You are on page 1of 82

CHAPTER 4: DATA ANALYSIS AND RESULT ANALYSIS

4.1. INTRODUCTION

The data analysis and result analysis of the topic has been shown below. The implementation of data has
been done using Statistical Package for the Social Sciences (SPSS). In this chapter a discussion is done of
the collected data which is gathered using a structured questionnaire.

4.2. DATA COLLECTION

For the study of the causes of change orders in construction projects which are being conducted in Oman
an analysis has been presented. The data for the analysis has been gathered through using a structured
questionnaire. This is done by collecting responses of 169 respondents which have been classified in the
percentage form. The frequency of the data has been used for extracting the percentage of responses
which shall be represented and elaborated.

4.3. RESULTS ANALYSIS

The purpose of this research is to develop an understanding of the topic and relevant literature which has
been discussed in the literature review of tis research. The structure of the analysis initially comprises the
general information of the participants which show the characteristics of the population of data. On the
basis of this causes of variation attributes associated with the data have been discussed which shows
relation to the clients, relation to the consultants, relation to the contractors and other associated changes
have been discussed. The effects of variations are also discussed through the data and associated
questions.

4.3.1. GENERAL INFORMATION OF THE PARTICIPANTS

In this section of the research general information of the participants are discussed and elaborated. The
below mentioned details shows the details of the respondents as per their positions which is bifurcated as
client, project manager, contractors, quality surveyors and consultants.

TABLE (4-1): RESPONDENTS AS PER POSITION

Position
Cumulative
Frequency Percent Valid Percent Percent

Valid Client 14 8.3 14.0 14.0

Project Manager 19 11.2 19.0 33.0

Contractors 28 16.6 28.0 61.0

Quantity Surveyor 18 10.7 18.0 79.0

Consultant 21 12.4 21.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The representation of the pie chart shows that from the data which has been gathered 14% individuals are
Clients, 19% individuals are Project Managers, 28% individuals are Contractors, 18% individual are
Quality Surveyors and 21% individuals are Consultants.

FIGURE (4-1): PERCENTAGE OF RESPONDENTS AS PER POSITION


The details which are shown below classify the experience level of the respondents. The frequency of
respondents is classified from 0 – 5 years, 6-10 years, 11 – 15 years and individuals who have an
experience of more than 15 years.

TABLE (4-2): RESPONDENTS AS PER EXPERIENCE

Experience

Cumulative
Frequency Percent Valid Percent Percent

Valid 0 - 5 years 22 13.0 22.0 22.0


6 - 10 years 24 14.2 24.0 46.0

11 - 15 years 30 17.8 30.0 76.0

> 15 years 24 14.2 24.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The pie chart which is shown below shows percentage classification of the respondents. The respondents
which have an experience of 0 – 5 years are 22%, 6 - 10 years are 24%, 11 -15 years are 30% and the
experience of more than 15 years individuals are 24%.

FIGURE (4-2): PERCENTAGE OF RESPONDENTS AS PER EXPERIENCE


The data which is represented in the table below shows details of the academic degrees of the
respondents. The details of the information which is shown below is classified as Bachelors, Masters and
Ph.D. All the respondents’ response has been classified separately so that the effectiveness of the
responses can be measure for further analysis.

TABLE (4-3): RESPONDENTS AS PER ACADEMIC DEGREE HELD

Academic Degree Held

Cumulative
Frequency Percent Valid Percent Percent

Valid Bachelor 32 18.9 32.0 32.0

Masters 37 21.9 37.0 69.0


Ph.D 31 18.3 31.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the pie chart which has been shown below the qualification details of the respondents have been
classified as percentage. The details of the data clearly shows that percentage of the respondents which
are Bachelors is 32%, Masters is 37% and Ph.D. is 31%. This classifies the quality of the responses which
have been gathered and creates an understanding of the accuracy of the data which has been gathered and
the academic degree which is held by the respondents.

FIGURE (4-3): PERCENTAGE OF RESPONDENTS AS PER ACADEMIC DEGREE HELD


In the table below the total respondents have been classified as per the types of organization in which they
work. In order to keep the classification simple the data has only been classified into the public and
private sector. More detailed analysis of this question was not required as per the requirement of the topic.

TABLE (4-4): RESPONDENTS AS PER TYPE OF ORGANIZATION

Type of Organization

Cumulative
Frequency Percent Valid Percent Percent

Valid Public 50 29.6 50.0 50.0

Private 50 29.6 50.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the pie chart which has been shown below the type of organization in which the respondents work have
been classified. The percentage of respondents which work in the private sector are 50% and the
percentage of respondents which work in the public sector are 50%.

FIGURE (4-4): PERCENTAGE OF RESPONDENTS AS PER TYPE OF ORGANIZATION


All the details which have been discussed above classify the respondents as per the requirement of the
topic which is relevant to the topic.

4.3.2. ANALYSIS OF OVERALL RESULTS

In the analysis which shall be further presented the data has been classified in the forms of indicators. The
details of the segment show the classification of the responses using the Likert scale in which the
responses are never, rarely, occasionally, often and always. This has been further evaluated through
classification as the causes and effects of variation. For the purpose of analysis several questions have
been asked to the respondents on the basis of which the survey has been done.

4.3.3. CAUSES OF VARIATION

In this section of the analysis the questions associated with the causes of variation in the of change orders
in the construction projects which are being done in Oman have been discussed. For the purpose of
analysis several questions have been formulated in various segments which shall be elaborately discussed
below.

4.3.3.1. RELATED TO CLIENTS


In this portion of analysis classification has been done of data of responses which relate to the clients. The
data has been structured statistically based on the responses and has been classified as percentage. The
detailed explanation and classification of percentage of responses shall be seen below in detail.

TABLE (4-5): RESPONDENTS AS PER RELATED TO CLIENTS

Related to Clients

Frequency Percent Valid Percent Cumulative Percent

Valid 1.53 1 .6 1.0 1.0

1.67 1 .6 1.0 2.0

1.80 1 .6 1.0 3.0

1.93 1 .6 1.0 4.0

2.07 1 .6 1.0 5.0

2.20 1 .6 1.0 6.0

2.33 1 .6 1.0 7.0

2.40 1 .6 1.0 8.0

2.47 1 .6 1.0 9.0

2.53 2 1.2 2.0 11.0


2.80 1 .6 1.0 12.0

3.20 1 .6 1.0 13.0

3.27 1 .6 1.0 14.0

3.33 1 .6 1.0 15.0

3.40 1 .6 1.0 16.0

3.47 5 3.0 5.0 21.0

3.53 1 .6 1.0 22.0

3.60 1 .6 1.0 23.0

3.67 3 1.8 3.0 26.0

3.73 4 2.4 4.0 30.0

3.80 4 2.4 4.0 34.0

3.87 2 1.2 2.0 36.0

3.93 2 1.2 2.0 38.0

4.00 8 4.7 8.0 46.0


4.07 5 3.0 5.0 51.0

4.13 7 4.1 7.0 58.0

4.20 6 3.6 6.0 64.0

4.27 6 3.6 6.0 70.0

4.33 7 4.1 7.0 77.0

4.40 5 3.0 5.0 82.0

4.47 3 1.8 3.0 85.0

4.53 6 3.6 6.0 91.0

4.60 4 2.4 4.0 95.0

4.67 1 .6 1.0 96.0

4.73 1 .6 1.0 97.0

4.80 1 .6 1.0 98.0

4.87 1 .6 1.0 99.0

4.93 1 .6 1.0 100.0


Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the change of the scope by the client has been discussed. The
respondents replied as never 4%, rarely 9%, occasionally 16%, often 38% and always 33%. Majority of
the respondents went with often and always in responding to change of scope by the client.

TABLE (4-6): RESPONDENTS AS PER CHANGE OF SCOPE BY THE CLIENT

Change of scope by the client

Frequency Percent Valid Percent Cumulative Percent

Valid Never 4 2.4 4.0 4.0

Rarely 9 5.3 9.0 13.0

Occasionally 16 9.5 16.0 29.0

Often 38 22.5 38.0 67.0

Always 33 19.5 33.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8


Total 169 100.0

In the table which has been shown below the clients change of project schedule has been discussed. The
respondents replied as never 1%, rarely 5%, occasionally 16%, often 44% and always 34%. Majority of
the respondents went with often and always in responding to change of client’s change of project
schedule.

TABLE (4-7): RESPONDENTS AS PER CLIENT’S CHANGE OF PROJECT SCHEDULE

Client’s Change of project schedule

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 5 3.0 5.0 6.0

Occasionally 16 9.5 16.0 22.0

Often 44 26.0 44.0 66.0

Always 34 20.1 34.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0


In the table which has been shown below the client’s financial problems has been discussed. The
respondents replied as never 1%, rarely 6%, occasionally 19%, often 32% and always 42%.

Majority of the respondents went with often and always in responding to client’s financial problems.

TABLE (4-8): RESPONDENTS AS PER CLIENT’S FINANCIAL PROBLEMS

Client’s financial problems

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 6 3.6 6.0 7.0

Occasionally 19 11.2 19.0 26.0

Often 32 18.9 32.0 58.0

Always 42 24.9 42.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the inadequate project objectives set by the client has been
discussed. The respondents replied as never 0%, rarely 6%, occasionally 21%, often 31% and always
42%. Majority of the respondents went with occasionally, often and always in responding to inadequate
project objectives set by the client.
TABLE (4-9): RESPONDENTS AS PER INADEQUATE PROJECT OBJECTIVES SET BY THE
CLIENT

Inadequate project objectives set by the client

Frequency Percent Valid Percent Cumulative Percent

Valid Rarely 6 3.6 6.0 6.0

Occasionally 21 12.4 21.0 27.0

Often 31 18.3 31.0 58.0

Always 42 24.9 42.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the client’s replacement of material has been discussed. The
respondents replied as never 1%, rarely 7%, occasionally 19%, often 35% and always 38%. Majority of
the respondents went with occasionally, often and always in responding to client’s replacement of
material.

TABLE (4-10): RESPONDENTS AS PER CLIENT’S REPLACEMENT OF MATERIALS

Client’s Replacement of materials


Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 7 4.1 7.0 8.0

Occasionally 19 11.2 19.0 27.0

Often 35 20.7 35.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the change inspecification by the client has been discussed. The
respondents replied as never 5%, rarely 9%, occasionally 11%, often 37% and always 38%. Majority of
the respondents went with often and always in responding to change in specifications by the client.

TABLE (4-11): RESPONDENTS AS PER CHANGE IN SPECIFICATIONS BY THE CLIENT

Change in specifications by the client

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0


Rarely 9 5.3 9.0 14.0

Occasionally 11 6.5 11.0 25.0

Often 37 21.9 37.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the client instructs modification to design has been discussed.
The respondents replied as never 2%, rarely 4%, occasionally 15%, often 28% and always 51%. Majority
of the respondents went with always in responding to client instructs modification to design.

TABLE (4-12): RESPONDENTS AS PER CLIENT INSTRUCTS MODIFICATION TO DESIGN

Client instructs modification to design

Frequency Percent Valid Percent Cumulative Percent

Valid Never 2 1.2 2.0 2.0

Rarely 4 2.4 4.0 6.0

Occasionally 15 8.9 15.0 21.0


Often 28 16.6 28.0 49.0

Always 51 30.2 51.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the financial constraints faced by the client has been discussed.
The respondents replied as never 1%, rarely 4%, occasionally 16%, often 33% and always 46%. Majority
of the respondents went with often and always in responding to financial constraints faced by the client.

TABLE (4-13): RESPONDENTS AS PER FINANCIAL CONSTRAINTS FACED BY THE


CLIENT

Financial constraints faced by the client

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 4 2.4 4.0 5.0

Occasionally 16 9.5 16.0 21.0

Often 33 19.5 33.0 54.0


Always 46 27.2 46.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the insufficient coordination among the parties by the client has
been discussed. The respondents replied as never 2%, rarely 9%, occasionally 18%, often 25% and
always 46%. Majority of the respondents went with always in responding to insufficient coordination
among the parties by the client.

TABLE (4-14): RESPONDENTS AS PER INSUFFICIENT COORDINATION AMONG THE


PARTIES BY THE CLIENT

Insufficient coordination among the parties by the client

Frequency Percent Valid Percent Cumulative Percent

Valid Never 2 1.2 2.0 2.0

Rarely 9 5.3 9.0 11.0

Occasionally 18 10.7 18.0 29.0

Often 25 14.8 25.0 54.0

Always 46 27.2 46.0 100.0


Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below the weak client’s decision making process has been discussed.
The respondents replied as never 5%, rarely 8%, occasionally 18%, often 42% and always 27%. Majority
of the respondents went with often in responding to weak client’s decision making process.

TABLE (4-15): RESPONDENTS AS PER WEAK CLIENT’S DECISION MAKING PROCESS

Weak client’s decision making process

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 8 4.7 8.0 13.0

Occasionally 18 10.7 18.0 31.0

Often 42 24.9 42.0 73.0

Always 27 16.0 27.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8


Total 169 100.0

In the table which has been shown below the change in design by the client has been discussed. The
respondents replied as never 9%, rarely 27%, occasionally 17%, often 32% and always 15%.

Majority of the respondents went with rarely and often in responding to change in design by the client.
This shows a varying perspective in situation.

TABLE (4-16): RESPONDENTS AS PER CHANGE IN DESIGN BY THE CLIENT

Change in design by the client

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 27 16.0 27.0 36.0

Occasionally 17 10.1 17.0 53.0

Often 32 18.9 32.0 85.0

Always 15 8.9 15.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0


In the table which has been shown below client’s lack of strategic planning has been discussed. The
respondents replied as never 9%, rarely 5%, occasionally 14%, often 32% and always 40%.

Majority of the respondents went with often and always in responding to client’s lack of strategic
planning.

TABLE (4-17): RESPONDENTS AS PER CLIENT’S LACK OF STRATEGIC PLANNING

Client’s lack of strategic planning

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 5 3.0 5.0 14.0

Occasionally 14 8.3 14.0 28.0

Often 32 18.9 32.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

In the table which has been shown below poor procurement process by the client has been discussed. The
respondents replied as never 0%, rarely 6%, occasionally 21%, often 31% and always 42%. Majority of
the respondents went with occasionally, often and always in responding to poor procurement process by
the client.

TABLE (4-18): RESPONDENTS AS PER POOR PROCUREMENT PROCESS BY CLIENT

Poor procurement process by Client

Frequency Percent Valid Percent Cumulative Percent

Valid Rarely 6 3.6 6.0 6.0

Occasionally 21 12.4 21.0 27.0

Often 31 18.3 31.0 58.0

Always 42 24.9 42.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 9%, rarely 27%, occasionally 17%, often 32% and always 15%.
Majority of the respondents went with occasionally, often and always in responding to change of plans by
the client.

Table (4-19): Respondents as per Change of plans by the client

Change of plans by the client


Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 27 16.0 27.0 36.0

Occasionally 17 10.1 17.0 53.0

Often 32 18.9 32.0 85.0

Always 15 8.9 15.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 28%, occasionally 12%, often 19% and always 38%.
Majority of the respondents went with often and always in responding to conflict between client and
contract documents.

TABLE (4-20): RESPONDENTS AS PER CONFLICTS BETWEEN CLIENT & CONTRACT


DOCUMENTS

Conflicts between client & contract documents

Frequency Percent Valid Percent Cumulative Percent


Valid Never 3 1.8 3.0 3.0

Rarely 28 16.6 28.0 31.0

Occasionally 12 7.1 12.0 43.0

Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The responses show that most of the time the change of planning is done due to the clients and this results
in variation of the plans when the details are related to the clients.

4.3.3.2. RELATED TO CONSULTANTS

In this portion of analysis classification has been done of data of responses which relate to the consultants.
The data has been structured statistically based on the responses and has been classified as percentage.
The detailed explanation and classification of percentage of responses shall be seen below in detail.

TABLE (4-21): RESPONDENTS AS PER RELATED TO CONSULTANTS

Related to Consultants

Frequency Percent Valid Percent Cumulative Percent


Valid 1.53 1 .6 1.0 1.0

1.67 2 1.2 2.0 3.0

1.73 3 1.8 3.0 6.0

1.93 1 .6 1.0 7.0

2.20 1 .6 1.0 8.0

2.40 1 .6 1.0 9.0

2.53 1 .6 1.0 10.0

2.60 1 .6 1.0 11.0

2.67 3 1.8 3.0 14.0

2.73 1 .6 1.0 15.0

2.87 2 1.2 2.0 17.0

2.93 1 .6 1.0 18.0

3.00 1 .6 1.0 19.0

3.07 1 .6 1.0 20.0


3.20 3 1.8 3.0 23.0

3.27 1 .6 1.0 24.0

3.33 2 1.2 2.0 26.0

3.40 2 1.2 2.0 28.0

3.47 1 .6 1.0 29.0

3.60 1 .6 1.0 30.0

3.67 2 1.2 2.0 32.0

3.80 1 .6 1.0 33.0

3.87 2 1.2 2.0 35.0

3.93 2 1.2 2.0 37.0

4.00 3 1.8 3.0 40.0

4.07 4 2.4 4.0 44.0

4.13 3 1.8 3.0 47.0

4.20 4 2.4 4.0 51.0


4.27 4 2.4 4.0 55.0

4.33 7 4.1 7.0 62.0

4.40 7 4.1 7.0 69.0

4.47 5 3.0 5.0 74.0

4.53 2 1.2 2.0 76.0

4.60 4 2.4 4.0 80.0

4.67 9 5.3 9.0 89.0

4.73 1 .6 1.0 90.0

4.80 2 1.2 2.0 92.0

4.87 4 2.4 4.0 96.0

4.93 4 2.4 4.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0


The respondents replied as never 5%, rarely 9%, occasionally 11%, often 37% and always 38%. Majority
of the respondents went with often and always in responding to consultants poorly executed design
drawings.

TABLE (4-22): RESPONDENTS AS PER CONSULTANT’S POORLY EXECUTED DESIGN


DRAWINGS

Consultant’s poorly executed design drawings

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 9 5.3 9.0 14.0

Occasionally 11 6.5 11.0 25.0

Often 37 21.9 37.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 10%, occasionally 14%, often 35% and always 36%.
Majority of the respondents went with often and always in responding to consultant’s error, incomplete or
inaccurate pricing documents.
TABLE (4-23): RESPONDENTS AS PER CONSULTANT`S ERROR, INCOMPLETE OR
INACCURATE PRICING DOCUMENTS

Consultant`s Error, incomplete or inaccurate pricing documents

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 10 5.9 10.0 15.0

Occasionally 14 8.3 14.0 29.0

Often 35 20.7 35.0 64.0

Always 36 21.3 36.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 27%, occasionally 13%, often 19% and always 38%.
Majority of the respondents went with always in responding to communication problems by the
consultant.

TABLE (4-24): RESPONDENTS AS PER COMMUNICATION PROBLEMS BY THE


CONSULTANT
communication problems by the consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 27 16.0 27.0 30.0

Occasionally 13 7.7 13.0 43.0

Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 1%, rarely 11%, occasionally 14%, often 34% and always 40%.
Majority of the respondents went with often and always in responding to inadequate site investigation by
consultant before the design period.

TABLE (4-25): RESPONDENTS AS PER INADEQUATE SITE INVESTIGATION BY


CONSULTANT BEFORE THE DESIGN PERIOD

Inadequate site investigation by consultant before the design period


Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 11 6.5 11.0 12.0

Occasionally 14 8.3 14.0 26.0

Often 34 20.1 34.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 6%, rarely 11%, occasionally 10%, often 32% and always 41%.
Majority of the respondents went with often and always in responding to insufficient material
investigation by consultant.

TABLE (4-26): RESPONDENTS AS PER INSUFFICIENT MATERIAL INVESTIGATION BY


CONSULTANT

Insufficient material investigation by consultant

Frequency Percent Valid Percent Cumulative Percent


Valid Never 6 3.6 6.0 6.0

Rarely 11 6.5 11.0 17.0

Occasionally 10 5.9 10.0 27.0

Often 32 18.9 32.0 59.0

Always 41 24.3 41.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 8%, occasionally 18%, often 42% and always 27%. Majority
of the respondents went with often and always in responding to improper construction method by the
consultant.

TABLE (4-27): RESPONDENTS AS PER IMPROPER CONSTRUCTION METHOD BY THE


CONSULTANT

Improper construction method by the consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0


Rarely 8 4.7 8.0 13.0

Occasionally 18 10.7 18.0 31.0

Often 42 24.9 42.0 73.0

Always 27 16.0 27.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 6%, occasionally 18%, often 36% and always 35%. Majority
of the respondents went with often and always in responding to uncertainty in locating pipe positions
underground by consultants.

Table (4-28): Respondents as per Uncertainty in locating pipe positions underground by consultant

Uncertainty in locating pipe positions underground by consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 6 3.6 6.0 11.0

Occasionally 18 10.7 18.0 29.0


Often 36 21.3 36.0 65.0

Always 35 20.7 35.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 0%, rarely 8%, occasionally 20%, often 36% and always 36%. Majority
of the respondents went with often and always in responding to change in design by the consultants.

TABLE (4-29): RESPONDENTS AS PER CHANGE IN DESIGN BY CONSULTANT

Change in design by consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Rarely 8 4.7 8.0 8.0

Occasionally 20 11.8 20.0 28.0

Often 36 21.3 36.0 64.0

Always 36 21.3 36.0 100.0

Total 100 59.2 100.0


Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 10%, occasionally 10%, often 37% and always 38%.
Majority of the respondents went with often and always in responding to conflict between consultants and
contract documents.

TABLE (4-30): RESPONDENTS AS PER CONFLICTS BETWEEN CONSULTANT &


CONTRACT DOCUMENTS

Conflicts between consultant & contract documents

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 10 5.9 10.0 15.0

Occasionally 10 5.9 10.0 25.0

Often 37 21.9 37.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8


Total 169 100.0

The respondents replied as never 2%, rarely 5%, occasionally 15%, often 29% and always 49%. Majority
of the respondents went with always in responding to design complexity from the consultants.

TABLE (4-31): RESPONDENTS AS PER DESIGN COMPLEXITY FROM THE CONSULTANT

Design complexity from the consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 2 1.2 2.0 2.0

Rarely 5 3.0 5.0 7.0

Occasionally 15 8.9 15.0 22.0

Often 29 17.2 29.0 51.0

Always 49 29.0 49.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 1%, rarely 4%, occasionally 16%, often 35% and always 44%. Majority
of the respondents went with often and always in responding to inadequate shop drawing details by the
consultants.
TABLE (4-32): RESPONDENTS AS PER INADEQUATE SHOP DRAWING DETAILS BY THE
CONSULTANT

Inadequate shop drawing details by the consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 4 2.4 4.0 5.0

Occasionally 16 9.5 16.0 21.0

Often 35 20.7 35.0 56.0

Always 44 26.0 44.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 10%, occasionally 14%, often 35% and always 36%.
Majority of the respondents went with often and always.

TABLE (4-33): RESPONDENTS AS PER LACK OF CONSULTANT'S KNOWLEDGE OF


AVAILABLE

Lack of consultant's knowledge of available


Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 10 5.9 10.0 15.0

Occasionally 14 8.3 14.0 29.0

Often 35 20.7 35.0 64.0

Always 36 21.3 36.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 2%, rarely 27%, occasionally 14%, often 19% and always 38%.
Majority of the respondents went with always.

TABLE (4-34): RESPONDENTS AS PER DESIGN DISCREPANCIES BY THE CONSULTANT

Design discrepancies by the consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 2 1.2 2.0 2.0


Rarely 27 16.0 27.0 29.0

Occasionally 14 8.3 14.0 43.0

Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 2%, rarely 11%, occasionally 20%, often 39% and always 28%.
Majority of the respondents went with often and always.

TABLE (4-35): RESPONDENTS AS PER CONSULTANT’S UNFAMILIARITY WITH LOCAL


CONDITIONS

Consultant’s unfamiliarity with local conditions

Frequency Percent Valid Percent Cumulative Percent

Valid Never 2 1.2 2.0 2.0

Rarely 11 6.5 11.0 13.0

Occasionally 20 11.8 20.0 33.0


Often 39 23.1 39.0 72.0

Always 28 16.6 28.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 2%, rarely 28%, occasionally 13%, often 19% and always 38%.
Majority of the respondents went with always.

TABLE (4-36): RESPONDENTS AS PER ERRORS AND OMISSIONS IN DESIGN BY THE


CONSULTANT

Errors and omissions in design by the consultant

Frequency Percent Valid Percent Cumulative Percent

Valid Never 2 1.2 2.0 2.0

Rarely 28 16.6 28.0 30.0

Occasionally 13 7.7 13.0 43.0

Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0


Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

4.3.3.3. RELATED TO CONTRACTORS

In this portion of analysis classification has been done of data of responses which relate to the contractors.
The data has been structured statistically based on the responses and has been classified as percentage.
The detailed explanation and classification of percentage of responses shall be seen below in detail.

TABLE (4-37): RESPONDENTS AS PER RELATED TO CONTRACTORS

Related to Contractors

Frequency Percent Valid Percent Cumulative Percent

Valid 1.44 2 1.2 2.0 2.0

1.56 1 .6 1.0 3.0

1.63 1 .6 1.0 4.0

1.69 1 .6 1.0 5.0

1.75 1 .6 1.0 6.0

1.88 1 .6 1.0 7.0


2.31 1 .6 1.0 8.0

2.38 1 .6 1.0 9.0

2.44 1 .6 1.0 10.0

2.56 2 1.2 2.0 12.0

2.81 2 1.2 2.0 14.0

2.88 1 .6 1.0 15.0

2.94 1 .6 1.0 16.0

3.00 2 1.2 2.0 18.0

3.06 1 .6 1.0 19.0

3.13 2 1.2 2.0 21.0

3.25 1 .6 1.0 22.0

3.31 1 .6 1.0 23.0

3.44 1 .6 1.0 24.0

3.50 2 1.2 2.0 26.0


3.56 1 .6 1.0 27.0

3.63 3 1.8 3.0 30.0

3.75 2 1.2 2.0 32.0

3.81 2 1.2 2.0 34.0

3.88 1 .6 1.0 35.0

3.94 1 .6 1.0 36.0

4.00 2 1.2 2.0 38.0

4.06 3 1.8 3.0 41.0

4.13 5 3.0 5.0 46.0

4.19 3 1.8 3.0 49.0

4.25 5 3.0 5.0 54.0

4.31 10 5.9 10.0 64.0

4.38 7 4.1 7.0 71.0

4.44 3 1.8 3.0 74.0


4.50 4 2.4 4.0 78.0

4.56 4 2.4 4.0 82.0

4.63 5 3.0 5.0 87.0

4.69 2 1.2 2.0 89.0

4.75 4 2.4 4.0 93.0

4.81 2 1.2 2.0 95.0

4.88 2 1.2 2.0 97.0

4.94 2 1.2 2.0 99.0

5.00 1 .6 1.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 17%, occasionally 15%, often 35% and always 30%.
Majority of the respondents went with often and always.

TABLE (4-38): RESPONDENTS AS PER LACK OF CONTRACTOR'S INVOLVEMENT IN


DESIGN
Lack of contractor's involvement in design

Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 17 10.1 17.0 20.0

Occasionally 15 8.9 15.0 35.0

Often 35 20.7 35.0 70.0

Always 30 17.8 30.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 7%, rarely 10%, occasionally 9%, often 41% and always 33%. Majority
of the respondents went with often and always.

TABLE (4-39): RESPONDENTS AS PER UNAVAILABILITY OF EQUIPMENT DUE TO


CONTRACTOR

Unavailability of equipment due to contractor

Frequency Percent Valid Percent Cumulative Percent


Valid Never 7 4.1 7.0 7.0

Rarely 10 5.9 10.0 17.0

Occasionally 9 5.3 9.0 26.0

Often 41 24.3 41.0 67.0

Always 33 19.5 33.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 6%, rarely 7%, occasionally 16%, often 30% and always 41%. Majority
of the respondents went with often and always.

TABLE (4-40): RESPONDENTS AS PER UNAVAILABILITY OF SKILLS MANPOWER BY


THE CONTRACTOR

Unavailability of skills manpower by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 6 3.6 6.0 6.0

Rarely 7 4.1 7.0 13.0


Occasionally 16 9.5 16.0 29.0

Often 30 17.8 30.0 59.0

Always 41 24.3 41.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 18%, occasionally 12%, often 41% and always 26%.
Majority of the respondents went with often and always.

TABLE (4-41): RESPONDENTS AS PER SHORTAGE OF MATERIALS PROVIDED BY


CONTRACTOR

Shortage of materials provided by contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 18 10.7 18.0 21.0

Occasionally 12 7.1 12.0 33.0

Often 41 24.3 41.0 74.0


Always 26 15.4 26.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 6%, rarely 11%, occasionally 10%, often 32% and always 41%.
Majority of the respondents went with often and always.

TABLE (4-42): RESPONDENTS AS PER FINANCIAL DIFFICULTIES FACED BY THE


CONTRACTOR

Financial difficulties faced by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 6 3.6 6.0 6.0

Rarely 11 6.5 11.0 17.0

Occasionally 10 5.9 10.0 27.0

Often 32 18.9 32.0 59.0

Always 41 24.3 41.0 100.0

Total 100 59.2 100.0


Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 8%, occasionally 18%, often 42% and always 27%. Majority
of the respondents went with often.

TABLE (4-43): RESPONDENTS AS PER SHORTAGE OF TECHNICAL PROFESSIONALS IN


THE CONTRACTOR’S ORGANIZATION

Shortage of technical professionals in the contractor’s organization

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 8 4.7 8.0 13.0

Occasionally 18 10.7 18.0 31.0

Often 42 24.9 42.0 73.0

Always 27 16.0 27.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0


The respondents replied as never 5%, rarely 20%, occasionally 16%, often 34% and always 25%.
Majority of the respondents went with often and always.

TABLE (4-44): RESPONDENTS AS PER INSUFFICIENT COORDINATION AMONG THE


PARTIES BY THE CONTRACTOR

Insufficient coordination among the parties by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 20 11.8 20.0 25.0

Occasionally 16 9.5 16.0 41.0

Often 34 20.1 34.0 75.0

Always 25 14.8 25.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 10%, occasionally 14%, often 35% and always 36%.
Majority of the respondents went with often and always.

TABLE (4-45): RESPONDENTS AS PER CONTRACTOR DID NOT FOLLOWED SAFETY


RULES AND REGULATIONS ASSIGNED BY CONTRACTOR’S ORGANIZATION
Contractor did not followed Safety rules and regulations assigned by contractor’s organization

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 10 5.9 10.0 15.0

Occasionally 14 8.3 14.0 29.0

Often 35 20.7 35.0 64.0

Always 36 21.3 36.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 0%, rarely 6%, occasionally 22%, often 31% and always 41%. Majority
of the respondents went with often and always.

TABLE (4-46): RESPONDENTS AS PER INCOMPETENT TECHNICAL STAFF ASSIGNED BY


CONTRACTOR

Incompetent technical staff assigned by contractor

Frequency Percent Valid Percent Cumulative Percent


Valid Rarely 6 3.6 6.0 6.0

Occasionally 22 13.0 22.0 28.0

Often 31 18.3 31.0 59.0

Always 41 24.3 41.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 1%, rarely 8%, occasionally 19%, often 34% and always 38%. Majority
of the respondents went with often and always.

TABLE (4-47): RESPONDENTS AS PER IMPROPER TECHNICAL STUDY BY THE


CONTRACTOR DURING THE BIDDING STAGE

Improper technical study by the contractor during the bidding stage

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 8 4.7 8.0 9.0

Occasionally 19 11.2 19.0 28.0


Often 34 20.1 34.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 6%, occasionally 18%, often 36% and always 35%. Majority
of the respondents went with often and always.

TABLE (4-48): RESPONDENTS AS PER POOR PLANNING AND SCHEDULING OF THE


PROJECT BY THE CONTRACTOR

Poor planning and scheduling of the project by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 6 3.6 6.0 11.0

Occasionally 18 10.7 18.0 29.0

Often 36 21.3 36.0 65.0

Always 35 20.7 35.0 100.0


Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 6%, occasionally 18%, often 36% and always 35%. Majority
of the respondents went with often and always.

TABLE (4-49): RESPONDENTS AS PER IMPROPER HANDLING OF THE PROJECT


PROGRESS BY THE CONTRACTOR

Improper handling of the project progress by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 6 3.6 6.0 6.0

Rarely 7 4.1 7.0 13.0

Occasionally 16 9.5 16.0 29.0

Often 30 17.8 30.0 59.0

Always 41 24.3 41.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8


Total 169 100.0

The respondents replied as never 1%, rarely 6%, occasionally 19%, often 32% and always 42%. Majority
of the respondents went with often and always.

TABLE (4-50): RESPONDENTS AS PER INEFFECTIVE QUALITY CONTROL BY THE


CONTRACTOR

Ineffective quality control by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 6 3.6 6.0 7.0

Occasionally 19 11.2 19.0 26.0

Often 32 18.9 32.0 58.0

Always 42 24.9 42.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 0%, rarely 6%, occasionally 21%, often 33% and always 40%. Majority
of the respondents went with often and always.
TABLE (4-51): RESPONDENTS AS PER USE OF UNACCEPTABLE CONSTRUCTION
TECHNIQUES BY THE CONTRACTOR

Use of unacceptable construction techniques by the contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Rarely 6 3.6 6.0 6.0

Occasionally 21 12.4 21.0 27.0

Often 33 19.5 33.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 9%, occasionally 11%, often 37% and always 38%. Majority
of the respondents went with often and always.

TABLE (4-52): RESPONDENTS AS PER POOR PROCUREMENT PROCESS BY THE


CONTRACTOR

Poor procurement process by the contractor

Frequency Percent Valid Percent Cumulative Percent


Valid Never 5 3.0 5.0 5.0

Rarely 9 5.3 9.0 14.0

Occasionally 11 6.5 11.0 25.0

Often 37 21.9 37.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 9%, rarely 5%, occasionally 14%, often 32% and always 40%. Majority
of the respondents went with often and always.

TABLE (4-53): RESPONDENTS AS PER LACK OF COMMUNICATION BY CONTRACTOR

Lack of Communication by contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 5 3.0 5.0 14.0


Occasionally 14 8.3 14.0 28.0

Often 32 18.9 32.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

Most of the responses went against the contractors and showed that major inefficiency is because of the
contractors.

4.3.3.4. RELATED TO OTHER CHANGES

In the table below the relative changes in responses based on other factors of the projects have been
discussed.

TABLE (4-54): RESPONDENTS AS PER RELATED TO OTHER CHANGES

Other Changes

Frequency Percent Valid Percent Cumulative Percent

Valid 1.29 1 .6 1.0 1.0

1.43 2 1.2 2.0 3.0


1.57 2 1.2 2.0 5.0

1.71 1 .6 1.0 6.0

1.86 2 1.2 2.0 8.0

2.29 1 .6 1.0 9.0

2.43 2 1.2 2.0 11.0

2.57 4 2.4 4.0 15.0

2.71 3 1.8 3.0 18.0

2.86 1 .6 1.0 19.0

3.00 2 1.2 2.0 21.0

3.14 4 2.4 4.0 25.0

3.43 3 1.8 3.0 28.0

3.57 4 2.4 4.0 32.0

3.71 4 2.4 4.0 36.0

3.86 5 3.0 5.0 41.0


4.00 7 4.1 7.0 48.0

4.14 13 7.7 13.0 61.0

4.29 13 7.7 13.0 74.0

4.43 9 5.3 9.0 83.0

4.57 11 6.5 11.0 94.0

4.71 4 2.4 4.0 98.0

5.00 2 1.2 2.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 28%, occasionally 12%, often 19% and always 38%.
Majority of the respondents went with always.

TABLE (4-55): RESPONDENTS AS PER CHANGE IN GOVERNMENT REGULATIONS

Change in government regulations

Frequency Percent Valid Percent Cumulative Percent


Valid Never 3 1.8 3.0 3.0

Rarely 28 16.6 28.0 31.0

Occasionally 12 7.1 12.0 43.0

Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 1%, rarely 11%, occasionally 14%, often 34% and always 40%.
Majority of the respondents went with often and always.

TABLE (4-55): RESPONDENTS AS PER SEVERE WEATHER CONDITIONS ON THE JOB


SITE

Severe weather conditions on the job site

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 11 6.5 11.0 12.0


Occasionally 14 8.3 14.0 26.0

Often 34 20.1 34.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 9%, rarely 27%, occasionally 17%, often 32% and always 15%.
Majority of the respondents went with often.

TABLE (4-56): RESPONDENTS AS PER CHANGE IN ECONOMIC CONDITIONS

Change in economic conditions

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 27 16.0 27.0 36.0

Occasionally 17 10.1 17.0 53.0

Often 32 18.9 32.0 85.0


Always 15 8.9 15.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 0%, rarely 5%, occasionally 14%, often 32% and always 40%. Majority
of the respondents went with often and always.

TABLE (4-57): RESPONDENTS AS PER UNFORESEEN PROBLEMS

Unforeseen problems

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 5 3.0 5.0 14.0

Occasionally 14 8.3 14.0 28.0

Often 32 18.9 32.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0


Missing System 69 40.8

Total 169 100.0

The respondents replied as never 4%, rarely 8%, occasionally 17%, often 34% and always 37%. Majority
of the respondents went with often and always.

TABLE (4-58): RESPONDENTS AS PER POLITICAL AND ECONOMIC FACTOR

Political and economic factor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 4 2.4 4.0 4.0

Rarely 8 4.7 8.0 12.0

Occasionally 17 10.1 17.0 29.0

Often 34 20.1 34.0 63.0

Always 37 21.9 37.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0


The respondents replied as never 3%, rarely 11%, occasionally 15%, often 42% and always 29%.
Majority of the respondents went with often and always.

TABLE (4-59): RESPONDENTS AS PER DIFFICULTIES IN OBTAINING WORK PERMITS

Difficulties in obtaining work permits

Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 11 6.5 11.0 14.0

Occasionally 15 8.9 15.0 29.0

Often 42 24.9 42.0 71.0

Always 29 17.2 29.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 4%, rarely 4%, occasionally 24%, often 42% and always 26%. Majority
of the respondents went with often and always.

TABLE (4-60): RESPONDENTS AS PER MATERIALS PRICE FLUCTUATIONS


Materials price fluctuations

Frequency Percent Valid Percent Cumulative Percent

Valid Never 4 2.4 4.0 4.0

Rarely 4 2.4 4.0 8.0

Occasionally 24 14.2 24.0 32.0

Often 42 24.9 42.0 74.0

Always 26 15.4 26.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

4.3.4. EFFECTS OF VARIATION

The effects of variation of data have been shown in the table below.

TABLE (4-61): RESPONDENTS AS PER EFFECTS OF VARIATIONS

Effects of variations

Frequency Percent Valid Percent Cumulative Percent


Valid 1.38 4 2.4 4.0 4.0

1.46 1 .6 1.0 5.0

1.54 1 .6 1.0 6.0

1.62 1 .6 1.0 7.0

2.23 1 .6 1.0 8.0

2.46 4 2.4 4.0 12.0

2.54 3 1.8 3.0 15.0

2.69 2 1.2 2.0 17.0

2.77 2 1.2 2.0 19.0

2.85 2 1.2 2.0 21.0

3.23 3 1.8 3.0 24.0

3.31 1 .6 1.0 25.0

3.38 1 .6 1.0 26.0

3.46 3 1.8 3.0 29.0


3.54 1 .6 1.0 30.0

3.62 2 1.2 2.0 32.0

3.69 2 1.2 2.0 34.0

3.92 5 3.0 5.0 39.0

4.00 3 1.8 3.0 42.0

4.08 5 3.0 5.0 47.0

4.15 8 4.7 8.0 55.0

4.23 10 5.9 10.0 65.0

4.31 4 2.4 4.0 69.0

4.38 7 4.1 7.0 76.0

4.46 8 4.7 8.0 84.0

4.54 5 3.0 5.0 89.0

4.62 5 3.0 5.0 94.0

4.69 1 .6 1.0 95.0


4.77 3 1.8 3.0 98.0

4.92 2 1.2 2.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 9%, occasionally 11%, often 37% and always 38%. Majority
of the respondents went with often and always.

TABLE (4-62): RESPONDENTS AS PER INCREASE IN THE COST OF THE PROJECTS

Increase in the cost of the projects

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 9 5.3 9.0 14.0

Occasionally 11 6.5 11.0 25.0

Often 37 21.9 37.0 62.0

Always 38 22.5 38.0 100.0


Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 9%, occasionally 15%, often 48% and always 23%. Majority
of the respondents went with often.

TABLE (4-63): RESPONDENTS AS PER INCREASE IN DURATION OF INDIVIDUAL


ACTIVITIES

Increase in duration of individual activities

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 9 5.3 9.0 14.0

Occasionally 15 8.9 15.0 29.0

Often 48 28.4 48.0 77.0

Always 23 13.6 23.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8


Total 169 100.0

The respondents replied as never 5%, rarely 6%, occasionally 18%, often 36% and always 35%. Majority
of the respondents went with often and always.

TABLE (4-64): RESPONDENTS AS PER DELAY IN COMPLETION SCHEDULE

Delay in completion schedule

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 6 3.6 6.0 11.0

Occasionally 18 10.7 18.0 29.0

Often 36 21.3 36.0 65.0

Always 35 20.7 35.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 6%, rarely 7%, occasionally 16%, often 30% and always 41%. Majority
of the respondents went with often and always.
TABLE (4-65): RESPONDENTS AS PER DELAY IN PAYMENT

Delay in payment

Frequency Percent Valid Percent Cumulative Percent

Valid Never 6 3.6 6.0 6.0

Rarely 7 4.1 7.0 13.0

Occasionally 16 9.5 16.0 29.0

Often 30 17.8 30.0 59.0

Always 41 24.3 41.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 18%, occasionally 12%, often 41% and always 26%.
Majority of the respondents went with often.

TABLE (4-66): RESPONDENTS AS PER DEMOLITION AND RE – WORK

Demolition and re – work


Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 18 10.7 18.0 21.0

Occasionally 12 7.1 12.0 33.0

Often 41 24.3 41.0 74.0

Always 26 15.4 26.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 5%, rarely 10%, occasionally 14%, often 35% and always 36%.
Majority of the respondents went with often and always.

TABLE (4-67): RESPONDENTS AS PER DECREASE IN PRODUCTIVITY OF WORKERS

Decrease in productivity of workers

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0


Rarely 10 5.9 10.0 15.0

Occasionally 14 8.3 14.0 29.0

Often 35 20.7 35.0 64.0

Always 36 21.3 36.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 28%, occasionally 12%, often 19% and always 38%.
Majority of the respondents went with often and always.

TABLE (4-68): RESPONDENTS AS PER INCREASE IN OVERHEAD EXPENSES

Increase in overhead expenses

Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 28 16.6 28.0 31.0

Occasionally 12 7.1 12.0 43.0


Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 9%, rarely 27%, occasionally 17%, often 32% and always 15%.
Majority of the respondents went with often.

TABLE (4-69): RESPONDENTS AS PER DECREASE IN QUALITY OF WORK

Decrease in quality of work

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 27 16.0 27.0 36.0

Occasionally 17 10.1 17.0 53.0

Often 32 18.9 32.0 85.0

Always 15 8.9 15.0 100.0


Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 9%, rarely 5%, occasionally 14%, often 32% and always 40%. Majority
of the respondents went with often and always.

TABLE (4-70): RESPONDENTS AS PER DELAY OF MATERIALS AND TOOLS

Delay of materials and tools

Frequency Percent Valid Percent Cumulative Percent

Valid Never 9 5.3 9.0 9.0

Rarely 5 3.0 5.0 14.0

Occasionally 14 8.3 14.0 28.0

Often 32 18.9 32.0 60.0

Always 40 23.7 40.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8


Total 169 100.0

The respondents replied as never 5%, rarely 9%, occasionally 11%, often 37% and always 38%. Majority
of the respondents went with often and always.

TABLE (4-71): RESPONDENTS AS PER DISPUTES BETWEEN CLIENTS AND


CONTRACTOR

Disputes between clients and contractor

Frequency Percent Valid Percent Cumulative Percent

Valid Never 5 3.0 5.0 5.0

Rarely 9 5.3 9.0 14.0

Occasionally 11 6.5 11.0 25.0

Often 37 21.9 37.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 1%, rarely 7%, occasionally 19%, often 35% and always 38%. Majority
of the respondents went with often and always.
TABLE (4-72): RESPONDENTS AS PER HOLD ON WORK IN OTHER AREAS

Hold on work in other areas

Frequency Percent Valid Percent Cumulative Percent

Valid Never 1 .6 1.0 1.0

Rarely 7 4.1 7.0 8.0

Occasionally 19 11.2 19.0 27.0

Often 35 20.7 35.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 18%, occasionally 15%, often 34% and always 30%.
Majority of the respondents went with often and always.

TABLE (4-73): RESPONDENTS AS PER ADDITIONAL MONEY FOR CONTRACTOR

Additional money for contractor


Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0

Rarely 18 10.7 18.0 21.0

Occasionally 15 8.9 15.0 36.0

Often 34 20.1 34.0 70.0

Always 30 17.8 30.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The respondents replied as never 3%, rarely 27%, occasionally 13%, often 19% and always 38%.
Majority of the respondents went with often and always.

TABLE (4-74): RESPONDENTS AS PER DECREASE IN PRODUCTIVITY

Decrease in productivity

Frequency Percent Valid Percent Cumulative Percent

Valid Never 3 1.8 3.0 3.0


Rarely 27 16.0 27.0 30.0

Occasionally 13 7.7 13.0 43.0

Often 19 11.2 19.0 62.0

Always 38 22.5 38.0 100.0

Total 100 59.2 100.0

Missing System 69 40.8

Total 169 100.0

The statistical data and classification of the data which has been gathered through the responses has been
shown below.

TABLE (4-75): STATISTICS OF DATA

Statistics

Academic Degree Type of


Position Experience Held Organization

N Valid 100 100 100 100

Missing 69 69 69 69

Mode 3 3 2 1a
Range 4 3 2 1

Percentiles 25 2.00 2.00 1.00 1.00

50 3.00 3.00 2.00 1.50

75 4.00 3.00 3.00 2.00

a. Multiple modes exist. The smallest value is shown

From the data which has been evaluated it is clear that the impact in the delay and hurdle arise mainly
because of the change in plans. The change can be initiated by either the client, consultant or the
contractor. All of the individuals are responsible for the delay as they are inefficient and don’t design the
plans through appropriate strategic planning required for the project.

You might also like