10_KGLT_PROJECT
NO. DETAILS ACTION ON BY STATUS AS ON 25.08.10
ITC/FABS expressed deep concern on the huge delay in mobilisation
of men and material for the project as a result of which there has
been slow progress at site from the date of issue of LOI (LOI to M/s
L&T was issued on 22nd June 2010).
M/s FABS/ITC informed M/s L&T that any delays in the milestones
agreed in the tender/contract would not be entertained and M/s L&T
to look at ways and means to make up the time lost and submit a
catch up schedule for the whole project
L&T informed that the Plant building RC concrete will be commenced 8/10/10 Commenced on 20/08/2010
on 10th August 10
L&T informed that the finalization of Brought out earth for filling
works schedule would be submitted shortly
L&T informed that the checklist & work method statement new
activity would be submitted one week prior to commencement of Record
new activity.
Safety:
JSA
M/s L&T informed that JSA would be submitted 1 week or 10
days prior to commencement of any activity. Note
Safety steward
M/s L&T informed that the required safety stewards (1:50)
will be deployed by 10th August 2010 for the current 8/10/10 Available nos 4 out of 8nos
manpower strength. Further the 1:50 ratio will be maintained
up to project end.
6 Access Ladder
M/s L&T informed that additional 8 Nos of ladder would be 8/11/10 Mobilized on 18/08/10
mobilised by 11th August 2010 for excavation pit works.
Display board
M/s FABS/ITC informed that a safety display board to be Immediately Completed
displayed for each building with the details of building,
building plan, contact person and emergency contact person.
Hard barricading
L&T agreed to have hard barricading with Pipe & clamps for Note All backlog completed. New one in progress
excavation work
M/s ITC/FABS advised M/s L&T that the third party approval is
required for Design Mix & L&T agreed for the same & same will be 8/25/10 L&T Submitted on 23/08/10
10 submitted along with 7days trial mix test results by 25th August 2010.
M/s L&T informed the team that the quality in-charge would report
12 at site by 16th August 2010 against commitment of 19th July 2010 8/16/10 L&T Reportedon 25/08/10
L&T informed that Anti-termite agency has been awarded and the
13 Technical specification, data sheet and work method statement will Note L&T Submitted
be submitted shortly.
Catch Up schedule:
14 M/s L&T committed to the team that the catch up schedule would be 8/10/10 L&T Submitted on 11/08/10. comments to be incorporated.
submitted by 10th August 2010 against commitment of 24th July 2010