Schedule - Oke
Schedule - Oke
DI M
I Tahap Persiapan
1 Koordinasi dengan Pemberi Tugas 16.75% 1.29% 1.29%
II Pengumpulan Data
1 Data Sistem Drainase Eksisting 2.55%
2 Data Kondisi Umum Wilayah 3.45% 1.72% 1.72%
TOTAL 100.00%
RENCANA PROGRES TIAP MINGGU 1.29% 1.81% 2.25% 2.64%
KOMULATIF RENCANA TIAP MINGGU - 1.29% 3.10% 5.34% 7.98%
Keterangan :
= Rencana Progres
= Progres Aktual
SCHEDULE DED DRAINASE PERMUKIMAN PAGARSIH PASTEUR
DI METROPOLITAN BANDUNG RAYA
TAHUN 2017
P E R I O D E
BULAN KE - II BULAN KE - III BULAN KE - IV BULAN KE - V
5 6 7 8 9 10 11 12 13 14 15 16 17 18
0.59%
0.88%
2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37%
0.57%
2.72% 2.99% 6.53% 5.24% 7.38% 6.09% 7.38% 6.09% 7.38% 6.09% 4.23% 2.37% 3.66% 2.37%
10.71% 13.70% 20.22% 25.47% 32.85% 38.94% 46.32% 52.41% 59.79% 65.88% 70.11% 72.48% 76.14% 78.51%
BULAN KE - V BULAN KE - VI BULAN KE - VII
19 20 21 22 23 24 25 26
0.27%
1.14%
0.29%
0.39%
0.02%
Bogor, 2017
PT. 4 Cipta Konsultan
R. Yudi Machyudi
Team leader
SCHEDULE DED DR
DI ME
I Tahap Persiapan
1 Koordinasi dengan Pemberi Tugas 16.75% 1.29% 1.29%
II Pengumpulan Data
1 Data Sistem Drainase Eksisting 2.55%
2 Data Kondisi Umum Wilayah 3.45% 1.72% 1.72%
TOTAL 100.00%
RENCANA PROGRES TIAP MINGGU 1.29% 1.81% 2.25% 2.64%
KOMULATIF RENCANA TIAP MINGGU - 1.29% 3.10% 5.34% 7.98%
REALISASI PROGRES TIAP MINGGU 1.29% 1.81% 2.25% 2.64%
KOMULATIF REALISASI TIAP MINGGU - 1.29% 3.10% 5.34% 7.98%
DEVIASI 0.00% 0.00% 0.00% 0.00%
Keterangan :
Rencana Progres
Progres Aktual
SCHEDULE DED DRAINASE PERMUKIMAN PAGARSIH PASTEUR
DI METROPOLITAN BANDUNG RAYA
TAHUN 2017
P E R I O D E
BULAN KE - II BULAN KE - III BULAN KE - IV BULAN KE - V
5 6 7 8 9 10 11 12 13 14 15 16 17 18
0.59%
0.88%
2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37% 2.37%
0.57%
2.72% 2.99% 6.53% 5.24% 7.38% 6.09% 7.38% 6.09% 7.38% 6.09% 4.23% 2.37% 3.66% 2.37%
10.71% 13.70% 20.22% 25.47% 32.85% 38.94% 46.32% 52.41% 59.79% 65.88% 70.11% 72.48% 76.14% 78.51%
2.72% 2.99% 6.53% 5.24% 7.38% 6.09% 7.38% 6.09% 3.66% 2.37% 3.66% 2.37% 2.37% 2.37%
10.71% 13.70% 20.22% 25.47% 32.85% 38.94% 46.32% 52.41% 56.07% 58.44% 62.10% 64.47% 66.84% 69.21%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% -3.72% -7.44% -8.02% -8.02% -9.30% -9.30%
BULAN KE - V BULAN KE - VI BULAN KE - VII
19 20 21 22 23 24 25 26
0.27%
1.14%
0.29%
0.39%
0.02%
R. Yudi Machyudi
Team leader