investment agreements.
The salient part of Article 13 of the ECT, which is representative of most
expropriation provisions, stipulates that '[i]nvestments ... shall not be
nationalized, expropriated or subjected to a measure or measures having
effect equivalent to nationalizing or expropriation ... except where [it] is:
(a) for a purpose which is in the public interest; (b) not discriminatory; (c)
carried out under due process of law; and (d) accompanied by the payment
of prompt, adequate and effective compensation'. Expropriation clauses
usually also set down a standard for compensation (eg fair market value
immediately before expropriation, payable without delay in a freely usable
currency, etc).
It is widely-recognised that a state will be liable not only for overt or direct
and intentional ('dejure') taking of property or other assets, such as through
nationalisation of an industry. A state will also be liable for covert or indirect
('de facto' or 'creeping') expropriation that effectively deprives an investor
of the use or enjoyment of its investment. In these cases, even legitimate
reasons behind the actions of a state (eg for environmental purposes) do
not generally bear on a determination whether such actions amount to
expropriation.
Thus, for example, arbitral tribunals have found expropriation where a
state broadcasting authority compelled an investor inter alia to give up
exclusive licensing rights it was specifically accorded at the outset of its
investment,36 and where a state wrongfully refused to permit an investor to
open and operate a waste facility that had been built in response to the
invitation of officials from the state. In the context of the oil industry, the
Iran-United States Claims Tribunal found that expropriation had occurred
35 Relevant to the oil and gas industry is the 2004 Occidentaldecision in which a state arbitrarily
and discriminatorily announced abruptly that an entrenched tax reimbursement scheme
no longer applied to foreign oil companies: see OccidentalExplorationandProductionCompany
v Republic of Ecuador (Case No UN 3467 Final Award dated 1July 2004).
36 CMIE Czech Republic BV(The Netherlands) v The Czech Republic (Partial Award of 13 September
2001).
37 Metalclad Corp v United Mexican States (ICSID Case No ARB(AF)/97/1 Award dated 30
August 2000) (2001) 16 ICSID Review-Foreign Investment LawJournal168.
38 PhillipsPetroleum v Iran (Case No 39, Chamber No Two, Award No 425-39-2, Iran-US Claims
Tribunal (June 1989)).
39 One issue that could arise is: can the actions of a state-imposed expert - for the purposes
of a treaty claim - be considered to be the actions of ajudicial authority the proper conduct
of whom/which can give rise to state responsibility? A case related to this issue is Loewen
Group, Inc and Raymond L Loewen v United States ofAmerica (ICSID Case No ARB(AF)/98/3,
Award dated 26June 2003) 7 ICSJD Reports, in which an arbitral tribunal recognised that a
state could be held liable for problems in its administration ofjustice.
Conclusion
40 See American Manufacturing& Trading, Inc v Republic of Zaire (ICSID Case No ARB/93/1
Award of 21 February 1997) (1997) 36 InternationalLegalMaterials1531. Indeed, Art 5(2) (b)
of the United States' model BIT specifies that 'full protection and security' 'requires each
Party to provide the level of police protection required under customary international
law'.
41 See Asian AgriculturalProducts Ltd v Republic of Sri Lanka (Award of 27June 1991) 4 ICS1D
Reports 246; Wena Hotels Ltd v Arab Republic ofEgypt (ICSID Case No ARB/98/4, Decision of
2000) (2002) 41 InternationalLegal Materials896.
42 See the related cases of Ronald S Lauder v The Czech Republic (UNCITRAL Final Award of
3 September 2001) and CME Czech Republic BV (The Netherlands)v The Czech Republic (partial
award of 13 September 2001).
43 See generally Case ConcerningElettronicaSicula, SpA (ELSI) (United States v Italy, judgment
of 20 July 1989) (1989) InternationalCourt ofJustice Reports 15.