A.

Informasi Network

No. Kegiatan Durasi Kegiatan Biaya Pekerjaan


1 A 2 8 6
2 B 3 A 9 6
3 C 4 A 12 12
4 D 5 A,C 20 10
5 E 5 B,D 15 15
6 F 4 D,E,G 12 16
7 G 6 C 12 12
8 H 8 F,G 24 8

B. Network Plannng Diagram


2 B 5
B
2 3 5 5

0 A 2
START A
3 2 5

2
2 C 6
C
5 4 9

C. Bautlah Bar- Chart


No Kegiatan Durasi EST LST EFT LFT Biaya 1 2 3
1 A 2 0 3 2 5 8 4 4
2 B 3 2 2 5 5 9 3
3 C 4 2 5 6 9 12 3
4 D 5 6 6 11 11 20
5 E 5 6 6 11 11 15
6 F 4 11 11 15 15 12
7 G 6 6 9 12 15 12
8 H 8 15 15 23 23 24
112 4.0 4.0 6.0
0 4.0 8.0 14.0
Pekerjaan
6
6
12
10
15
16
12
8

5 6 E 11
E
6 5 11 11

11

6 D 11 11 F 15 15 15 H 23
D F H

6 6 5 11 11 11 4 15 15 8 23

12

6 G 12
G
9 6 15
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

3 3
3 3 3
4 4 4 4 4
3 3 3 3 3
3 3
2 2 2 2 2 2

6.0 6.0 3.0 6.0 6.0 6.0 6.0 6.0 5.0 3.0 3.0 3.0 3.0 3.0 3.0
20.0 26.0 29.0 35.0 41.0 47.0 53.0 59.0 64.0 67.0 70.0 73.0 76.0 79.0 82.0
FINISH
19 20 21 22 23 24

3 3

3 3 3 3
3.0 3.0 3.0 3.0 3.0 3.0
85.0 88.0 91.0 94.0 97.0 100.0