Professional Documents
Culture Documents
CE 72152
CONTRACTS & LEGAL ISSUES
ASSIGNMENT
– -I
Presented by
CHAPTER TITLE
1. Introduction
2. Objective
3. Literature Review
4. Conclusion and Recommendation
CHAPTER – 1
INTRODUCTION
CHAPTER – 2
OBJECTIVES
The main aim of this research is to study the impact of the FIDIC selected clauses
on the construction project performance.
These objectives may be summarized as follows:
1. To identify contractual clauses which mostly affect the project performance, according
to FIDIC general conditions clauses (fourth edition 1987, reprinted 1992 with further
amendments);
2. To elicit views from contractors, owners and consultants on the identified FIDIC contract
articles concerning its impact on project performance;
3. To test if there is a significant difference in points of view of contract parties regarding
FIDIC groups' clause
CHAPTER – 3
LITERATURE REVIEW
B. Claim definition
A claim can be defined as a right given to the party who deserves a request for
compensation for damages incurred by the other party. A construction claim can also be
defined as ‘‘a request by a construction contractor for compensation over and above the
agreed-upon contract amount for additional work or damages supposedly resulting from
events that were not included in the initial contract.
However, the existence of a right is very subjective because of the complexity of
the construction contract and process. Furthermore, the amount of money involved in a
construction project is usually so large that a small discrepancy in the contract
interpretation will cause significant impact on the project profit. The increased complexity
and scale of the building process is one of the major reasons for increasing the number of
claims.
F. Delay claims
Finishing a project on schedule is a difficult task to accomplish in the uncertain,
complex, multiparty, and dynamic environment of construction. Thus, it has been common
for a construction project to encounter delays that on a construction site are normally
inevitable and, as a result, many claims arise with few of them ending up in litigation.
There are several reasons that can contribute to delaying a project. Analyzing the various
causes that contribute to the delay encountered in a construction project is an important
task to resolving this delay problem. Determining, in a scientific manner, the impact,
timing, and contributing effect of each cause to the overall delay should assist the parties
to clearly identify the responsibility of each. This scientific identification of each party’s
responsibility to the delay should be a good foundation to a successful negotiation effort.
It should result in the parties being able to settle this delay. If the parties were not able to
settle through negotiations, then the claim case will go to court, where the delay claim will
be analyzed, and that analysis will be crucial for either party to provide it case.
1. Period of suspension
Owners must ensure that the contractor's suspension rights are consistent with their
rights under the off take/ supply arrangements, in particular to ensure that they are not
obligated to continue supply after the contractor's obligations have ceased (in addition to
this owners are best advised to endeavor to keep production ahead of their supply
obligations so that stockpiles may be utilized to meet any gap in this respect). It is important
to ensure that both the right to suspend and the obligations cast on the party suspending to
work to overcome the force majeure event are (at least) consistent and it is preferable that
the contractor's obligations to restore supply are broader than the owner's under the off
take/sales agreements .
2. Termination rights
A second key issue here is the period of time for which the force majeure event can
continue before the right of termination crystallizes. An owner does not want to be in a
position where its contractor terminates but it is obligated to keep its off take/sales
obligations on foot {admittedly suspended but with the possibility that the force majeure
event may abate without the owner being in a position to perform). Ideally, the agreements
will be consistent in this respect, with the termination rights arising under all key
agreements at the same time. In the event that the owner cannot persuade the off taker or
contract miner to accept the same time periods, another option is to agree to separate time
periods but, in addition to those time periods, provide that a termination for force majeure
by the counterparty to a nominated co- dependent agreement entitles either party to
terminate for force majeure.
3. Payment rights
Finally, owners should consider payment rights under the project documents for
force majeure events and ensure that any payments due to the owner are paid to it prior to
it being obliged to make payments to the demobilizing.
3.4.9 Settlement of disputes
1. Engineer's decision
If a dispute of any kind whatsoever arises between the employer and the contractor
in connection with, or arising out of, the contract or the execution of the works, whether
during the execution of the works or after their completion and whether before or after
repudiation or other termination of the contract, including any dispute as to any opinion,
instruction, determination, certificate or valuation of the engineer, the matter in dispute
shall, in the first place, be referred in writing to the engineer, with a copy to the other party.
Such reference shall state that it is made pursuant to this clause. No later than the eighty-
fourth day after the day on which he received such reference the engineer shall give notice
of his decision to the employer and the contractor. Such decision shall state that it is made
pursuant to this clause.
If the engineer has given notice of his decision as to a matter in dispute to the
employer and the contractor and no notice of intention to commence arbitration as to such
dispute has been given by either the employer or the contractor on or before the seventieth
day after the day on which the parties received notice as to such decision from the engineer,
the said decision shall become final and binding upon the employer and the contractor (sub-
clause 67.1 of FIDIC 1987).
2. Amicable settlement
Where notice of intention to commence arbitration as to a dispute has been given
in accordance with the engineer's decision sub-clause 67.1 (the previous section), the
parties shall attempt to settle such dispute amicably before the commencement of
arbitration. Provided that, unless the parties otherwise agree, arbitration may be
recommended on or after the fifty-sixth day after the day on which notice of intention to
commence arbitration of such dispute was given, even if no attempt at amicable settlement
thereof has been made (sub- clause 67.2 of FIDIC 1987).
3. Arbitration
Any dispute in respect of which:
(a) The decision of the engineer has not become final and binding pursuant to sub-clause
67.1, and
(b) Amicable settlement has not been reached within the period stated in sub-clause 67.2,
shall be finally settled, unless otherwise specified in the contract, under the rules of
conciliation and arbitration of the international chamber of commerce by one or more
arbitrators appointed under such rules. The said arbitrator/s shall have full power to
open up, review and revise any decision, opinion, instruction, certificate or valuation
of the engineer related to the dispute. Arbitration may be commenced prior to or after
completion of the works, provided that the obligations of the employer, the engineer,
and the contractor shall not be altered by reason of the arbitration being conducted
during the progress of the works (sub- clause 67.3 of FIDIC 1987).
CHAPTER 4
CONCLUSION AND RECOMMENDATIONS
The main aim of this study is to investigate the impact of selected FIDIC clauses
on the construction project performance. The study results prove that FIDIC clauses have
significant impact on construction project performance, and are satisfactory to the contract
parties. This is because the surveyed contractors, owners and consultants consider the text
of FIDIC groups' clauses clear and treats the subjects of contract's clauses properly. The
researcher offers practical recommendations to support and develop a successful
contracting strategy with proposed additional studies in this subject.
As a result, practical recommendations pertaining to contract parties in respect to
the most important and troublesome FIDIC groups clauses, were generated as follows:
3.4.1: Contract documents clauses
To achieve clear contract documents, there must be common understanding only
realized with open and honest communications between the contracting parties prior to
contract execution.
Contract Document
Employer → U Moe Myint
Contractor → Trust & Gain Co., Ltd
Architect → Trust & Gain Co., Ltd
Structural Engineer → U Thein Soe
Project Manger → Daw Eigyin
Quantity Surveyor → Daw San Yi Oo
Contract Type → Lump Sum
REFRENCES
[1] FIDIC general conditions clauses (fourth edition 1987, reprinted 1992 with further
amendments);