Introduction
Value Engineering (VE) is a systematic process using a team from a variety of disciplines
to improve the value of a project through the analysis of its functions. The VE process
incorporates, to the extent possible, the values of design, construction, maintenance, contractors,
state, local and federal approval agencies, other stakeholders, and the public.
In accordance with 23 CFR Part 627, State highway agencies must establish programs to
assure that VE studies are performed on all Federal-aid highway projects on the NHS (National
Highway System) with an estimated cost of $25 million or more and for bridge projects with an
estimated cost of $20 million or more. The Office of Quality Assurance, in cooperation with the
design team, should identify and implement VE studies on additional projects with
characteristics or factors that may offer improved value. Factors may include more than one
alternative, complexity, fast track scheduling, controversial components, innovation, traffic
impacts or scope creep.
Projects meeting the underlined criteria above must have a documented VE study
performed in a timely manner. Failure to conduct a VE study as stipulated by federal
requirements may result in delays in authorization of construction funds for those federal-aid
projects meeting the criteria that have not had a Value Engineering study performed.
This document will serve as a guideline to maintain the Value Engineering Program
within the Connecticut Department of Transportation. As such, the document itself will be
subject to revision and maintenance as needed. Any modifications/updates to this document
should be coordinated with the Federal Highway Administration (FHWA).
3
Value Engineering Program
November 2009
Project Selection
The trigger for Value Engineering studies to be warranted is first evident at Project
Scoping when the Department’s design team estimates that the preliminary total project costs,
including Environmental studies, Preliminary Engineering, Final Design, ROW and Construction
costs of the project, will exceed the identified cost criteria (see below). At any time during the
project development that the Engineer’s Estimate indicates the total project costs will exceed the
identified cost criteria, the Design Project Manager is to notify OQA that a VE study must be
implemented.
Other projects may also be selected for VE studies. In addition to the cost, other issues
adding to the complexity of the project design should be considered in the selection process.
These complexities may include: critical constraints, difficult technical issues, expensive
solutions, external influences, or complicated functional requirements. The types of projects that
usually provide the highest potential for value improvements are:
• Projects with alternate solutions which vary the scope and cost
• New alignment or by-pass sections
• Widening existing highways for capacity improvements
• Major structures
• Interchanges on multi-lane facilities
• Projects with extensive or expensive environmental or geotechnical requirements
• Difficult materials requirements or inferior material sources
• Major reconstruction of existing highways
• Projects with major traffic control
• Projects with multiple stages
4
Value Engineering Program
November2009
OQA personnel will track all potential projects due for VE studies. The initial indicator
tool is the Department’s “Working Schedule of Federal-Aid Obligations” compiled by the Office
of Capital Services. OQA compiles and updates a list of projects due for Value Engineering
studies, adding or removing projects as project estimates go through refinements. OQA shall
ensure that a listing of all federally funded projects planned for VE studies is forwarded to
FHWA on a semi-annual basis. The Department’s designers will play a major role in identifying
candidate projects for VE studies.
Whenever a VE study is required, the project’s budget and schedule should be adjusted to reflect
the additional resources necessary to complete the study.
VE Study Levels
The Department has established two (2) levels of Value Engineering studies: Level A,
and Level B. The level chosen will dictate the composition of the study team and the scope of
the procedures to be followed.
The Level A study is the most comprehensive and should be considered for complex
projects, new construction, capacity improvements, and major reconstruction. This level will
typically involve task-based consultant engineers with particular expertise relating to the type of
project under study.
The Level B study should be considered for “maintenance” type work (paving, guiderail,
drainage improvements) and replaced-in-kind work where no additional capacity is gained.
Level B studies may be completed by task-based consultant or in-house staff.
Once a project is selected for study, OQA and the design team will determine the level of
study and composition of study team. Later sections of this document contain more specific
information about the personnel and procedures to be utilized in Level A versus Level B studies.
Timing
The timing of when to conduct the VE study is important. The Department has
completed studies at various times in the project schedule. Many projects have gone all the way
to final design before a VE study is done. When a study is done at that late of a stage, it is costly
and difficult to implement any recommendations from the VE study. It is recommended that the
VE study be completed as early in the design process as possible. VE is more effective and
influential on performance, quality, and cost of a project when done relatively early in the project
schedule.
When 30% plans of projects due for VE studies are available, OQA will begin to
assemble a study team. OQA will be responsible for scheduling the location(s) and necessary
personnel, both Department and Consultant, to conduct the VE study.
5
Value Engineering Program
November 2009
Study Team
The Value Engineering study team, either Level A or Level B, must be totally
independent of the design team and will typically consist of a Team Leader and five to seven
other members with expertise in various specialties related to the project. OQA will coordinate
with the project designer to determine the engineering disciplines that should be represented on
the VE study team. When necessary or appropriate the OQA may also utilize a consultant
engineering firm specifically contracted by the Department for VE services to assemble the team.
For each VE effort initiated, OQA shall ensure FHWA is offered the opportunity to attend and
participate. (FHWA Major Projects Team Leader 860-659-6703 ext. 3008)
To ensure a productive and focused VE effort, the Team Leader should be a Certified
Value Specialist (CVS), certified by SAVE International, or a Professional Engineer registered in
the State of Connecticut, with a minimum of ten years of experience related to roadway or bridge
design, roadway or bridge construction, maintenance or a specific engineering discipline
required by the project. For a Level A study the Team Leader should be a CVS who has
experience with VE studies. Level B studies can be led by either a CVS or a CT registered
Professional Engineer.
The other team members shall have diverse areas of expertise with concentration on the
major challenges/problem areas anticipated within the project (traffic, structures, soils, paving,
etc.) and general knowledge in design, construction, rights-of-way, maintenance and/or traffic
operations. Level A team members will typically be staff from a consultant engineer firm
specifically contracted by the Department to conduct VE services. Level B team members may
be in-house or VE consultant engineers or a combination of the two.
The project designers (Department and/or consultant), will also participate in the VE as
required to provide plans, special provisions and estimates, as well as to present the project
overview and conduct project site field reviews. The project designers will be expected to attend
the VE sessions to answer design specific questions and to hear the oral presentation on the last
study day so they can begin to review the recommendations made.
The Office of Quality Assurance will coordinate the activities of the VE study team,
including providing manuals and reference materials, providing access to a conference room
with any needed electronic equipment, arranging for site visits and any other materials that may
be considered necessary. Level B studies will most likely occur within the DOT Newington
Headquarters building. Some Level A studies may be held at a consulting engineer’s office
within the state.
6
Value Engineering Program
November2009
o Design Presentation/Site Visit - Look at the overall project, its location and
existing conditions. Begin to understand the design philosophy used.
o Audit Phase - Establish a record system to track the results and accomplishments
of the VE program and to compile the appropriate statistical analysis as requested
by management personnel.
7
Value Engineering Program
November 2009
is more “polished” and is independent of the results of the review of recommendations. It does
not contain information about which recommendations were incorporated into the project or
rejected.
The reviewers will include, but not be limited to, the project’s designers, DOT personnel
from Consultant Design, Hydraulics and Drainage, Soils and Foundations, Environmental
Planning, Traffic, Construction, Maintenance and FHWA. The recommendations will go
through an objective review and the length of time for the review may vary depending on project
complexity, but should be limited to one month. There may be some discussion between the
reviewers and the VE team to resolve any issues that arise regarding the recommendations. The
various reviewers will submit their comments to Design to recommend implementation or
rejection of the individual VE study recommendations, similar to a plan review process.
Ultimately the Project Manager in Design, in consultation with the various Department
Units/Sections involved with the project, will determine which VE recommendations will be
developed into the project, as well as documenting the rationale for not progressing the other VE
recommendations.
The Implementation Phase concludes when Design notifies the FHWA by letter (See
Appendix B for sample letter) outlining all the VE recommendations, and detailing the approved
VE recommendations which will be incorporated into the design of the project, and the estimated
cost savings from the approved recommendations. The recommendations which have been
rejected must be also be justified in the letter. The Department shall document the date of the
letter and reference the VE study completion when transmitting the PS&E document for
approval.
The Office of Quality Assurance will initiate the Audit Phase once the final approved and
rejected recommendations are developed by tracking pertinent VE information on the project.
As the project plans and specifications progress through 60%, 90% and final design, the
Engineer’s Estimate will be logged in a database. When the project is advertised, subsequent
bids are opened, and throughout the construction, OQA will continue to track the costs. Of
course, there will be no absolute way to compare the costs of the implemented VE recommended
design to the initial design.
VE During Construction
The Department has a Value Engineering provision within Division I of its Standard
Specifications for Roads, Bridges and Incidental Construction (Form 816) wherein a Contractor
may propose changes to a project of any size for potential cost savings. Article 1.09.02 outlines
the steps necessary for a Value Engineering Change Proposal (VECP) to be approved by the
Department. Generally, the process is carried out by the Office of Construction with input from
the project Designer(s). The Office of Quality Assurance maintains a database where VECP’s
are tracked for future reference, Lessons Learned information and for inclusion in the yearly
report to the FHWA.
8
Value Engineering Program
November2009
Beyond the necessary reporting, the information obtained from the various VE studies
helps all involved to think about alternative ways to look at problem solving and design methods.
9
Value Engineering Program
November 2009
* Not all information listed may be available to the team, depending on the stage of the project.
** If a site visit is not possible, provide video of the project.
10
Value Engineering Program
November2009
Division Administrator
Federal Highway Administration
628-2 Hebron Avenue, Suite 303
Glastonbury, Connecticut 06033
Dear :
Enclosed is a copy of the Value Engineering (VE) Report, together with a copy of the
responses to the VE proposals, for the subject project. These documents are the culmination of
the VE workshop conducted ___________ through ________________.
Three (3) recommendations were generated by the VE Team and further developed into
proposals. The advantages, disadvantages, and cost savings of each proposal were evaluated, as
follows.
VE Proposal Estimated Comments
VE Proposal
Number Savings
Of the three (3) proposals, the following one (1) proposal will be incorporated into the final
contract documents:
• _______________________________
If you have any questions concerning this material, please contact __________________
at 860-594-____.
Signature
Title
Office of Quality Assurance
Enclosures
11
Value Engineering Program
November 2009
1a Does your DOT have a formal VE Answer “Yes” if your DOT has a documented plan or
Program? Yes/No policy statement that identifies the elements and
components of a VE program.
1b Briefly describe your DOT’s If your DOT has processes for delivering the VE Program
documented VE policies or and conducting VE studies documented in a Project
procedures. Development or Design manual or other location, briefly
summarize the following:
Brief Narrative
• Processes used to develop the multi-year VE
program;
• Processes used to ensure VE studies are conducted
on all required projects, including those projects
administered by local agencies;
• Processes for reviewing, accepting or rejecting VE
recommendations;
• Processes for tracking and monitoring VE studies
and the implementation of recommendations.
1c If available, provide the current Provide links to any Web sites currently available that
links to your DOT’s VE-related contain your DOT’s:
Web sites
• General VE Program information
• VE Policies and Guidance
• VE Processes and Procedures
2a Does your DOT monitor the Answer “Yes” if your DOT monitors its performance at a
performance of the VE Program? programmatic level.
Yes/No
2b Does your DOT evaluate and Answer “Yes” if your DOT prepares an annual report that
report on the performance of the evaluates the performance of the VE Program.
VE Program? Yes/No
2c Does your DOT utilize Answer “Yes” if your DOT tracks performance measures
performance measures to assess other than those already required by this survey.
the effectiveness of the VE
Program? Yes/No
2d If the answer to 2b is “Yes”, please If the answer to Question 2a was “Yes”, indicate the
briefly describe. additional performance measures that are utilized.
12
Value Engineering Program
November2009
3a Describe any successful practices Briefly describe individual practices or policies that enable
your DOT uses in the delivery of VE studies to be conducted in a successful manner.
the VE Program.
Brief Narrative
3b Describe any successful practices Briefly describe individual practices or policies that enable
your DOT uses to encourage more VE Change Proposals to be implemented in a successful
successful implementation of manner.
VECPs during construction.
Brief Narrative
4a Identify the typical project factors Identify and briefly describe how project functions (e.g.,
and associated measures that your traffic, safety) are typically addressed during the
DOT requires to be analyzed on Investigation, Speculation, and Evaluation phases of your
VE Studies. VE analyses; explain the typical level of effort expended in
analyzing these critical project functions.
Examples:
Factor Measure
Safety Crashes
Traffic flow Delay
Cost $$$
Brief Narrative
Yes/No
4c If the answer to 4b is “Yes”, please Summarize your DOTs use of life cycle cost analyses while
explain. conducting VE studies; indicate whether they are conducted
as part of the study directly, if the study incorporates an
Brief Narrative independently conducted life cycle cost analysis, etc.
4d Describe when VE studies are Identify the most common point in the project development
generally conducted by your DOT process (planning, 0-30%; 30-70%; 70% or later) when VE
for design-bid-build projects. studies typically occur at your DOT.
Brief Narrative
4e Describe how and when VE studies Identify the point in the project development process (e.g.,
are generally conducted by your planning, prior to issuance of RFP, after issuance of RFP)
DOT for design-build projects. when VE studies typically occur. Briefly detail the
approach taken to conducting the study based on the stage
Brief Narrative of the project when the study was conducted.
13
Value Engineering Program
November 2009
4f If your DOT conducts multiple VE Identify the common points in the project development
studies on Major Projects, describe process when VE studies typically occur for Major Projects
the points in the project ($500 million or greater). If your DOT has no current
development process where the projects meeting this definition, or if one study is
studies occur. Brief Narrative completed, answer “N/A”.
5 Briefly describe a successful study Briefly describe a successful 2008 VE study as a "best
completed by your DOT in FY practice", or describe a general "lesson learned" from
2008. Brief Narrative conducting a particular VE study
6 Briefly describe any special studies Describe any business process, review of standards &
conducted by your DOT in FY specifications, or any other unique studies that used the VE
2008. job plan for which cost savings were not calculated.
Brief Narrative
Brief Narrative
# DOT
# FHWA
#Other
8b Describe your State DOT’s general Indicate the most common approach taken to conduct VE
approach to conducting VE training (e.g., VE Module 1 courses, shorter-duration
training. workshops, etc.) and indicate whether your DOT has
implemented any innovative training techniques.
Brief Narrative
14
Value Engineering Program
November2009
9a Total # of Studies Completed in FY Report only on studies that for which all activities were
____ completed; distinguish between studies accomplished by in-
house resources and consultants
# In-House, # Consultant
9c Anticipated # of Studies to be For informational purposes only, report on any studies that
Completed during the next two were initiated in the current fiscal year but will be finalized
fiscal years next year, in addition to all other planned studies for
completion in the next two fiscal years, if information is
available.
10a Report on the costs associated with When reporting on cost of studies completed, include the
conducting the VE studies following:
• Planning
• Environmental Compliance
• Preliminary Engineering
• Construction Estimate
• Construction Engineering Estimate
.
15
Value Engineering Program
November 2009
11a Enter the total number of Enter the total number of recommendations proposed.
recommendations proposed
11b Enter the total number of Enter the total number of recommendations that were
recommendations approved approved.
12a Enter the value of Enter the total net value of the proposed recommendations.
recommendations proposed
12b Enter the value of Enter the total net value of the recommendations that were
recommendations approved approved.
13a Enter the total number of VECP Enter the total number of VECP that were submitted.
submitted
13b Enter the total number of VECP Enter the total number of VECP that were approved.
approved
14a Enter the total value of VECP Enter the total value of the proposed VECP.
submitted
14b Enter the total value of VECP Enter the total value of the approved VECP.
approved
16
Value Engineering Program
November2009
17
Value Engineering Program
November 2009
Brief Narrative
Yes/No
Yes/No
19a Describe how the VE Program is For your Division’s Stewardship and Oversight Agreement,
currently addressed in your summarize what is currently documented regarding the VE
Division’s Stewardship and Program’s:
Oversight Agreement with your
DOT. • Description of general Roles and Responsibilities
• Procedures for the Division’s VE Coordinator
Brief Narrative • Delegation of Authority for Projects
19b Describe your Division’s current Discuss the Division’s regular interaction with the State
level of involvement in the VE DOT VE Program staff in activities including the
Program following: