SUB-STATION EARTHING SYSTEM-[11 KV]

PRJECT :- Electrical Distribution Works( 433v & 11KV network


Extension) to feed power supply to the unit houses at Mudhai.
CLIENT :- RAECO
CONTRACTOR : -Al Fajer Al Jadid Trade. & Cont.Co
LOCATION :- Mudhai - Social Houses
Earthling No. of No. of Sets Additional Rod Total No. of Rods
System Rods/Set
NE 2 1 2
BE 2 1 2
RMU 2 1 2
FPE 2 1 2
Spacing between Rods: - 2 Mts. Soil Condition: -

Instrument Used:

Make : Kyoritsu
Model: 3122
Sino : 1329680

Sketch Layout:
Earthling Test Result:
F PE
R TX
P
M RMU E
U

NE

TX E

Earthling Test Result


First Reading Final Reading
NE 4.8 Ohm
RMU E 4.6 Ohm
TX E 4.6 Ohm
FPE 4.8 Ohm
Remarks:
Conducted By Witnessed By