Professional Documents
Culture Documents
PSCAD Relay Manual V3 2 PDF
PSCAD Relay Manual V3 2 PDF
Version 3.2
Table of Conte
Chapter 1
Overview of PSCAD/Relay......................................1
PSCAD/Relay Introduction..................................................1
Why Use a Power System Simulator .................................2
What Type of Testing.........................................................3
Parameters That Can be Modified......................................3
Chapter 2
Installation...........................................................4
Hardware and Software Requirements .............................4
Fortran Compilers..............................................................5
TCP/IP Network Protocol....................................................6
Licensing...........................................................................6
PSCAD Installation.............................................................9
License Manager Install...................................................13
Manually Configuring the License Manager.....................18
Manually Stopping the License Manager.........................20
Manually Starting the License Manager...........................20
Adding a License.............................................................21
Avoiding the Most Common Mistakes..............................21
GNU/EGCS Fortran Install.................................................22
Running PSCAD...............................................................23
Problems That Can Occur................................................24
PSCAD Compile Generates “make –f” Error..................24
Unable to Connect to License Manager Server.............24
Unable to Acquire License from ‘localhost’...................26
Getting Help During Installation......................................26
Uninstalling......................................................................26
Chapter 3
Case Descriptions...............................................27
Cases Included................................................................27
Case 1: Single Line..........................................................28
Substation Control Panel..............................................33
Playback Recorders......................................................34
Breaker Controls...........................................................35
Steps to Perform a PSCAD Simulation ........................35
Modification of Parameters..............................................38
Three Phase Voltage Source ........................................38
iv PSCAD/Relay Manual
PSCAD/Relay
PSCAD/Relay Manual v
Table of Contents
Appendix B
Using PSCAD/Relay...........................................112
Starting PSCAD..............................................................112
Title Bar and Menu Bar..................................................112
Title Bar and Active Project........................................113
Menu Bar and Menu Items..........................................113
Menu Buttons.............................................................113
Project Tree and Message Tree......................................114
Loading a Case Project..................................................114
Running a Simulation.....................................................116
Printing..........................................................................117
PSCAD/Relay Graphical Interface Features....................119
Scrolling.....................................................................120
Keyboard Shortcuts....................................................120
Printing Circuits and Plots...........................................120
Printing Component Parameters.................................120
Creating Plots and Graphs..........................................120
Connecting Wires.......................................................121
Creating Slider, Switch, Button, and Dial Interfaces. . .121
Changing Simulation Time Step and Run Duration.....121
Using Arrays...............................................................121
MultiPlot Features: FFT, THD and Curve Calculation...122
Tlines and Cables.......................................................122
Grouping Components................................................122
Editing Component Parameters..................................122
Undo...........................................................................122
Windows Meta File Export..........................................123
Finding Components...................................................123
Viewing Error and Warning Messages.........................123
Changing Page Size and Layout.................................123
Appendix C
Technical Support.............................................124
How to Contact Us.........................................................124
Maintenance Contract...................................................124
EMTDC Users’ Group......................................................125
Index..................................................................126
vi PSCAD/Relay Manual
Chapter 1
Overview of PSCAD/Relay
PSCAD/RELAY INTRODUCTION
PSCAD/Relay is a power system simulator designed
especially for AC protection relay test and analysis
personnel. PSCAD/Relay is designed with a number of
predefined transmission system configurations or cases.
The idea is to allow the user to load the case of interest,
enter the appropriate system parameters and solve the
simulation with very little effort.
• Fault Locations
• Fault Type: Single and 3-phase, phase-to-phase, and
phase-to-ground
• Fault Impedance
• Fault Duration
• Pre-fault Voltage, Power Flow and MVAR Conditions
• Point on Wave Timing for Fault Application
• Reclosing of Breakers after Fault Clearing
• Breaker Operating Time
• Single Phase Breaker operation
• Equivalent System Impedance
• Sequence of Breaker Opening and Closing
• Recorded Waveforms for Real Time Playback Testing
• Multiple Run or Batch Solutions
Cha
Installa
The PSCAD/EMTDC family of products uses the EMDTC
solution engine to solve simulations. Similar licensing,
installation and compiler requirements are necessary for all
versions of PSCAD/RELAY. Visit the web site www.hvdc.ca
for more information on other PSCAD products.
Category Requirement
use PSCAD.
FORTRAN COMPILERS
PSCAD requires a Fortran compiler to run. The following
commercially available compilers are presently supported:
If you are using a standalone PC, you can also install TCP/IP
using the Windows dial up network setup. Go to START |
Settings | Control Panel | Network… and add an adapter.
Remove the client for Netware (if you use Novell networking,
this is not required) and add the Protocol for Microsoft
TCP/IP.
http://www.microsoft.com/windows95/downloads/def
ault.asp, or: www.tucows.com in the Windows
95/Networking area.
25-Pin Serial Port Dongle
NOTE: These updates are important if you want to run the
PSCAD Educational, Commercial, or Relay Editions (which
require the License Manager) on a standalone Windows 95
machine that does not have a network card.
LICENSING
Licensing is required for the PSCAD/Relay program.
The License Manager software is used in conjunction with a
hardware lock, known as a dongle (shown in the side
column). The dongle contains pre-programmed information
regarding the type and amount of licenses, as well as other
user information. When PSCAD is started, it will request a
license from the License Manager. The License Manager, in
turn, checks the information on the dongle in order to verify
the request.
Not all computers come with USB ports. If you are not sure
if you have one, contact your System administrator for help.
EXAMPLE: A PSCAD/Relay
user wants 5 licenses on 1
dongle. This diagram
illustrates how this user
could install the License
Manager on their LAN
(Local Area Network).
PSCAD INSTALLATION
PSCAD comes with an easy to use installation program. The
only difficulty is typically found installing the License
Manager program
location.
When you have finished selecting a destination for
PSCAD, click "Next."
The installation program included with PSCAD will now
branch off into additional installers. These programs will
install other programs that you have indicated you
require, such as the License Manager or GNU/EGCS
Fortran.
LICENSE MANAGER INSTALL
The License Manager Install program will only run if you
selected it in the PSCAD install, step 4 above, or if it is
required by the version of PSCAD that you are installing. If
you did not select the License Manager, skip this section and
Neverproceed to 2.12
modify or delete the GNU/EGCS FORTRAN INSTALL.
“lmgr-hvdc” file on your
computer.
If you have the License Manager installed on your machine,
you do not need to run the License Manager Install again.
Please see “2.9 Adding a License” for further instructions.
Chapter 2: Installation
The installer will ask “Would you like to start the License
Manager during machine boot?” If the dongle is the only
device on the serial port, it is safe to select “Yes,” which
means the License Manager will start automatically when
the system is re-booted.
Select Yes:
Select No:
If you select Yes, it will ask you for your new license.
This is usually located on the floppy disk that came with
PSCAD, entitled “License Manager: License.txt.” Be sure
to have this disk ready for step five (5).
Chapter 2: Installation
‘lmgrd.ini’ File
‘lmgrd-log.txt’ File
• Windows 95/98/ME:
Go to START | Programs | HVDC Lmgr. Select ‘Start
License Manager.’
• Windows NT:
Go to START | Settings | Control Panel | Services.
Select the HVDC License Manager and select ‘Start’.
If HVDC License Manager does not exist in the list of
services, you must install it as a service. See
“Problems that can occur” for more information.
• Windows 2000:
Go to START | Settings | Control Panel |
Administrative Tools | Services. Highlight ‘HVDC
License Manager,’ right-click and select ‘Start,’ If the
HVDC License Manager does not exist in the list of
services, you must install it as a service. See
Chapter 2 “Problems that can occur” for more
information.
ADDING A LICENSE
If you have previously installed the License Manager, you do
not need to reinstall it. All you will need to do is add a new
license into the license database that resides on your
computer’s hard drive.
RUNNING PSCAD
To run PSCAD, simply click on Start | Programs | PSCAD |
PSCAD Relay. It should load and work without any
problems. You are ready to simulate cases!
Followed by either:
or
Case Descriptions
CASES INCLUDED
There are nine (9) distinct cases included with PSCAD/Relay.
They are located in the PSCAD/examples/Relay cases. The
following sections describe each case in detail. For
component description and how to run a case, see Case 1:
Single Transmission Line.
3 Phase 3 Phase
RMS RMS
B1 B2
Subpages are yellow in The 100 km transmission line is designated as Line 1. This
colour. Double click them frequency dependent transmission line is accurate for all
to see more!
frequencies, including mutual coupling between phases and
zero sequence components. The line model is developed
from dimensional data for the physical construction or
geometry of the transmission line. The line data includes
the type and impedance of the conductor and any ground
conductors that may exist. The frequency dependent
transmission line is accurate, not only at 60 Hz, but also at
all frequencies between DC and several hundred kHz. If line
geometrical data is not available, then phasor based (60Hz)
line R, X and B data can be utilized. See Chapter 4 for more
details on transmission line modeling. At the other end of
the transmission line is breaker B2 and Substation 2, with
similar settings to breaker B1 and substation 1.
SUBSTATION 1
V Ph
-110.1 [MW]
24.44 [MVAR]
B1
There are two Breakers in Case 1, one at either end of the
transmission line. Breaker B2 connects the transmission
line to the Bus of Substation 2 and displays the MW and
MVAR flowing through the breaker. The breaker component
will change colour according to the current state of the
breaker. Red signifies the breaker is closed and green
signifies the breaker is open.
On the main page of the case, there are also two plot
subpages, coloured yellow. These pages contain the analog
waveforms as recorded at Breaker B1 and Breaker B2.
Moving the mouse on top of the icon and double clicking the
left mouse button will open the subpage and display the
graphs. Placing the mouse over the graph and clicking the
right mouse button can access graph controls.
100.0 km
LINE1
The transmission line is shown between both breakers.
Double clicking on it will allow you to change any
parameters necessary.
SOURCE 1 B1 Timing
Ph Angle S1W S1Q Voltage V1rms P1 Q1 0 0 42-B1 B1 T1 B1 T2
180 500 C O 2 2
0.15 0.5
MW MVAR kV MW MVAR
-300 300 -100 100 220 250 -150 150 -30 30 Recorder Control
0 0 en Record1 en Record2 0 0
0 -300 -100 230 220 -150 -30 OFF ON OFF ON 0 0.31 0.36
SOURCE 2 B2 Timing
Ph Angle S2W S2Q Voltage V2rms P2 Q2 42-B1 B2 T1 B2 T2
180 500 1 1 C O 2 2
To turn the Recorders on,
MW MVAR kV MW MVar click on the switch.
-300 300 -100 100 220 250 -150 150 -30 30
On = Recorder will record data.
-180 0 0 0
20 -300 -100 230 220 -150 -30 Off = Recorder will NOT 0 0.31 0.36
record data.
Timed
FAULT C ONTROLS
B1T1
Breaker
Logic
Closed@t0 B1
B1T2
Fault location Fault Type Fault Start Duration Rf
5 6 7 1 1 50
2 3 Tfs
4 8 Timed
B2T1
FType
3 9 Fault
2 10 Logic Fault
1 4 1 11 0 0 0.001 B2
3 4 0.2 0.12 0.001
B2T2
Tfd Timed
Breaker
Dial Position: Dial Position: Logic
Closed@t0
1=>FT1: 1=> A-g
Between Source 2=> B-g
and B1 3=> C-g
2=>FT2: 4=> AB-g
Between Line 5=> AC-g Exports to Main Page
and B1 6=> BC-g
3=>FT3: 7=> ABC-g
Between Line 8=> AB
and B2 9=> AC
4=>FT4: 10=> BC
Between Source 11=> No fault (0)
and B2
Playback Recorders
Hint: The sliders can be
adjusted up and down with Recorders
the arrows keys or a value Start Stop
can be entered from the 1 1
keyboard by clicking on the
digital value. Enter the
desired value and press
“Enter.” 0 0
0.15 0.5
Recorder Control
en Record1 en Record2
O FF ON OFF ON
1 1
Fault Controls
MODIFICATION OF PARAMETERS
Three Phase Voltage Source
Z1 = 52.9 [ohm] /_ 80.0 [°]
100.0 [MVA]
230.0 [kV], 60.0 [Hz] The equivalent system impedance is defined in the voltage
source. Place the mouse on top of the drawing of the
voltage source and double click the left button. The
following properties, menu will be displayed.
V Ph
Hint: The value of the fault Fault resistances can be defined as a variable, or a real
resistance is determined by
the slider reading at the constant. In Case 1, the fault ON resistance is set as
instant the “fault” is variable “Ron,” and fault OFF resistance is the real variable
applied. Adjusting the
slider after the Fault time
1.0E6 [ohm] (1 Mega ohm). The value of Ron is controlled
will have no effect. by Slider Rf on the Controls’ page.
Fault Control
Recorder Parameters
• Stn1.cfg
• Stn1.hdr
• Stn1.dat (from RECORDER 1)
• Stn2.cfg
• Stn2.hdr
• Stn2.dat (from RECORDER 2)
3 Phase 3 Phase
RMS RMS
B1 B2
To change line length, right click with the mouse over top of
the transmission line and edit the line Properties. Change
the line length to the desired value, remembering to ensure
line section T1 added to line section T2 equals the total
length of the line you wish to simulate. For example, if the
total length of the line is 200 km, and the fault location is at
Chapter 3: Case Descriptions
V Ph Ph V
3 Phase 3 Phase
-0.03452 [MW] RMS RMS 0.04279 [MW]
0.285 [MVAR ] -0.04818 [MVAR]
100.0 km
FT1 LINE2 FT4
B3 B4
F1 V3 V4 F4
FT5 FT6
F5 F6
1 A phase to ground
2 B phase to ground
3 C phase to ground
4 AB phase to ground
5 AC phase to ground
6 BC phase to ground
8 AB phase to phase
9 AC phase to phase
10 BC phase to phase
11 No fault
For example:
• Assume 3-phase to ground Fault is on Transmission
Line 2 in front of Breaker B3. The following settings
would have to be made.
Fault Location = 5 and Fault Type = 7
Playback Recorders
Recorders
Start Stop
1 1
0 0
0.15 0.55
Chapter 3: Case Descriptions
Select the Start and Stop times for the playback recorders.
A1 A2 A3 A4 A5 A6
Analog Inputs
v2.0 RTP Recorder No. 1
Start File: stn1
Format: RTP
Comtrade 91
End Comtrade 99
Digital Inputs
D1
Plots Plots
B1 B3 B2 B4
3 Phase 3 Phase
52.54 [MW] RMS RMS -51.28 [MW]
-10.57 [MVAR] 8.376 [MVAR ]
SUBSTATION 1 50 km 50 km SUBSTATION 2
T1 T2
B1 B2
V1 FT2 FT4 V2
Fault FT3 Fault
Z1 =52.9 [ohm] /_ 80.0 [°] Z1 =52.9 [ohm] /_ 80.0 [°]
100.0 [MVA] Fault 100.0 [MVA]
230.0 [kV], 60.0 [Hz] 230.0 [kV], 60.0 [Hz]
V Ph Ph V
3 Phase 3 Phase
52.54 [MW] RMS RMS -51.28 [MW]
-10.57 [MVAR] 8.376 [MVAR ]
50 km 50 km
FT1 T3 T4 FT5
B3 B4
Fault V3 V4 Fault
FT6 FT7 FT8
Fault Fault Fault
3 P hase
0.2286 [MW] RMS
0.04266 [MVAR]
50 km
LINE4 #1 #2
B5
V Ph Ph V
FT1
F1 3 Phase 3 Phase FT4
-0.2557 [MW] RMS RMS 0.3089 [MW]
F4
0.2106 [MVAR] -0.2844 [MVAR]
100.0 km
LINE3
B3 B4
V3 V4
FT5 FT6
F5 F6
50 km
T5
50 km
T6 #1 #2 FT9
B5
FT9
F9
F9 40.0 [MW] 10.0 [MVAR]
V5 FT8
F8
-16.22 [MW]
3 Phase
RMS
3 Phase
RMS 50.88 [MW]
Fault and signal labels.
85.16 [MVAR ] -89.68 [MVAR]
SUBSTATION 1 50 km 50 km
LINE1 LINE2 SUBSTATION 2
B1 B2
V1 FT2 FT3 V2
F2 F3
Z1 = 52.9 [ohm] /_ 80.0 [°] Z1 =52.9 [ohm] /_ 80.0 [°]
100.0 [MVA] 100.0 [MVA]
230.0 [kV], 60.0 [Hz] 230.0 [kV], 60.0 [Hz]
V Ph Ph V
FT1
F1 3 Phase 3 Phase FT4
-33.17 [MW] RMS RMS 35.56 [MW]
F4
86.75 [MVAR ] -89.07 [MVAR]
50.0 km 50.0 km
T3 T4
B3 B4
V3 V4
FT5 FT7
F5 FT6 F7
Plots Plots
F6
B1 B3 B2 B4
The controls for Case 7 have the same general look and feel
as for the previous cases. Power and VAR flows are adjusted
Plots Plots Plots
SUBSTATION 1
3 Phase 3 Phase
B1 RMS RMS B2 B3 B4
#1 #2
B1 B2 B3
V Ph V2 Ph V
V1 FT1 FT2
F1 F2
Display
Tap Position FT3
-0.2166 [MW]
F3
-0.1577 [MVAR]
0.9 1.1
B4
0.9 FT4
V3
F4 20.0 [MW] 5.0 [MVAR]
Tap Changer setting
refers to final Turns ratio
in Per Unit
B5
FT5
Plots Plots Plots
F5
SUBSTATION 1
B1 B2 B3 / 4
3 Phase 3 Phase
RMS RMS
#1 #3
B1 B2 B3
V Ph V2 Ph V
V1 FT1 FT2
F1 25 [MVA] F2
230.0 [kV]/10 [kV]/25 [kV]
1.0
FT3
-6.447 [MW]
F3
-1.574 [MVAR]
B4
Display V3 FT4
off line tap F4
20.0 [MW] 5.0 [MVAR]
0.9 1.35
1.05
SUBSTATION 1 B1 B3 B2 B4
Line 3 Line 1
3 Phase 3 Phase
Z1 = 17.95 [ohm] /_ 87.63 [°]
24.08 [MW] 36.05 [MW] RMS RMS -25.51 [MW]
100.0 [MVA] 82.54 [MVAR] 117.4 [MVAR] -65.69 [MVAR]
230.0 [kV], 60.0 [Hz] SUBSTATION 2
Line 5
B5 B1 50 [%] 50 [%] B2
Ph V1 FT2 FT4 V2
V Z1 = 3.8 [ohm] /_ 87.69 [°]
Fault Fault 100.0 [MVA]
230.0 [kV], 60.0 [Hz]
FT3
Fault
Ph V
B3 50 [%] 50 [%] B4
V3 V4
FT6 FT8
Fault Fault
FT7 Line 2
Fault
PSCAD/Relay Components
TRANSMISSION LINE MODELING
The modeling of transmission lines for transient simulation is
an important and complex topic. Transmission lines and
cables in electric power systems are non-linear in nature
due to frequency dependency in conductors (skin effect)
and the ground or earth return path. PSCAD/Relay offers
the most accurate time domain transmission line models
offered today, but can also accommodate limited models
based on the available system data.
1. Bergeron model
2. Frequency Dependent (Mode) model
3. Frequency Dependent (Phase) model
1
This is a valid web site as of August 23, 2001.
Frequency Dependent (Mode) Model Options
Travel Time Interpolation: On
Curve Fitting Starting Frequency: 0.5 [Hz]
Curve Fitting End Frequency: 1.0E6 [Hz]
Maximum Order of Fitting for ZSurge: 20
Maximum Order of Fitting for Prop. Func.: 20
Maximum Fitting Error for ZSurge: 2 [%]
Maximum Fitting Error for Prop. Func.: 2 [%]
Tlines
G1 G2
10 [m] C2
10 [m]
C1 5 [m] C3
10 [m]
Tower: 3H5
30 [m]
Conductors: chukar
Ground_Wires: 1/ 2"HighStrengthSteel
0 [m]
Sequence Impedance(ohms)
R X
POS 3.62518 50.8645
NEG 3.62518 50.8645
ZERO 36.3595 132.732
Sequence Admittance (mhos)
G B
POS 1e-005 0.000327118
NE G 1e-005 0.000327118
ZER O 1e-005 0.000232266
The load flow line model data can be transferred into the
coupled pi section component. The steps to do this are as
follows:
50 [%] 50 [%]
Tower Component:
G1 G2
10 [m] C2
10 [m]
C1 5 [m] C3
10 [m]
Tower: 3H5
30 [m]
Conductors: chukar
Ground_Wires: 1/2"HighStrengthSteel
0 [m]
Ground Component:
Ground Resistivity: 100.0 [ohm*m]
Relative Ground Permeability: 1.0
Earth Return Formula: Deri-Semlyen
Chapter 4: PSCAD/Relay Components
If the line length is known, and it exceeds 100 km, the long
line correction factor should be applied in converting the per
unit line data for manual entry into a Bergeron line model.
The line data with the long line correction removed enables
parameters to be determined in terms of 1-metre sections
for the Bergeron line model. The correction factors for long
line effects can be enabled in the Bergeron line model or
can be applied to the data conversion. In this example, the
factors included are to compensate for effects of long,
greater than 100 km lines.
3. Save conductor.clb.
C1 5 [m] C3
10 [m]
Tower: 3H5
30 [m]
Conductors: chukar
Ground_Wires: 1/2"HighStrengthSteel
0 [m]
9. Click OK.
C1 5 [m] C3
10 [m]
Tower: 3H5
30 [m]
Conductors: polly
Ground_Wires: 1/2"HighStrengthSteel
0 [m]
This web site requires a user name and password, which are
free to users of PSCAD.
1. Log on to
http://www.hvdc.ca/main/downloads/pscad_v3/i
ndex.html
3. Fill out the form. The Name you enter will be your
user name.
Chapter 4: PSCAD/Relay Components
http://www.hvdc.ca/main/downloads/pscad_v3/pe_reg/pe/ind
ex.html
TRANSFORMERS
Simulation of transformers requires an understanding of
#2 some of their basic properties involving both core and
winding configuration. This is complicated by the fact that
#1 #3 the core of the transformer is prone to saturation leading to
the phenomena of inrush current, remanence, geomagnetic
current effects and ferroresonance.
Three phase component of
a transformer model.
In this section, the main emphasis is on the magnetic
properties of transformers. The effects of winding
capacitance are generally minimal and need not be modeled
providing the frequencies of interest are less than about
2000 Hz and switching transients are of interest. Winding
capacitance is important when fast front studies are to be
performed and magnetic effects can usually be neglected.
Core Configuration
XO = XH-L + 3*XN
From which;
XN = [ XO – XH-L ]/3
LN = XN * MVA / (w * VH2)
Where:
Ungrounded Windings
Autotransformers
Saturation
BREAKER COMPONENT
PSCAD/Relay breaker component models the switching
behaviour of an AC system breaker. This breaker can be B1
displayed graphically in several formats, and display
calculated MW and MVAR at the location of the breaker.
Both the open and closed resistances can be specified. The
breaker can be specified to open only at current zero, allow
for single phase control, and can be programmed to include
pre-insertion resistors.
and are centered on the Fault Start time, which is set within
the Controls’ page.
FStart
FDur
doble
V
ProTesT
I
I1A
I1B
I1C
I1
Once the case is run, the .ss1 files will be located in the
.emt directory created. These files are ready for import into
Doble’s ProTesT software with no changes required.
Chapter 5
Advanced Topics
SEQUENCER
These components can be used to set up complex
sequences to control the application of faults,
opening/closing of breakers, or waiting for events (such as a
zero crossing...), for example. A sequence can be merged
with other sequences, or a single sequence can branch off
into many sequences. Some examples are shown in the
PSCAD/Relay Master Relay Library in the Sequencer
subpage.
Sequence Control
StartTime Seq. E nable FaultAngle Prot Time Prot Delay
1 Off Enab 360 0.1 0.1
0 0 0 0
0.2 1 22.8 0.032 0.014
B3seq
A
Ctrl = 1
Timed
Breaker B
Logic
Closed@t0 Ctrl B3
Seq_enable
Seq_enable
Ctrl B4
B
Timed
Breaker
Logic Ctrl = 1
A
Closed@t0
B4seq
1 Meas-Enab
.
Ch. 1 . V1
V1a FAngle1
.
Ch. 2 V2
V1B FaultType
Ch. 3 Multiple
Run
V1c
Ch. 4
I3a
Ch. 5
I3B
Ch. 6
I3c
In the Controls' subpage of the Case 3 multiple run
example, the Multiple Run component is found.
S
Wait For
FDelay (Sec)
N N
N/D N/D
FAngle1 FDelay
360.0 D 60.0 D
FREQ
The second output control variable is FaultType. FaultType
is defined inside the component as an integer list
containing a set of three integer values, 1, 4 and 7. One (1)
represents an A phase to ground fault, 4 is an AB to ground
fault and 7 is an ABC to ground fault. FaultType replaces
the need to set the fault using the Fault Type dial.
PSCAD/Relay will set the fault type automatically with the
FaultType variable.
On the left hand side of the Multiple Run icon, six inputs are
analyzed during the multiple PSCAD/Relay runs. The fault
location for the example is chosen as location FT5, between
Breaker B3 and Line 2. This is set the same way as previous
cases were, using the Fault Location Dial. Both the 3-
phase Voltage and Breaker B3 currents are recorded for
analysis.
Multiple Run will collect and store its output data into a file.
The file name is also defined as a parameter within the
component itself, as shown on the next page.
The optimum occurred for run # 5 and has been repeated for the last run below:
Run # Fault Angle Fault type V1A V1B…
16 360.0000000 1 186.8472801 188.6665013…
MR Enable
MREnable
OFF ON
A Ctrl = 1
FaultType
B
FaultType1 Ctrl FType
1
6 = dial
5 Off Off On 6 (correct,
dial is off)
1=
multiple run
6 On On On 5
control
(correct)
STARTING FROM A SNAPSHOT
PSCAD/Relay starts all simulations by ramping the voltage
sources over a time constant. This is done is order to
prevent oscillations and numerical instability of the
solutions. One of the options of PSCAD/Relay is to begin the
solutions from a known operating point, instead of all the
internal variables set to zero. A snapshot data file can be
taken at anytime during the simulation. The simulation then
can be started, not from time zero, but from the snapshot
time. Where is this feature useful? Inside PSCAD/Relay, the
systems being modeled are relatively small and the cases
arrive at steady state operation by 0.2 seconds of
simulation. However, if a multiple run case was solving 100
cases, there may be advantage to starting from a snapshot
and reduce the overall simulation time required.
TIME
A
Compar-
Controls
ator B1opT
0.1
B
0.1
B1opT
0
0.05
V
1 V TRIP
I
1 I OP
B1testa
Control
3 1
B
Delay
2 V TRIP
2 I OP
B1testb
3 V TRIP
3 I OP
B1testc
Controls
B1opT
0.1
0
0.05
Timed
Breaker
Logic
Closed@t0 B3A
Flt_en2
Timed
Breaker B3B
Logic
Closed@t0
Timed
Breaker
Logic
Closed@t0
B3C
B3 Timing
42-B3 B3AT1 B3AT2 B3BT1 B3BT2 B3CT1 B3CT2
C O 2 2 2 2 2 2
0 0 0 0 0 0
0 0.35 0.42 2 2 2 2
SUBSTATION 1 SUBSTATION 2
B1 B2
V1 FT2 FT3 V2
F2 F3
Z1 = 52.9 [ohm] /_ 80.0 [°] Z1 = 52.9 [ohm] /_ 80.0 [°]
100.0 [MVA] 100.0 [MVA]
230.0 [kV], 60.0 [Hz] 230.0 [kV], 60.0 [Hz]
100.0 km
3 Phase
3 Phase
L1_2
RMS
RMS
V Ph Ph V
-0.04062 [MW] 0.0474 [MW]
0.2957 [MVAR ] -0.05028 [MVAR]
FT1 FT4
B3 B4
F1 V3 V4 F4
FT5 FT6
F5 F6
3 Phase 3 Phase
290.3 [MW] RMS RMS -276.2 [MW]
14.05 [MVAR] 86 [MVAR]
V Ph Ph V
3 Phase 3 Phase
0.005515 [MW] RMS RMS -0.02128 [MW]
0.1912 [MVAR] -0.02051 [MVAR]
80.456 km 80.456 km
T3 T4
FT1 FT5
B3 B4
Fault V3 V4 Fault
FT6 FT8
Fault FT7 Fault
Fault
Appe
Troubleshooting Ins
STARTING THE LICENSE MANAGER SERVICE
WINDOWS NT:
This will solve the problem, and you will be able to open the
help files.
Appe
Using PSCAD/Re
This appendix is a quick guide to useful features in
PSCAD/Relay, as well as a general how to.
The area under the title bar consisting of menu items and
menu buttons is called the main menu bar. All main
menu items are drop down menus, which means that when
you point the cursor to one of these menu items and click
the left mouse button, you will see a list appearing below it.
To select an item from this list, first move the cursor onto
that item (the item is highlighted) and then click the left
mouse button. The following menu shows how to load a
project using the File menu from the main menu bar.
Menu Buttons
The plot and graphs will contain the values of the voltage at
the mid-point of the circuit; the current flowing through the
circuit.
RUNNING A SIMULATION
Before we run the simulation, we will do a simple calculation
to find out what load current and mid-point voltage we
should be expecting. Double-click on the source component
You must have a Fortran
Compiler installed before
to view its data. Note that the source voltage magnitude is
you can run a case.
70.71 kV rms or 100 kV peak. Close this dialog by clicking
on the Cancel button at the bottom of the dialog. Click
anywhere in the empty space to de-select the selected
component. This will stop the blinking of the selected
component. For a 100 kV source voltage, we know that the
mid-point voltage should be 50 kV peak and the load current
should be 50 kA peak. Now let us run the simulation and
actually verify the current and voltage waveforms.
Click on the RUN button to see the run once again. It will
go through all three stages, however, you will not be able to
notice the first two stages, as they pass by very quickly.
This is because PSCAD optimizes on these stages and
performs them only if required.
PRINTING
To print the circuit along with the graph you just simulated,
click the right mouse button on the background of the circuit
page and select the Print item.
Appendix B: Using PSCAD/Relay
The best way to learn more about what these options can do
for you is to try them out. Before printing, PSCAD provides
you a preview of what you are about to print in relation to Print
the selected paper size and orientation.
Scrolling
Use the scroll bars on the right and bottom side of the
window to scroll through the page instead. A page-style
scrolling can be achieved by holding the Ctrl key down,
pressing the left mouse button on the page and then
dragging the mouse. You can also use the centre wheel
feature on your mouse, if the mouse has one, or the arrow
keys in the extended keyboard.
Keyboard Shortcuts
Connecting Wires
Run time interfaces for slider, push button, switch, and dial
are always located inside a special component called
Control Panel. Right click on the background of the page
where you want to place the interfaces and select Add ⇒
Control Panel from the pop up menu. Then, right click on
the title bar of the panel, currently called ”CPanel“ and
select Help from the pop up menu for further details.
Right click on the case name in the project tree and select
Properties… from the pop up menu. Click on the Help
button on the Case Properties dialog for further details.
Using Arrays
Plots are very versatile. Use one of the pages in your case
to lay the plots out the way you like. Currently, PSCAD
supports only time plots, i.e., the horizontal axis is always
TIME.
Grouping Components
Undo
Finding Components
Appe
Technical Supp
HOW TO CONTACT US
The Manitoba HVDC Research Centre and its representatives
are committed to providing you with the best technical
support. We can be reached at:
• Phone: +1-204-989-1240
• Fax: +1-204-453-5074
• Email: pscad@hvdc.ca
MAINTENANCE CONTRACT
A maintenance contract provides the following support and
upgrades. Please contact us for details.
In
A FFT...................................122
Active project...................113 Finding components.........123
B Fortran...........................5, 24
Bergeron model.................62 G
Breaker controls.................35 Geomagnetic current effects
Breakers.......................30, 84 .......................................78
C Get license info..................21
Cases included...................27 Graph.................................31
Changing simulation time Ground component............69
step and run duration...121 Grouping components......122
Conductor database...........71 H
Conductor.clb.....................71 Hardware lock......................7
Connecting wires.............121 Hardware requirement.........4
Contact us........................124 HTML viewer....................110
Continuous system model I
function (CSMF)..............90 Inrush current....................78
Control module..................33 Installation...........................9
Core configuration.............79 Internet explorer................12
Coupled Pi Model Component K
.....................47, 54, 59, 66 Keyboard shortcuts..........120
Creating a snapshot.........101 L
Creating plots and graphs 120 Leakage reactance.............79
Creating slider, switch, License manager install.....13
button and dial interfaces Licensing..............................6
.....................................121 Line constants....................62
Curve calculation.............122 Lmgr-hvdc database file.....14
D Load a case......................114
Data.out.............................97 Localhost......................11, 26
Doble.................................85 M
Dongle.................................7 Magnetizing current...........79
E Make-f error.......................24
Editing component Menu bar..........................113
parameters...................122 Menu buttons...................113
Enter license key................21 Mid-line fault......................47
Error and warning messages Multiple run........................91
.....................................123 MultiPlot features.............122
F N
Fault controls.....................35 Netscape............................12
Fault description................49 Number of runs..................93
Fault impedance................43 O
Fault type...........................49 Output file..........................84
Fault type dial....................92 P
Faults.................................30 Page size and layout........123
Ferroresonance..................78
Parallel transmission line. . .48 Serial port............................7
Parameters........................38 Single phase breaker
Multiple run....................91 operation......................105
Recorder...................44, 82 Snapshot..........................101
Three phase voltage Solve constants..................64
source.........................38 Starting PSCAD................112
Transformer....................55 State Component...............85
Transmission line......41, 70 Steps required to perform
Phase angle.......................89 simulation.......................50
Phase comparator block...104 Steps to perform PSCAD
Pi line sections.............61, 64 simulation.......................35
Ping....................................14 Subpages...........................30
Playback recorders.............34 Substation control panel....33
Plot....................................31 T
Print.................................117 T-Tap.................................55
Printing circuits and plots.120 TCP/IP..................................6
Printing component Tertiary winding fault.........58
parameters...................120 Testing transformer
Project manager...............114 protection.......................57
Project tree......................114 THD..................................122
Protection relays..............103 Three phase voltage source
R .......................................29
Reboot...............................23 Title bar...........................112
Register online...................77 Tower component..............69
Remanence........................78 Transmission line...............32
Run button.......................116 Transmission line modeling61
Running a case..................23 U
Runtime settings................37 Undo................................122
S Uninstall.............................26
Saturation....................78, 81 USB......................................7
Scrolling...........................120 Using arrays.....................121
Sequence information........63 W
Sequencer..........................89 Winding capacitance..........78
Sequencer control logic......91 Windows meta file export.123