You are on page 1of 49

Technical Training

Manual
INDEX

1. Technical Training Calendar for Year 2008-09

2. Flow Chart of Training & Training Effectiveness

3. Formwork

4. Concrete Technology

5. Project Operations- S Cadre

6. Introduction to Contracts

7. Introduction to Project Management

8. QA/QC on site

9. Safety in Civil Construction

10. Introduction to PMV Works on Site

11. Enterprise Resource Planning (ERP)

12. Quality Management System (QMS)

13. Finishes

14. Contract Management

15. Project Operation- E Cadre

16. Design and Build


Flow chart for Technical Training
The Technical Training has been divided into two Cadres- S and E.

Step 1:
At the beginning of the financial year the schedule for the training is sent
to all GM’s and the HR heads in the regions. Care is taken to see that
only one training is conducted in a region per month.

Step 2:
The master trainer list is sent to all regions along with a request to
choose the regional trainers. The regional trainers in future will take over
from the master trainers and conduct training for their respective
regions. The presentation for the training module will be prepared by the
Master Trainer which will remain as standard across regions.

Step 3:
At the beginning of each month a mail is sent out from the HO Technical
Training department reminding them of the training to be conducted in
the region for that month. Consent is also taken from the GM regarding
the training.

Step 4:
The participant list is sent by the RO to the HO for information.

Step 5:
The training is conducted on the date as agreed by the RO. After the
training is over feedback is taken from the participants. A short test is
conducted by the trainer to assess the comprehension of the training.

Step 6:
The feedback form, test papers are sent to the HO by the RO. The data
on the same is compiled at the HO and records are maintained.

Step 7:
Three months after the training is conducted a training effectiveness
form is sent to the RO to be forwarded to the superior of the participant.
The form tries to capture the improvement of the individual on site after
training. The forms are compiled in the HO and a report goes out to the
region giving them a complete insight into the training
Formwork

Duration: The training session is for 2 days with 3 workshops.

Eligibility: The training is for site engineers. The participants will


be essentially S & E Cadre people who are on Project
Sites.

Key Features:

1. Requisites of a good formwork system on site and implication on


Quality.

2. Knowledge of formwork systems and its components being used in


the organization.

3. The quality requirements of formwork.

4. An Introduction to formwork design, planning & practical


implementation.

5. Workshop on preparing scheme drawings and Material


Quantification.

6. Understanding of Shuttering Usage Ratio and Labor Productivity.

7. Costing of formwork –Material Cost, System and consumable


concept, impact of extended stay on cost of material on site.

8. Good housekeeping & storage practices to reduce wastage cost.

9. Safe practices in Formwork.

10. Case Studies involving minimum cycle time & challenging


designs.

The training is followed by an assessment test.


Curriculum:

1. Introduction
(a) What is formwork?
(b) Requirements of good formwork
(c) Materials used in Formwork
(d) Factors to be considered in design

2. Timber Formwork
(a) Components of Timber Formwork
(b) Design of formwork for footings
(c) Design for Columns
(d) Design for Walls
(e) Design for beam sides / bottoms
(f) Design for slab soffits

3. Proprietary systems for staging / formwork


(a) Props and Acrow spans
(i) Design for beam bottom
(ii) Design for slab soffits
(b) H-frames
(i) Design for beam bottoms
(ii) Design for slab soffits
(c) Cup lock system
(i) Design for beam bottoms
(ii) Design for slab soffits
(d) DOKA System
(i) For columns and walls
(ii) For beams and slabs

4. Formwork for other elements


(a) Staircases
(b) Circular columns
(c) Precast elements – Kerbs, lintels
(d) Cantilever slabs /beams
(e) Waffle slabs
5. Introduction to special formwork
(a) MIVAN Tunnel system
(b) Slipforming
(c) Domes
(d) Tableform system

6. Quality Requirements
(a) Checking line, level, plumb and finish in footings, columns,
walls, beams, slabs
(b) Corrective measures
(c) Special care for water tight structures, pumping

7. Deshuttering
(a) Deshuttering period for various elements
(b) Sequence of deshuttering of slab soffits

8. Planning of Formwork
(a) Understanding of cycle time and repetitions
(b) Wall beams and slabs

9. Productivity
(a) Understanding shuttering usage Ratio, Labour productivity
(b) Measures to increase productivity

10. Introduction to costing


(a) Concept of depreciation
(b) Elements of costing of formwork – labour, materials, plant,
etc.
(c) How the tender direct cost is worked out

11. Care of Formwork


(a) Care in storage
(b) Care in handling especially during deshuttering
(c) Reconciliation of materials
12. Safety
(a) Shoring in unsafe excavation
(c) Use of PPE – helmets, gloves, safety shoes, safety harness,
nets
(d) Precautions when working at heights
(e) Provision of access – staircases, platforms, gangways

13. Case Studies


(a) One where min. cycle time was achieved
(b) On involving design challenge.

14. Discussions & lessons learnt

15. IN THE SITE:


(a) Demonstration of erection of columns shuttering
Demonstration of deshuttering of slab
Concrete Technology

Duration: The training session is of 1.5 days.

Eligibility: The training is for site engineers in the S Cadre who


are in core execution.

Key Features:

1. Constituents of concrete like different types of cement, Additives,


different properties & requirements of concrete as per IS Codes.

2. Complete idea of IS Code for mix Design of Concrete and how


higher durability and strength can be obtained through it.

3. Safe handling & Pouring of concrete on various surfaces. An in-


depth knowledge of how Quality is achieved and how testing of
concrete is done.

4. Control of wastages in cement, sand, aggregates which affect the


costing of the project.

Case Studies of high and large pours are discussed.

The training is followed by an assessment test.

Curriculum:

1) Concrete
(a) Constituents of concrete
(b) Introduction to different types of cement
(c) Introduction to additives
(d) Properties and requirements of concrete (As per IS)
- Durability
- Workability
- Density
2) Mix design for concrete
(a) Introduction to design of mix
(b) Effect of variation in constituents
(c) Design for waterproof concrete
(d) Fly Ash concrete
(e) Temperature controlled concrete

3) Mixing of concrete
(a) In Mixers
(b) Using mini batching plants
(c) Batching plants

4) Transport and placing of concrete


(a) Using wheel barrows, mini dumpers
(b) Transit mixers
(c) Pouring in :
i) Foundation and rafts
ii) Columns and walls
iii) Beams and slabs
(d) Arrangements for large pours (>100 M3 or 5 hours)

5) Consolidation and finish


(a) Use of vibrators
(b) Effects of over and under vibration
(c) Finishing of concrete

6) Concrete in Floor Finishes


(a) IPS Flooring
(b) VDF Flooring

7) Quality Assurance
(a) Cube Test for compressive strength
(b) Slump tests
(c) Other tests
i) Cores
ii) NDT
iii) Ultrasound
iv) Hammer rebound
8) Post Concrete
(a) Curing
i) vertical surfaces like columns, walls
ii) horizontal surfaces like slabs, footings
(b) Rectification
i) Minor honeycombing
ii) Major honeycombing
iii) Grouting
iv) Bulging
v) Leakage in water retaining structures/slabs

9) Productivity
(a) Productivity expected from batching plants
(b) Labour productivity – manual and pumped concrete
(c) Measures to increase productivity

10) Introduction to costing


(a) Elements in the cost – labour, materials, plant
i) The cost of batching plant / pump / crane
(b) How the tender direct cost is worked out
(c) Cost control
i) Reducing wastage
ii) Cost of rework / rectification

11) Safety
(a) Use of PPE
(b) Precaution when working at Heights

12) Housekeeping and maintenance


(a) Cleaning excess concrete
(b) Keeping floors clean
(c) Cleaning of mixer drums
(d) Cleaning of pump & pipeline

13) Case Studies


(a) One involving a large pour and high rate of pouring
(b) One involving innovative placing technique

Discussions & Lessons learnt


Project Operations- S Cadre

Duration: The training session is of one day duration.

Eligibility: The people who should be selected for this training


should be from all across S-Cadre inclusive of
Planning, Billing and core site execution.

Key Features:

1. Image Management – How to put up a site office

2. Site Execution from excavation to formwork, reinforcement, &


concrete and Finishes.

3. Quality Plan & Control over Quality.

4. Handling of Equipment.

5. Safety

6. Planning- for material, manpower & resources.

7. Function of Stores & how material are handled.

8. Cost Control & Wastage management.

9. Customer Relationship

The training is followed by an assessment test.


Curriculum:

(A) SITE EXECUTION:


1. Formwork
(a) Formwork systems for:
(i) Footings
(ii) Columns
(iii) Walls
(iv) Beams and slabs

(b) Quality Requirements


(i) Checking line, level, plumb and finish in footings,
columns, walls, beams and slabs
(ii) Special care for water light structures, pumping

(c) Deshuttering
Deshuttering period for various Elements

(d) Planning of formwork


(i) Understanding cycle time and repetitions
(ii) Understanding shuttering usage ratio, labour
productivity

(e) Care of formwork

(f) Safety in formwork

2. Reinforcement
(a) Detailing of reinforcement in:
(i) Footings
(ii) Columns
(iii) Walls
(iv) Beams
(v) Slabs
(b) Quality Requirements
(i) Checking dia size, spacing, cover and lap length
(c) Preparation of Bar bending schedules
(d) Reinforcement Planning
(i) Labour Productivity
(ii) Reconciliation of Steel
(iii) Reducing wastage
3. Concrete
(a) Properties and requirements
(b) Introduction to Mix Design
(c) Mixing of Concrete
(d) Placing of concrete
(e) Pouring of concrete in:
(f) Consolidation
(g) Quality Assurance
(h) Post Concrete
(I) Curing

4. Blockwork
(a) Testing of bricks and blocks
(b) Preparation of Mortar
(c) Execution
(d) Quality checks

5. Finishes
(a) Plastering
i) Difference bet internal and external plaster
ii) Preparation prior to plastering
iii) Execution
iv) Quality checks
(b) Floor Finishes
i) Cast in situ floor finishes – IPS & VDF
ii) Tiling with ceramic, terrazzo, granite etc.
(c) Wall Finishes
i) Wall tiling
ii) Painting

6. Waterproofing
a) Tanking – membrane
b) Basement waterproofing

c) Waterproofing in Toilets
d) Roof Waterproofing

7. External works
(a) Roads
(B) QUALITY ASSURANCE / CONTROL
1. Quality Plan
2. Checklists for key activities
3. ISO procedures

(C) SAFETY
1. Safety plan
2. Use of Protective Personal Equipment
3. Safety measures
a) Deep excavation
b) Working at heights
c) Edge and opening protection
d) Electrical
e) Operation of crane, builders hoist

(D) PLANT
1. Earth moving / compacting machinery – JCB, Excavator,
Vibro rollers, plate compactor
2. Concreting plant – Mixers, Batching Plant, Concrete Pumps,
Vibrators
3. Reinforcements plant – Bar bending and cutting machinery
4. Material handling plant – Mini dumpers, Tower Cranes,
Mobile Cares and Hydra, Builders Hoists
5. Pumps – Dewatering and curing
6. Generators
7. Welding transforming and rectifier
8. Others – Drilling machines, Compressors and Jack hammers

For all above i) Capacities and capability


ii) Guidelines for proper use
iii) Care and maintenance

(E) PLANNING
1. Understanding the MSP Programme
a) Weekly targets based on above

2. Preparation of Progress Reports


a) Weekly
b) Monthly (MIS Report)
c) Client Reports
3. Resource Planning
a) Lab our
i) Productivity of Carpenters, Fitters &
Masons
ii) Requirements based on MCP

b) Materials
i) Repetitions in Formwork, requirements as
per MCP
ii) Delivery lead times for various materials
c) Staff
i) Staff Productivity
ii) Typical Site Organization Structure
d) PMV
i) Plant requirement based on quantum of
work and MCP

4. Preparing Pre start Estimate


a) Principles behind PSE
b) Importance of PSE
c) What is C2C ?
d) C2C as a key control tool
(F) QUANTITY SURVEYING
1. Preparation of labour bills
2. Extra Items / variations

(G) STORES
1. Procedure for indenting materials
a) Local Purchases
b) Purchases through RO / HO
2. Procedure for receiving and issue of materials
a) DMR Register
b) MIV
c) MTV
3. Inspections carried out by stores
4. Debits to subcontractors
5. Demobilization
6. Housekeeping
Introduction to Contracts

Duration: The training session is for 2 days.

Eligibility: This training should be for people who are core civil
engineers (S Cadre & E Cadre) from sites and RO who
need to understand what Contracts is.

Key Features:

1. An Idea of different types of Contracts and their features, and its


making.

2. Awareness of the company’s Procedures (PSE, C2C, P&L).

3. Awareness of Preparation of Claims during the Contractual Period.

4. Maintenance of transparency with client & PMC.

5. Overcoming the Contractual difficulties w.r.t original contract.

6. Price Escalation during project duration and related claims.

The training is followed by an assessment test.

Curriculum:

1. Different types of Contracts

(a) Item Rate


(b) Lumpsum
(c) Cost plus

2. Contract Documents

(a) Invitation to Tender


(b) Form of tender
(c) Annexure to Form of Tender
(d) General Conditions
(e) Special Conditions
(f) BOQ
(g) Technical Specifications
(h) List of drawings
(i) Tender correspondence
(j) Letter of Intent
(k) Contract Agreement

3. Important features in the Contract

(a) Completion Period


(i) Mobilization Period
(ii) Intermediate milestones
(b) Payment Terms
(c) Mobilization Advance
(d) Bonds and Guarantees
(i) For Mobilization Advance
(ii) For Retention
(iii) Performance Bond
(e) Retention
(f) Liquidated Damages
(g) Secured Advance
(h) Insurance Requirements
(i) Contractors All Risk Policy
(ii) Workmen compensation
(i) Escalation
(j) Delay in completion
(k) Handing over
(l) Final Bill

4. Nominated Sub-Contracts

5. Preparation of RA Bills

(a) Read the Contract


(b) Measurements to be preferably approved before submission
(c) Recoveries
(d) Follow up for Payment Certificate
6. Final Bill and Closure of Contract

(a) Work to be re-measured. Use RA Bill measurements


(b) Claim maximum work done in pre-final bill
(c) Ensure all claims and extra items are included
(d) Comply with contract requirements respecialist guarantees
and As Built Drawings
(e) Follow up rigorously for payment

7. Preparation of Claims

All contractual correspondence – letters, MOM’s., Approvals,


transmittals to be meticulously filed. Also press clippings relating to
inclement, weather, strikes, increase in prices to be maintained.
Client’s letter should be replied immediately.

(a) Extension of Time


(b) Escalation
(c) Damages caused by other agencies
Forward claim immediately after the incident
(d) Idle labour due to holds / lack of fronts

8. Variations and Extra Items

(a) Inform Client in writing about variation / extra item

(b) Submit cost and time implications. Use dayworks rates for
labour and PMV. Note that small jobs done after completion
of main work require disproportionate supervision and
productivity will be low. BOQ rates are not applicable for
new work done after expiry of original completion date.

(c) Preferably execute variations / extra items only after rates


for same are approved.

(d) Include complete list of variations / extra items / claims in


each RA Bill.

(e) In Meetings, remind Client about approval and inform


them about the effect on our Cash flow.
9. Preparation of PSE, C2C and P & L Statements

(a) PSE Statement

To be prepared within 45 days of award of contract. Great


care to be taken as this is a very important document and is
reviewed by top management as it has an impact on the
Organizations profitability.

(b) C2C Statement

Prepared every quarter, this statement reflects the actual


financial health of the project. It compares actual
performance vis-à-vis PSE and also projects performance in
the future.

(c) P & L Statement:

Prepared in conjunction with the Accounts department, this


statement will report the current profitability of the project
based on actual expenditure (payments made to labour,
vendors, suppliers, staff salaries, etc. including provisions
made for future payments). The statement will split
expenditure on labour, plant, materials, sub contractors, etc.
and give the cost incurred for Major activities vis-à-vis.
PSE provision. This would enable the management to take
corrective action well in advance.

10. ERP

(a) Control Estimate module


(b) Client billing module
Introduction to Project Management

Duration: The training session is of one day.

Eligibility: The people who should be selected for this training


should be from S-Cadre & E Cadre essentially
Planning & Billing Engineers and Construction
Managers.

Key Features:

1. Basics of Project Management & Interlinking between Planning,


execution and billing in a project.

2. The essential features of the contract document and why it has to


be understood.

3. An in depth study of Master Construction Programme and how it


should be done.

4. Various other aspects like Resource Planning and Mobilization.

5. Billing, Cost & Progress Monitoring including preparation of


various reports.

6. Contractual Correspondence and Preparation of claims.

7. Contract Closure.

The training is followed by an assessment test.

Curriculum:

1. Study of Contract Documents

(a) Conditions of contract


i) Advances
ii) Performance Bond
iii) Payment Terms
iv) Retention
v) Insurance
vi) Liquidated Damages
vii) Variations
viii) Delays in execution
ix) Final Bill and Virtual Completion Certificate

(b) Technical Specifications


i) RCC
ii) Tolerances

(c) BOQ
i) Preamble

(d) Drawings
i) Register
ii) Drawing Control

e) RFI
i) Check drawings
ii) Bring discrepancies to Client’s notice
f) Salient features of specifications, programme,
methodlogy and resourcing to be discussed with
engineer/subcontractor before start of activity

2. Preparation of Master Construction Programme

Of immense importance, Contractor will be expected to comply


with the same. Delays will lead to blame game and needless
correspondence. It should be prepared with great thought.

3. Resources Planning

(a) Organization structure


Client may not accept any change from the chart submitted
during tender.
(b) PMV Requests
Client may again not accept any change from the
commitment submitted at Tender Stage.
(c) Labour:
Shortage of labour is one of the main reasons for delays in
progress.
Labour especially skilled may not be easy to mobilize and
undergo sharp dips during festive seasons like Holi, Puja
and harvest season. Arranging labour is primarily a site
responsible.

(d) Bought out Items


Specialist subcontractors – waterproofing, Aluminum Works,
Hand-railing, False Ceiling, Granite, Painting – have a major
role as their performance can affect both the progress and
quality of the job.

(e) Formwork Requirement


i) Formwork scheme will be finalized with the regional
coordinator on receipt of LOI and requirements worked
out. These quantities will be considered in the PSE.
ii) As formwork is an expensive component, high
shuttering usage ratio is required. Otherwise additional
material will be required to meet the programme
resulting in higher depreciation costs.
iii) It is essential to anticipate additional formwork atleast
a month in advance, as the system may not be
available ex-stock. Failure to arrange formwork in time
is another common reason for delays.
iv) Planning Manager should review with the Construction
Manager if the formwork being executed on site is as
per the Project Scheme.

(f) Reinforcement Requirement


A key material in RCC, shortage of reinforcement has, on
occasions, slowed down the work. Most often, the site had
given the requirement very late. Certain diameters – 25/32
especially – may be out of stock. There is heavy demand for
steel from the main producer and prices keep fluctuating.
This is a sellers market. This is the reason RO’s have a
system of asking monthly requirements from site at least 15
days in advance.
i) On receipt of LOI, steel requirements should be
worked out at least to Ground floor slab level.
Foundation steel will be required on the 7th day in
some cases.
ii) In absence of further GFC drawings, Client should be
asked to give the quantities dia wise for procurement
purposes.
iii) There should be at least two alternate suppliers.
iv) The minimum stock requirement is 15 days.
v) In emergencies, approach client for substitution of
dias.

4. Temporary Infrastructure Layout


This is a requirement in some tender submissions. But in any
case, finalization of the temporary Infrastructure Layout (in
Consultation with the Project Manager and Plant Manager) is to be
taken up immediately on award of the contract. A well-designed
layout will facilitate work resulting in higher productivities.

5. Quality and Safety Plans


These are to be submitted during the mobilization period. They
are usually prepared by the QA/QC and safety officers respectively
with their regional coordinators. The Planning Manager has to
essentially follow up and submit to client.

6. S Curve and Cash flow


When the cumulative billing month wise is plotted on a graph, it
has the shape of a S curve. The S curve is ideal as it indicates a
gradual start and closure with the peak at the midway point. The
S curve is part of the MIS Report.
The cash flow is to be prepared for our Accounts to enable them to
plan the financial requirements. Both the S curve and cash flow
would require to be revised accordingly to the progress.

7. Progress Monitoring
The progress of the project is to be monitored at every stage.
Corrective action is to be taken when delays occur.
8. Cost Monitoring
As important as progress monitoring is the Cost Monitoring. A
loss-making project is like a terminally ill patent. A good Project
Team should ensure that this situation does not arise.
(a) Pre Start Estimate (PSE).
(b) Labour bills
(c) Purchase of materials at site
(d) Cost to complete (C2C) statements
(e) P & L statements

9. Billing
Billing – Clients and labour – should be done immediately at the
start of the month for the work done in the previous month. Any
delays will affect the Project’s; Cash flow and cause discontent in
the labour force. (a) The RA bills.
(b) Labour bills
(c) “Unfavorable Items”.

10. Project Control


There are other parameters, which are deployed to check if the
project execution – especially with respect to time and cost – is
under control. (a) Material Reconciliation
(b) Labour Productivity
(c) PMV output.

11. Delay Analysis


(a) Most projects extend beyond completion date and if we are
to avoid Liquidated Damages or claim for associated costs,
correspondence reality to delay should be maintained from
DAY ONE.
(b) Common causes for delay on project not attributable to
contractor:
(c) Record the reasons in letters, MOM’s. Record dates of
receipts of drawings and Site Instructions (confirm if verbal).
(d) Submit letter for Extension of time with all backups, atleast
30 days ahead of Project Completion date.
(e) Claim for associated costs to include site overheads, labour
establishment (but not labour cost), PMV and formwork
depreciation, bank charges.

12. Closure of Contract


QA/QC on Site

Duration: The training session is of one day duration.

Eligibility: The participants chosen should be essentially QA/QC


engineers or those earmarked for QA/QC.

Key Features:

1. Quality awareness amongst engineers & supervisors

2. Project Quality Plan and its execution.

3. Setting up a lab & testing of materials.

4. Execution as per ISO procedures and documentation of it.

5. To understand the non-conformity in products.

6. To give a product according to customer satisfaction.

7. Conducting and preparing for external and internal audits.

The training is followed by an assessment test.

Curriculum:

1. Preparation of Project Quality Plan


- Features
- To be Site Specific

2. Testing of materials
(a) Cement
i) Initial and final setting times
ii) Compressive Strength
iii) Fineness
iv) External tests
(b) Sand
(i) Grading
(ii) Silt Content
(iii) Other visual checks
(c) Aggregates
i) Grading
ii) Fineness Modules
iii) Flakiness Index
iv) CBR Test
v) External tests
d) Mortar
i) Compressive strength
e) Blocks
i) Compressive strength
ii) Water absorption
f) Reinforcement Steel
i) In the lab – Unit weight for rolling margin
ii) External Mechanical
- Yield Stress
- Ultimate Tensile Strength
- Bend / Re bend
iii) External Chemical
- Carbon content
g) Soil
i) Atterberg’s limits
ii) Bearing capacity
iii) Optimal Moisture Content
iv) Proctor density
v) Understanding geotechecnical reports

3. Design of Concrete Mixes

(a) Various methods for designing mixes


(b) Testing of individual constituents
(c) Batching of ingredients and preparing trial cubes
(d) Corrections for moisture content, workability
(e) Using concrete from RMC with their design mix
4. Setting up of laboratory
(a) Basic layout of lab- Curing tank for concrete cubes
(b) Soil testing
i) Core cutters
ii) Oven
(c) Cement- i) Vicat’s Apparatus
(d) Aggregates- i) Sieves
(e) Concrete
i) Cube Moulds
iii) Slump test apparatus
iv) Comp. Strength testing machine
(f) Mortar- i) Moulds
(g) General
i) Weigh balances
ii) Calipers
(h) Calibration of testing apparatus

5. Compliance with ISO


(a) ISO 9001 as applicable to site
(b) Internal Audits
(c) External Audits

6. Documentation
(a) Registers- i) Cube testing
(b) RMC Delivery Challans
(c) Cement and steel Test Certificates
(d) Site checklists
(e) Method statements
(f) Calibration reports

7. Best practices in Construction


(a) Composition in fill / back fill
(b) Formwork finish
(c) Consolidation of concrete
(d) Laying of Blockwork
(e) Plastering
(f) Ceramic tiling
(g) Granite / Marble Works
(h) Painting
(i) Road works
(j) Waterproofing
8. Quality Inspection on Site
(a) Shuttering
(b) Concrete
- Before Pouring
- Port Concreting
(c) Blockwork
(d) Plastering
(e) Tiling Mockup
(f) IPS Flooring Mockup

9. Rectification of defects
(a) Concrete finishes
- Honeycombing
- Fins and bulging
(b) Variation in concrete dimensions beyond tolerance
(c) Cube strength below acceptable level
- Cores
- NDT Tests
(d) Rehabilitation of defective concrete
- Epoxy treatment
- Retrofitting
- Demolition
(e) Blockwork
- Additional thickness of plastering
(f) External Plastering
- Not in plumb
- Shade variation
(g) Tiling
- Lack of slope in wet areas
- Uneven joints
- Insufficient bedding
(h) Leakages
- Roof waterproofing
- Toilets
- Basement walls
- External Walls
(i) External Works
- Settlement

10. Case study and lessons learnt


Safety in Civil Construction

Duration: The training will be of one day duration.

Eligibility: It is meant for all Safety officers at sites.

Key Features:

1. Preparation of Safety plan for the site.

2. Various procedures of safety right from excavation stage.

3. Setting up of First Aid Rooms and First Aid Boxes at the sites.

4. Educating staff and workers on all safety procedures and


practices.

5. Ties up with hospital & health care centers in case of accidents &
other emergencies at sites.

6. Case Studies

The training is followed by an assessment test.

Curriculum:

1. Preparation of Safety Plan

2. Safety during Execution


(a) Earthworks
i) Barrication around excavations
ii) Stability of cut slopes
iii) Movement of vehicles
(b) Works at a height
i) Safe ladder access
ii) Barricading edges
iii) Use of safety belts, nets, fall arrestors
iv) Prevention of falling objects
(c) Material handling
i) Testing of crane slings, builders hoist
ii) Precautions during crane movements
iii) Safe storage of materials

(d) Scaffolding
i) Stability
ii) Access for people
iii) Working platforms

(e) Electrical and welding


i) Jointing of cables, Use of ELCB’s, plugs
ii) Check hand tools
iii) Earthing of equipment
iv) Gas cutting operations – Flash arrestor

(f) At the labour camp


i) Hygiene
ii) Toilets and garbage disposal
iii) Safe water

(g) House keeping

3. Inculcating Safety Culture


(a) Induction for new workers and staff
(b) Tool Box talks
(c) Safety campaigns
(d) Meetings of Site Safety Committees
(e) Conducting safety audits

4. First Aid and Stores


(a) Setting up First Aid Room
(b) Identifying and tie up with local doctor / hospital
(c) Stores

5. Safety Records
(a) At Site
(b) Reports to be submitted to RO / HO
6. Human Relations
(a) With workers and subcontractors
(b) With colleagues and staff
(c) With client

7. Emergency Response
(a) Major Incident
(b) Post incident measures

8. Case study and Lessons learnt (At least 2 Projects)


Introduction to PMV Works on Site

Duration: The training session is of one day duration.

Eligibility: This training is for all PMV staff including all the
Mechanical GET’s.

Key Features:

1. Creation of site PMV & Electrical infrastructure including of


positioning of PMV.

2. Determination of power requirements and lighting of the whole


site.

3. To install, commission & maintain various PMV systems.

4. Maximize the utilization by allotting proper trained manpower and


proper maintenance.

5. Adherence to ISO systems.

6. Costing of PMV inclusive of fuel, spare parts.

7. Preparation of various reports

The training is followed by an assessment test.

Curriculum:

1. Site Infrastructure

(a) Determining the normal and peak power requirements


(b) Selecting and locating Generators
(c) Electric Supply Layout
(d) Water supply layout
(e) Location of major plant – Batching Plant, Tower Crane,
Wood M/c.
(f) Bar bending and cutting machines
(g) Location and layout of PMV workshop
(h) Lighting Layout in site
(i) Labour camp

2. Installation and commissioning of following plants

(a) Batching Plant


(b) Tower Crane
(c) Generators
(d) Bar bending and cutting machines
(e) Builders Hoists

3. Operation and Maintenance of Key Construction Equipment

(a) Earthworks
(b) Concrete
(c) Reinforcement
(d) Pumps
(e) Material Handling
(f) Others

4. Maintenance of Records

(a) Registration, Fitness certificates, Insurance, Taxes


(b) History Sheets, Job Cards
(c) Utilization
(d) Vehicle Inspection certificates
(e) Safety Certificates for cranes, etc.

5. Other Procedures

(a) Demobilization
(b) Transfer to other sites / central yard
(c) Hiring of PMV
(d) Purchase of spares and repair of PMV outside site.
6. Introduction to costing

(a) Depreciation costs


(b) Hire costs

(c) Operation costs


i) Fuel / Power
ii) Lubricants
iii) Spares
(d) Operator costs
(e) Efficiency Ratios
(f) Productivity of major plant
i) Batching Plant
ii) Transit Mixers
iii) Concrete Pumps
(g) Cost of breakdowns / non-availability of plant

7. Troubleshooting common problems in PMV

8. Case Studies and Lessons learnt

(a) One major project with extensive PMV deployment


(b) Innovative repairs of PMV
Enterprise Resource Planning (ERP)

Duration: The training will be of three days duration.

Eligibility: The training will be essentially for


Planning/Billing/Contract Engineers who will be
actually working on ERP modules.

Key Features:

The system is an integrated information system that serves all


departments within an enterprise. The ERP system will give insight into

• Tendering
• Planning
• Execution
• Accounts
• Purchasing & Stores
• Plant & Machinery
• Human Resource
• Payroll
• Client Billing
• Control Estimate

The training will help the employee to minimize costs, maximize service,
performance and information quality. Produce immediate data flow
between modules and avoid duplication of data. It generates instant
company wise information across various modules. It helps in
streamlining systems and procedures within the organization.

The training is followed by an assessment test.


Quality Management System (QMS)

Duration: The training is for one day’s duration.

Eligibility: The training is for all employees for all cadres.

Key Features:

• Definition of Quality, Quality Assurance & Quality Control


• Definition of Process, Process Approach & PDCA Cycle
• Quality Management Principles
• Advantages of ISO
• Six Mandatory Procedures
• Current Master-list of General Procedures
• Details of ISO 9001: 2000 Certificate & scope
• Advantages of using Checklist
• System of Internal Quality Audits
• Customer Satisfaction
• Attending Customer Complaints, Defects on sites & Vacating
NCR’s
• Measures taken to ensure Quality during construction
• Format of reporting of Corrective / Preventive Action Reports

The training is followed by an assessment test.


Finishes

Duration: The training is of one day’s duration.

Eligibility: The training is for all site engineers in S cadre who are
in execution and in Finishes.

Key Features:

1. Emphasis the importance of quality in execution of all types of


Finishes.

2. Execution of blockwork according to Specs and drawings.

3. Various types of plastering and execution of the same with


emphasis on quality.

4. Various types of Floor Finishes with emphasis on material


selection and quality.

5. Different types of Paints & Preparation of various surfaces before


application of paint.

6. A visit to site to witness the actual execution of Finishes.

The training is followed by an assessment test.

Curriculum:

1. Introduction

(a) Importance of quality in Finishes


(b) Features of Finishes works
- Procurement planning to be done well in advance
- Co-ordination with services work
- Supervision of specialist vendors
- Sequencing
- Protection of Finished works
2. Blockwork

a) Selection of materials - blocks, sand


i) Testing of blocks
b) Preparation of mortar
c) Execution
i) Study of drawings for openings
ii) Laying first course
iii) Arrangement of materials
- Planning in multistoried buildings
- Scaffolding
iv) Quality checking
- Line, Plumb, Right angles, thickness of joints,
closing at top
- Size & Location of openings
d) Curing

3. Plastering

a) Types of plastering
b) Preparation of mortar for various types of plastering
c) Preparation prier to plastering
d) Execution
e) Curing
f) Preparation of Mockup

4. Floor Finishes

a) Introduction to various types of floor finishes


b) Granolithic Flooring
i) Preparatory work
ii) Execution
c) VDF Flooring
d) Tiling
i) Inspection of materials for size, squareness, colour
variations.
ii) Wall Tiling
iii) Floor Tiling
iv) Staircases
e) Rectification of defects in floor finishes
5. Painting

a) Introduction to different types of paints


b) Preparation prior to paint
- c) Application of finish coats
d) Quality checks
e) Preparation of Mockup

6. Introduction to other specialist finishes

a) ACP cladding and structural glazing


i) Civil requirements
b) False ceilings
i) Different types
ii) Sequence of erection
iii) Co-ordination with services

7. Lesson learnt

8. Case studies
a) Toilet finishes in a large project
b) External painting / VDF flooring

9. Discussions
Contract Management

Duration: The training is of one day duration.

Eligibility: The training is for E Cadre engineers who are in site


execution as well as in contracts.

Key Features:

1. Understanding the Contract Documents including Technical


Specifications & Drawings and implications of key contractual
condition.

2. Importance of maintaining of all contractual correspondence on


site during execution.

3. Preparation of Claims and responding to extra claims and other


correspondence from the employer’s side.

4. Master Construction Programme.

5. Closure of Project.

The training is followed by an assessment test.

Curriculum:
(A) Understanding Contract Documents

1) Tender Documents
2) Addendums
3) Submissions
4) Letter of Intent
5) Contract Agreement
B) Contractors Obligations

1) On award of contract during mobilization period


i) Submission of BG’s for Performance Bond, Advance
Payment and Retention Money
ii) Submission of Insurance – CAR Policy, Workmen’s
Compensation
iii) Submission of MCP, temporary infrastructure layout,
list of vendors, details of staff, safety plan, quality plan,
Progress Report Formats, Cash Flow
iv) Submission of mix design, method statements for initial
activities
v) Mobilization of equipment, supervisory staff and
construction of site facilities including labour camps.

2) Execution Phase
i) Execution of work as per GFC drawings, Tender specs
and in line with MCP
ii) Selection of materials and vendors as per approval
iii) Submission of monthly R.A.Bills
iv) Submission of progress reports, method statements,
RFI’s
v) Attend Meetings

3) On completion
i) Demobilize
ii) Attend to Snags
iii) Apply for virtual completion certificate
iv) Submit Final Bill

C) Employer’s Obligations

1) On Award of Contract
2) Execution Phase
3) On Completion

D) Handling Changes

1) Changes – Deviations in any form from The Original


Contract
2) How are changes handled in the Contract
E) Claims
1) Difference between claims and variations

2) Grounds for claims


3) Claims likely from Employer’s side.

F) How should the Contractor prepare for variations and


claims?

1) Proper Records
.
2) Correspondence
The most important record of the history of the project and
the key component of any dispute resolution. Letters should
be written without fail to record the following:

a) Drawing
b) Holds
c) Clearances / Approvals.
d) Payments
e) Execution
f) Other Contractual
i) Inclement weathers especially rains. This would
not only affect progress on site but supplies too.
Offsite production unity too could be affected.
ii) Transporters strikes. Both National and local.
Attach press clippings.
iii) Increase in rates of basic materials and changes
in taxes. Attach press clippings.

3) Minutes of Meetings:
This has equal importance as formal correspondence.
(a) In the meetings, insist that our concerns on
delays in drawing issue, approvals and payments
are recorded. Our views on delays in execution
should also be recorded.
(b) Put on record our disagreement with recorded
minutes and let this be connected in the next
MOM.
4) Master Construction Programme:
(a) If there is a major delay and the cause is not
attributable to us, we can revise the MCP. The
MCP should be submitted for approval of client.
Follow up for approval of revised MCP.
(b) Follow up for approval of revised MCP. Any
monitoring of progress should be with respect to
revised MCP.

G) Important Contractual Communication:


Listed below are the key contractual communications, which
should not be neglected.
1) Client complaints on Quality & Progress
(a) Quality (b) Progress

2) Escalation:
Non-private sector contracts will not award escalation
costs during the tenure of the contract period. But in the
extended phase, they can either revise the BOQ rates or
pay escalation costs on the work executed during the
extension phase. Anyway, there is no harm in presenting an
escalation claim.

3) Extension of time:
Almost all projects today extend beyond the original
completion date for a variety of reasons – due to both the
contractor and the client. In many cases, the client suffers
financial losses (or at least opportunity costs) if the facility
is not handed over in time. The client would try to recoup
some of the losses by levying Liquidated Damages (LD)
on the contractor. The contractor also is losing money on
additional overheads expenses and will try to recover these
costs from the client.
4) Request for Virtual Completion Certificate.
When the works are substantially complete viz. no new
works are balance, the contractor should apply for the Virtual
Completion Certificate. This certificate is vital since it marks
the commencement of the defect liability period and is proof
that the building has been handed over for the clients use.
5) Submission of Final Bill
The contract is usually very explicit in the procedures for
preparation, submission and processing of the Final Bill.
(i) Since balance payment in the Final Bill is a long time in
coming (60 to 120 days after issue of Virtual
Completion Certificate), please ensure that the pre-
final bill is as high as possible and no work is left
unbilled.
(ii) If variations and claims are settled during the contract
period, it will not delay the processing of the Final Bill.
(iii) As the final bill is a re-measurement of the entire
project, make proper measurements during the RA Bill
and use the same in the Final Bill. A good Qs will not
re-measure for the Final Bill. He / she will only
combine them from previous bills.
(iv) Before the payment certificate is issued, the Client
would – if specified in the contract – ask the following
requirements to be met.
iv) Submission of 10 year guarantees for items like anti
termite treatment and waterproofing
v) Submission of “As Built” drawings
vi) Evidence that payments have been made to sub
contractors
vii) Mutual argument on claims
(v) Unconditional acceptance by the Contractor of the
Final Payment Certificate would any scope for
discussion of claims / disputed items in the future.

6) Completion of Defect Liability Period:

On completion of the defect liability period, the contractor


should request release of balance retention money and
return of the Performance Bond.
Project Operations – E Cadre

Duration: The training is for one day’s duration.

Eligibility: The training is for all Senior E cadre Engineers who


are managing the site.

Key Features:

1. Raise the awareness of site managers in planning all resources –


Manpower, Material, Money & Machinery.

2. Prepare the Engineer to anticipate all difficulties which could arise


in execution.

3. Provide a complete insight into Costing and monitoring the cost.

4. Explain the importance of Productivity and how it can be


increased.

5. Importance of working with best vendors.

6. Throw light on Project Closure

7. Evaluate on Manpower Management – Motivation of Staff &


Labor.

The training is followed by an assessment test.

Curriculum:

1. Increasing Productivity

(a) Motivation
i) Motivation of Labour / Sub Contractor
ii) Motivation of Staff
(b) Mechanization
i) Earthworks
ii) Concrete
iii) Blockwork
iv) Finishes

(c) Erection
i) Earthworks
ii) Concrete
iii) Formwork and Reinforcement
iv) Blockwork & finishes
-
(d) Resource planning
i) Minimum stock of one week consumption for cement
ii) Reinforcement to be atleast 20% surplus. Extra care
for higher dia.
iii) Stock aggregates before monsoon & festival season
iv) Give 15 days lead for manpower mobilization. Keep
20% surplus
v) Aluminum works, finish doors, granite, etc. are long
lead items. Select vendor atleast 4 months in advance.

2. Cost Control

(a) Elements of activity cost


i) Materials
ii) Labour
iii) Plant and Machinery
iv) Indirect costs
v) Profit and overheads

(b) Materials
i) Wastage to be minimum
ii) Cost of poor quality of materials
iii) Order correct quantities
iv) Demobilize formwork material immediately to reduce
depreciation cost.
(c) Labour
i) Award work on piece-rate. Monitor productivity to avoid
claims
ii) Avoid excessive labor supply
iii) Use correct category of labor for type of job

(d) Plant & Machinery


i) Poor condition will result in high maintenance costs
ii) Idle time will result in high depreciation costs
iii) Higher utilization will result in higher productivity
iv) Productivity important especially in hired plant

(e) Indirect costs


i) Includes power, water, salaries, labour establishment,
Bank charges
ii) Delay will increase Indirect Costs
iii) Acceleration in work – if not accounted for - will
increase indent costs
iv) Poor infrastructure planning will increase – Indirect
costs
v) Demobilize staff in time

(f) Profit and Overheads


i) Overheads are RO & HO overheads. Compulsory
administration costs not in control of site.
ii) Profit (Margins) is essential for the company to grow
and value.

(g) Main causes for spiraling costs


i) Materials – High wastage. Depreciation of formwork
ii) Labour – Low Productivity, High Labour Supply
iii) Plant and Machinery – High Maintenance Costs
iv) Indirect costs – Project Delays
v) All of above will reduce margins

(h) Measures to control costs


1. Materials
2. Labor
3. Plant and Machinery
4. Indirect Costs
5. Select sub-contractors well in advance
3. Vendor Control

(a) Suppliers
(b) Sub contractors

4. Project Monitoring

(a) Construction Programmes


(b) Resource Planning
MCP and other programmes are the basis for resource
planning:
i) Materials
ii) Labour
iii) Plant and Machinery
iv) Staff

5. Getting the best out of PMV

(a) Choosing the right equipment


(b) Using the equipment

6. Introduction to Contracts

(a) Claims
(b) Extra works and variations
(c) Extension of Time
(d) Virtual completion certificate
Design and Build

Duration: The training is of one day duration.

Eligibility: All engineers in S, E And C Cadres who need to


understand the concept of Design & Build.

Key Features:

1. Design – Build Concepts

2. Design – Build Project flowchart – Pretender / Post tender

3. Costing process for DB Projects – Budgetary Offer / Detailed


Costing

4. Value Engineering Methodology

5. Design – Build Contracts – Terms & Conditions

6. Advantages of executing Design – Build Projects to RO’s

7. Integration of ‘Design & Build’ with ‘Site Operations’ based on


‘failures & lessons learnt’

8. Business Development for Design & Build.

9. Project Management as an instrument for Time Extension & Cost


Deviations.

You might also like