Professional Documents
Culture Documents
The guiding obligations and good practices which determine whether the project is genuinely being
managed using PRINCE2. If a project does not apply all seven principles, it is not a PRINCE2
project. The principles are:
Aspects of project management that must be addressed continually and in parallel throughout the
project. They explain the specific treatment required by PRINCE2 for various project management
disciplines and why they are necessary. Any project manager who gives thorough attention to these
themes will fulfill the role in a professional manner. The themes are:
All 7 themes must be applied in a project but they should be tailored according to the scale,
nature and complexity of the project concerned.
Processes: Definition
Describe a step-wise progression through the project lifecycle, from getting started to project
closure. Each process provides checklists of recommended activities, products and related
responsibilities.
A process takes one or more defined inputs and turns them into defined outputs.
A process provides the set of activities required to direct, manage and deliver a project
successfully.
Processes: The Seven Processes
1. Starting up a project
2. Directing a project
3. Initiating a project
4. Controlling a Stage
5. Managing Product Delivery
6. Managing a Stage Boundary
7. Closing a Project
1. Starting up a project
a. Purpose:
i. To ensure that the prerequisites for initiating a project are in place by
answering: do we have a viable and worthwhile project?
ii. To verify that the project is worthwhile and viable.
2. Directing a project
a. Purpose: To enable the Project Board to be accountable for the project’s success by
making key decisions and exercising overall control while delegating day-to-day
management of the project to the Project Manager.
3. Initiating a project
a. Purpose: To establish solid foundations for the project, enabling the organization
to understand the work that needs to be done to deliver the project’s products before
committing to a significant spend.
4. Controlling a Stage
a. Purpose: To assign work to be done, monitor such work, deal with issues, report
progress to the Project Board, and take corrective actions to ensure that the stage
remains within tolerance.
5. Managing Product Delivery
a. Purpose: To control the link between the Project Manager and the Team
Manager(s), by placing formal requirements on accepting, executing and delivering
project work.
6. Managing a Stage Boundary
a. Purpose: To enable the Project Board to be provided with sufficient information by
the Project Manager so that it can review the success of the current stage, approve
the next Stage Plan, and confirm continued business justification and acceptability
of the risks.
7. Closing a Project
a. To provide a fixed point at which acceptance for the project product is confirmed,
and to recognize that objectives set out in the original Project Initiation
Documentation have been achieved (or approved changes to the objectives have
been achieved), or that the project has nothing more to contribute.
Process 1: Starting up a Project
Purpose:
1. To ensure that the prerequisites for initiating a project are in place by answering: do we
have a viable and worthwhile project?
2. To verify that the project is worthwhile and viable.
Stage: Pre-Project
Activities: Outputs
Purpose:
1. To enable the Project Board to be accountable for the project’s success by making key
decisions and exercising overall control while delegating day-to-day management of the
project to the Project Manager
Level: Directing
1. Authorize Initiation
2. Authorize the project
3. Authorize a Stage or Exception Plan
4. Give ad hoc direction
5. Authorize project closure
Purpose:
1. To establish solid foundations for the project, enabling the organization to understand the
work that needs to be done to deliver the project’s products before committing to a
significant spend.
Stage: Initiation
Level: Managing
Activities: Outputs
Purpose:
1. To assign work to be done, monitor such work, deal with issues, report progress to the
Project Board, and take corrective actions to ensure that the stage remains within tolerance.
Level: Managing
1. Work Packages
a. Authorize a Work Package
b. Review Work Package Status
c. Receive Completed Work Packages
2. Monitoring and reporting
a. Review the Stage Status
b. Report Highlights
3. Issues
a. Capture and examine issues and risks
b. Escalate issues and risks
c. Take Corrective Action
Activities: Outputs
1. Work Packages
a. Authorize a Work Package
i. Output:
1. Work Packages
2. Updated current stage plan
3. Updated Configuration Item Records
4. Updated Quality Register
5. Updated Risk Register
6. Updated Issue Register
7. Authority to deliver a work package
b. Review Work Package Status
i. Output
1. updated Stage Plan
2. Updated Configuration Item Records
3. Updated Risk Register
4. Updated Issue Register
5. Updated Work Package
c. Receive Completed Work Packages
i. Output
1. Updated configuration item records
2. Updated Stage Plan
2. Monitoring and reporting
a. Review the Stage Status
i. Stage boundary approaching
ii. Project end approaching
iii. Request for advice
iv. Updated Risk Register
v. Updated Issue Register
vi. Updated Stage Plan
vii. Updated Lessons Log
viii. Updated Issue Report
b. Report Highlights
i. Highlight Report
3. Issues
a. Capture and examine issues and risks
i. Output:
1. Issue Report
2. Updated Daily Log
3. Updated Issue Register
4. Updated Risk Register
5. Request for advice
b. Escalate issues and risks
i. Output:
1. Exception Report
2. updated Issue Register
3. Updated Risk Register
4. Updated Issue Report
5. Exception Raised
c. Take Corrective Action
i. Updated Daily Log
ii. updated Issue Register
iii. Updated Risk Register
iv. Updated Issue Report
v. Updated Stage Plan
vi. Updated Configuration Item Records
vii. Corrective Action
Process 5: Managing Product Delivery
Purpose:
1. To control the link between the Project Manager and the Team Managers, by placing
formal requirements on accepting, executing and delivering project work.
Level: Delivering
Activities: Outputs
Purpose:
1. To enable the Project Board to be provided with sufficient information by the Project
Manager so that it can review the success of the current stage, approve the next Stage Plan,
review the updated project plan, and confirm continued business justification and
acceptability of the risks.
Level: Managing
The 5 Activities:
Activities: Outputs
Purpose:
1. To provide a fixed point at which acceptance for the project product is confirmed, and to
recognize that objectives set out in the original Project Initiation Documentation have been
achieved, or that the project has nothing more to contribute.
Level: Managing
Activities: Outputs