Professional Documents
Culture Documents
4. Date of Dispatch -
Page 1
LIST OF CONTENT
1 Introduction………………………………………………………. 03
2 Public Private Partnership…..……………………………………. 04
3 Option of PPP……...…………………………………………….. 05
4 What is BOT………….………………………………………….. 08
4.1 Advantages & Challenges of BOT Project……………………… 10
5 Case study: Mumbai Metro….…………………………………... 12
5.1 Project Description………………………………………………. 12
5.2 PPP Structure of the project……………………………………… 13
5.3 Key Lessons……………………………………………………… 15
Page 2
1. INTRODUCTION
long term, between the public and private sectors whereby some of the
services that fall under the responsibilities of the public sector are
of each Party and clearly allocate risk. In a BOT arrangement, the private
sector designs and builds the infrastructure, finances its construction and
There are a number of major parties to any BOT project, all of whom
Page 3
2. PUBLIC PRIVATE PARTNERSHIP
government agency for the purpose of completing a project that will serve
and provision of services that were traditionally the domain of the public
sector. One of the key reasons is that governments are unable to cope
Page 4
greater incentives for the control of construction, operating and
The diagram below illustrates the continuum of options for involving the
At the left are supply and service contracts, which tend to be of short
duration and require less private commitment than the options higher in
providing the service, but instead for performing specified tasks, such as
customers. At the left are the longer term arrangements which require
Page 5
3. OPTION OF PPP
in Table 1.
participation options
Page 6
Service Contract:
service for a fee, for example meter reading, billing and collection.
Management Contract:
In this option, the private sector is paid a fee for operating and
decisions.
Lease:
Under the lease option, the private sector leases facilities and is
Concession:
Under concessions, the private sector finances the project and also has
the asset and all full use rights must revert to the government after the
Page 7
4. WHAT IS BOT?
ownership of the project to the government (although this need not be the
case).
needed for the facility’s revenue stream to pay off the company’s debt
and provide a reasonable rate of return for its effort and risk.
The table provided below reviews the BOT option and its variants,
Page 8
BOT PROJECT PROCUREMENT STRUCTURES
Build Own Operate Transfer (BOOT) • The service provider is responsible for design and
concession period
Build Own Operate (BOO) • Similar to BOOT projects, but the service provider
Lease Own Operate (LOO) • Similar to a BOO project but an existing asset is
Page 9
BOT projects, when properly designed, offer significant potential for
The BOT approach has many potential advantages, some of which have
length of time required to develop and negotiate BOT schemes, the need
following:
Page 10
User costs imposed for the first time or increased to match market rates.
competitive basis.
High financing costs. Financing costs for BOT projects tend to be high, as
the legal fees associated with their contractual arrangements are much
the credit means that lenders need more time than usual to assess a
benefits associated with a BOT scheme are taken into account when
such projects.
Page 11
5. CASE STUDY: MUMBAI METRO
Mumbai. The system is designed to address both present and future needs
Operate and Transfer (BOOT) method and has been India’s first PPP
responded to the EoI and a pre-bid meeting was held in November 2004
and final tender was given to Reliance Energy and Connex France. Veolia
Transport and Hong Kong MRT were the other members of the
Page 12
5.2 PPP Structure of the project
(MMRDA) holding 69 per cent, 5 per cent and 26 per cent of equity share
capital respectively.
The cost of the project was estimated at Rs. 2,356 crores, but due to
delays in completion of project the cost has swelled by Rs. 1,935 crores.
The total cost was financed on the basis of viability grant amounting to
Maharashtra.
The remainder being financed by 70 per cent debt and 30 per cent equity.
The project's master plan execution has been planned in three phases.
Page 13
Phase I covers a total length of 62.68 KM including 11.07 KM Versova -
Phase II has been planned to cover the 7.5 KM Charkop - Dahisar route,
For this, Siemens will supply the signalling systems required for the
Page 14
5.3 Key Lessons
well.
The process of bid for choosing the successful bidder took more than 2
years. This led to a lesser number of bidders to bid for the project. Similar
hurdles were experienced in the bid process for the Metro Line 2 as the
These delays resulted in only one bidder finally submitting a bid for the
project.
There was a delay in obtaining approvals for the over bridge that passed
over the railway line from the railway authorities. Project gets delayed
planned project while bidding out such projects and resolve the same
Page 15
Specification on Assets transfer:
before the expiry of the concession period (i.e. 35 years) a survey of the
schedule in the concession agreement does not have clear and robust
dispute.
individuals.
Page 16