You are on page 1of 207

Emirates Computers

Professional Services

BPCS – Contractors and


Owners Guide
Dubai Municipality
Contractors & Owners User Guide BPCS

Table of Contents

1 Introduction............................................................................................................... 4
1.1 Document Structure ....................................................................................................... 4
2 Overview .................................................................................................................... 5
2.1 BPCS Features ............................................................................................................... 5
2.2 BPCS Architecture......................................................................................................... 6
3 System Requirements ............................................................................................... 8
3.1 Software Requirements .................................................................................................. 8
4 Getting Started .......................................................................................................... 9
4.1 Contractor Prerequisites................................................................................................. 9
4.2 Logging in to BPCS ..................................................................................................... 10
5 Projects..................................................................................................................... 13
5.1 Creating a new project ................................................................................................. 13
5.2 Viewing Project Details ............................................................................................... 17
5.3 Deleting a Project......................................................................................................... 23
6 Applications ............................................................................................................. 24
6.1 Creating a New Application (Generic) ........................................................................ 26
7 Application for Building Demolition..................................................................... 28
7.1 Building Demolition Permit – Manual......................................................................... 29
7.2 Building Demolition Permit – Mechanical .................................................................. 34
8 Miscellaneous Service Request .............................................................................. 39
8.1 Requesting an Increase in Electric Power.................................................................... 40
8.2 Requesting Additional Meters ..................................................................................... 46
8.3 Requesting a Building Number.................................................................................... 51
8.4 Requesting a To Whom It May Concern Letter........................................................... 57
8.5 Photocopying and Stamping Blueprints....................................................................... 61
8.6 Renewing Permit for 6 Months .................................................................................... 65
8.7 Extending Approval Validity ....................................................................................... 69
8.8 Requesting Permit Cancellation before Start of Work................................................. 73
8.9 Applying for Building Permit Application Cancellation ............................................. 77
9 Permit Application for Owners & Decor Companies.......................................... 81
9.1 Requesting an Adjustment Addition Permit (Simple – Owner)................................... 82
9.2 Requesting a Maintenance Permit................................................................................ 87
9.3 Requesting a Painting Permit ....................................................................................... 96
9.4 Requesting a Normal Decor Permit ........................................................................... 101
9.5 Requesting a Simple Decor Permit ............................................................................ 112
9.6 Requesting a Decor Permit before Issue of Completion Certificate .......................... 118

Dubai Municipality 2
Contractors & Owners User Guide BPCS

10 Acquiring Permission for Road Service and Temporary Works ................. 123
10.1 Walk Side Booking Permit ........................................................................................ 124
10.2 Temporary Tents Permit ............................................................................................ 128
10.3 Electricity Cable Permit ............................................................................................. 132
10.4 Road Signboard Permit .............................................................................................. 135
10.5 Roof Signboard Permit............................................................................................... 140
10.6 Occupy Parcel ............................................................................................................ 146
10.7 Pavement Permit ........................................................................................................ 150
10.8 Outside Planting Permission ...................................................................................... 154
10.8.1 Permission for Full Planting .......................................................................................... 154
10.8.2 Permission for Partial Planting ...................................................................................... 159
11 Availing Special Services & Exceptions.......................................................... 164
11.1 Requesting New Building Style Verification Permit ................................................. 164
11.2 Requesting Exceptions............................................................................................... 168
12 Other Applications............................................................................................ 176
12.1 Viewing Other Applications ...................................................................................... 176
12.2 Request Statistical Info .............................................................................................. 177
12.3 To Whom It May Concern letter................................................................................ 180
12.4 Unblocking Services .................................................................................................. 183
13 Appendix............................................................................................................ 186
13.1 Creating Charges........................................................................................................ 187
13.2 Viewing Modification Options .................................................................................. 190
13.3 Creating Versions of a Returned Application ............................................................ 196
13.4 Re submitting a CFR Application .............................................................................. 200
13.5 Responding to Engineer Notes................................................................................... 204
13.6 Printing Screens from BPCS...................................................................................... 206

Dubai Municipality 3
Contractors & Owners User Guide BPCS

1 Introduction
This document is the user guide for the contractors and owners of Building Permit &
Control System (BPCS). An owner here refers to the land/building owners.

1.1 Document Structure


This guide has10 chapters and the outline of each chapter is given below:

Chapter Name Description


Introduction Introduces the structure of the guide, and the audience of
the guide.
System Requirements Describes the minimum hardware and software
requirements to be able to access BPCS.
Getting Started Describes the business user prerequisites, and the steps
involved to register and log on to BPCS.
Projects Describes projects and the steps involved to create, view
and delete projects.
Applications Describes applications, application types and the steps
involved in creating permit application
Adjustment, Addition & Demolition Describes the steps involved to submitting a permit
Permits application for demolition
Miscellaneous Service Requests Describes the steps involved in submitting permit
application requests for increasing power, additional
meters, building number requests, to whom it may concern
letters, renewing permit, extending approval validity,
unblocking a parcel and other miscellaneous services
Permit Application for Owners & Describes the steps involved in submitting permit
Décor Companies application for painting, simple and normal décor works,
décor permit before issue of completion certificate,
adjustment addition permit and maintenance permits
Acquiring permission for road Describes the steps involved in submitting permit
services and temporary works application for walk side booking, temporary tents,
electricity cable, road and roof sign boards and outside
planting
Availing special services & Exceptions Describes the steps involved in submitting permit
application for requesting exceptions and new building
style verification
Other Applications Describes the steps involved in creating applications
requesting statistical info, to whom it may concern letters
and unblocking services
Appendix Describes the steps involved in creating applications for
creating charges, steps to view modifications for all the
décor applications, creating versions of a returned
application, responding to engineer notes, resubmitting a
CFR application, and printing screens. These processes are
common to all application types and hence are included in
this section.

Dubai Municipality 4
Contractors & Owners User Guide BPCS

2 Overview
Building Permit & Control Systems (BPCS) is a system that has revolutionized and
automated the building departments permit issue and control section application process
in Dubai Municipality.

BPCS allows business users which are consultants, contractors, and owners, to apply for,
and follow up on the application for permits through an e- service. This ensures the
minimal manual transactions in Dubai Municipality for buildings permit related work.

BPCS includes all the processes that covers the building permits needs of consultant
/contractors and owners and provides them with options to track the processing and
checking results. Also, the system is integrated with DM systems such as e-payment
system, Geographical Information System (GIS), financial systems, pre qualification
procedures and more to provide a convenient and enterprise environment for BPCS users.

2.1 BPCS Features


BPCS allows the business users to perform the following functions online:

• Create new building permit applications, view application information, building


data, pay the charges and more

• Create new building permit and control applications for the required mandatory
processes

• Upload/attach documents against the applications

• Make payments

• Submit the applications to Dubai Municipality

• Review the status of the submitted application

• Review the charges

• Review Control section inspection requests and violations/fines

• Receive notifications/messages from DM employees

Dubai Municipality 5
Contractors & Owners User Guide BPCS

2.2 BPCS Architecture


This section gives a brief overview of BPCS architecture and the flow of the application.
The pictorial representation of the BPCS architecture is given below

Figure 2-1: BPCS Overview

Dubai Municipality 6
Contractors & Owners User Guide BPCS

A general description of the BPCS architecture and the process is described below.
Each user logs into the DM portal and creates an application which belongs to a specific
project. Once the application is complete and submitted to DM, it goes through an
approval process based on the type of permit and the type of building.
The counter clerk is the first interface between the user and engineers in DM. The counter
clerk reviews the application and either approves or rejects the same. If the application is
rejected, it’s returned to the user. If the application is accepted, it’s forwarded to the
relevant building engineer committee for approval.
Each of engineers reviews the application and the attachment and if approved, forward it
to the senior architect or engineer for final approval. If the engineers don’t approve the
application, it’s returned to the user with comments. The user creates a new version of the
application and resubmits the same for acceptance and approval.
The senior architects or engineers review the application and approve the same. The
approved application is returned to the user with further instructions. If the senior
engineers or architects reject the application, the application is still returned to the user
with comments, who resubmits the same for acceptance and approval.
The instructions to create the different applications, based on the application types are
discussed in detail in the manual.

Dubai Municipality 7
Contractors & Owners User Guide BPCS

3 System Requirements
This section lists the minimum hardware and software requirements by the contractors
and owners to access and use BPCS.

3.1 Software Requirements

The minimum software required to access BPCS are:

Description Version
Operating System Windows 2000 and above

Internet Explorer 5.0 and above

Internet Speed 512 Kbps and above

RAM 256 MB and above

Dubai Municipality 8
Contractors & Owners User Guide BPCS

4 Getting Started
This section describes the prerequisites to be a Contractor. It also describes the
Registration process for the Dubai municipality portal and the log in process for BPCS.

4.1 Contractor Prerequisites


Dubai Municipality has a qualification or a grading process that categorizes e-service
users into Consultant, Contractor, and public users. It is mandatory for every consultant
and contractor to have a trade license and the same should be registered with Dubai
Municipality’s pre-qualification department.

Dubai Municipality grades consultants and contractors based on certain requirements.

The requirements for a contractor to access BPCS are:

• Apply for a trade license form the Department of Economic Development (DED)

• Register the license with the e-government department of Dubai Municipality to


be able to access the Dubai Municipality services

• Register the trade license with the pre-qualification department of Dubai


Municipality

The registration processes of DED, e-government and pre-qualification of building


department are out of the scope of this document

After registering with e- government, the user name and password is issued for the
contracting company. The company in turn creates users ids for its employees and assigns
services and roles to employees to access the BPCS system. The applicant uses this user
name and password to log on to the BPCS system as a contractor and creates projects and
applications.

Contractors are of different categories. Based on the nature of work and the application,
contractors are classified as General Contractors, Decor Contractors, Digging Contractors
and more. However, there is no categorization of contractors in BPCS. The contractor
selects the category based on the application type.

For the Digging and Decor Permits the Contractors are identified by the activities defined
by pre-qualification section. Else contractors can apply for any type of contractor related
permits.

Dubai Municipality 9
Contractors & Owners User Guide BPCS

4.2 Logging in to BPCS


To log in to BPCS:

Step Action

1. Open the web browser (Internet Explorer is recommended) and enter the
following URL: www.dm.gov.ae. The following page is displayed.

Figure 4-1: Dubai Municipality Homepage


2. Enter the User Name and Password. After the credentials are verified the DM
services page is displayed. Click the Building & Control Services link listed as
one of the DM Services. The BPCS homepage is displayed in a new window.

Dubai Municipality 10
Contractors & Owners User Guide BPCS

Figure 4-2: BPCS Homepage


3. The home page is divided into two panes: Tasks and Messages and General
Messages Pane.
4. The Tasks and Messages pane lists the notifications received from the Dubai
Municipality with regards to the submitted applications. It displays details such as
Message Date, Sender, Message, Application Type, Application Status,
Parcel number and Application number.
5. It also allows you to search for information based on Parcel Id, Project Number,
Application Number, Application Status, and Message Date.
6. The General messages pane displays any communication/ messages sent by the
Dubai Municipality.
7. It displays details such as Message Date, Sender, and the Message. You can also
send messages to the Dubai Municipality for any communication relating to the
application follow up.
8. To send a general message, click the Send General Messages link. The Send
Messages screen is displayed.

Dubai Municipality 11
Contractors & Owners User Guide BPCS

Figure 4-3: Send General Messages Screen


9. Enter the message in the message box. To send the message, and click the Send
Message button.
10. To cancel the message, click the Reset button.
11. To return to the homepage, click the App. Follow Up link.

Dubai Municipality 12
Contractors & Owners User Guide BPCS

5 Projects
A project refers to a new file opened by the consultants and contractors to apply for any
permit related work on the parcel. A project can have more than one application (but only
one draft application per applicant is allowed in the same project). A Contractor can have
more than one project for different building assignments, and more than one application
for each project. Each project has a unique project number which is generated by BPCS
when the first application in the project is submitted. If there are no submitted
applications in the project, then the application is assigned a draft number.

Parcel refers to a defined plot of land in an area. A parcel could be an empty plot of land,
or a land with building existing on it. Each parcel has a unique parcel id which is
provided by the Geographical Information System (GIS). It is mandatory for the
consultant to provide the parcel id when applying for the any building permit. A parcel id
is a seven digit number, where first 3 digits represent the Community number.

5.1 Creating a new project


Contractors can create a new project for different application types.

To create a new project:

Step Action

1. Click the Working Area link on the homepage. The following screen is
displayed.

Dubai Municipality 13
Contractors & Owners User Guide BPCS

Figure 5-1: Working Area


2. Click the New Project button. The following screen is displayed.

Figure 5-2: Project Information


It is mandatory to fill out the fields with an asterisk (*) against the field name.

Dubai Municipality 14
Contractors & Owners User Guide BPCS

3. Enter a description for the project in the Project Description field.


4. You will notice that the Contractor Name is automatically displayed.
5. To view the contractor information, click the Cont Info link. The following
screen is displayed.

Figure 5-3: Contractor Information


6. To return to the Project Information screen, click Close.
7. Enter the Owner Password incase the owner needs to access the project.
8. Enter the seven digits Parcel Id allotted to you in the affection plan.
9. To view the geographic location of the parcel, click the Show Map link. The
following screen displaying the location of the parcel is displayed.

Figure 5-4: Map of the Parcel Id

Dubai Municipality 15
Contractors & Owners User Guide BPCS

10. To check if the parcel exists, click the Show Info button. If the parcel exists, the
details such as the community name, parcel status and zone code are displayed.
11. Enter the percentage of the parcel occupied in the %of parcel occupied field.
This field is applicable to projects that have new building projects.
12. Select the check box against the “I agree that I hold an approval letter from
the parcel owner to be his consultant for the specified parcel”.
13. Click the Save button to save the project information. The following screen is
displayed.

Figure 5-5: Project Information


14. This step marks the end of project creation.

Dubai Municipality 16
Contractors & Owners User Guide BPCS

5.2 Viewing Project Details


To View projects:

Step Action

1. Click the Working Area on the home page. The working area screen is
displayed. Scroll down and locate the project details pane.

Figure 5-6: Project Details List


2. The project details pane lists all the open projects with details such as Project
Status, Project No, Project Description, No of applications, Parcel Number,
Project Date, Display Building, and Old System.
3. To view details of a particular project, click the details listed under the Project
Number column. The following project information screen is displayed.

Dubai Municipality 17
Contractors & Owners User Guide BPCS

Figure 5-7: Project Information


4. To view the parcel details of the project, click the details listed under the Parcel
Number column. The parcel details screen is displayed.

Dubai Municipality 18
Contractors & Owners User Guide BPCS

Figure 5-8: Parcel Details


5. The parcel details screen displays details of the Affection Plan which includes the
parcel id, the community name and code; the Area of Land which includes
affected area, balance area and total area; the Zoning Details such as the set back,
the land usage, height, parking and remarks if any; and Miscellaneous, Parcel
Gate Level and Exception details if any.
6. If the parcel has existing building, and you wish to view the building details, click
the View link listed in the Display Building Details column. The following
screen is displayed.

Dubai Municipality 19
Contractors & Owners User Guide BPCS

Figure 5-9: Building Details


7. To view the number of application in the project, click View App. The
application details associated with the project are displayed.

Figure 5-10: Permit Applications


8. To view the version details of the application listed in the project, click the
number listed in Version Number column. The following screen is displayed.

Dubai Municipality 20
Contractors & Owners User Guide BPCS

Figure 5-11: Application Versions


9. To view the application details, click the View link listed under the App. Details
column. The following screen is displayed.

Dubai Municipality 21
Contractors & Owners User Guide BPCS

Figure 5-12: Permit Application Details


10. To return to the home page, click the App. Follow Up link.

Dubai Municipality 22
Contractors & Owners User Guide BPCS

5.3 Deleting a Project


To delete a project:

You cannot recover a project once it has been deleted. So make sure you don’t need the
project before deleting the same.

Step Action

1. Click the Working Area tab on the homepage. The working area screen is
displayed.
2. Scroll down to the Project details pane and select the check box against the
project you wish to delete.

Projects which have one or more submitted applications cannot be deleted. You will notice
that the check box under the Delete column is grayed out for such projects.

Figure 5-13: Select Project for deletion


3. Click the Delete Project button. The following screen, asking you to confirm the
deletion is displayed.

Figure 5-14: Confirm Deletion


4. To delete the project, click Ok. Else click Cancel.

Dubai Municipality 23
Contractors & Owners User Guide BPCS

6 Applications
Application refers to the permit request forms that are submitted by consultants and
contractors to get DM’s permission before initiating buildings or parcel related work. All
applications are linked to a project. Each application has a unique number made up of
three parts: Project Number, Application Number and Application Version Number.

For instance, in the application id: 118183 - 10 – 1:

118183 –is the project number,


10-is the application number, and
1-is the version number of the application.

An application has to be associated with a project. An application cannot be independent of a


project.

Application Groups & Types

The permit applications are arranged in below hierarchy:

• Processes Group
o Application Types
Applications

A Process group is set of related application/permit types

An application type defines the purpose of application. One application type can only
belong to one process group.

BPCS has categorized applications into six process groups. The five process groups
related to contractors are:

• Adjustments/additional/demolition permit applications


• Miscellaneous services regarding permit application
• Applications for owners & decor companies
• Permission for road services and temporary works
• Special services & Exceptions

Application types are categorized into process groups for easy identification and
allocation of application types. For instance, the new building permit application group
has two application types: Preliminary and Final new building.

Dubai Municipality 24
Contractors & Owners User Guide BPCS

The application types associated with each the above six process groups are given below:

• Adjustment/Additional/Demolition permit application


o Building demolition permit
• Miscellaneous services regarding permit application
o Request to increase electricity power
o Request additional meters
o Building number requests
o For whom it may concern request
o Blue prints photocopying and stamping requests
o Renew permit for 6 months request
o Extend approval validity request
o Permit cancellation before start of work request
o Building permit application cancellation request
o Request for unblocking
• Applications for owners & decor companies
o Adjustment and addition permit (Simple-Owner)
o Maintenance permit by owner
o Painting permit by owner
o Normal decor permit
o Simple decor permit
o Décor permit before issuing completion certificate
• Permission for road services and temporary works
o Walk side booking permit
o Outside planting permit request
o Pavement permit
o Occupy parcel permit
o Electricity cable permit
o Temporary tents permit
• Special services & Exceptions
o New building style verification
o Request for exceptions

Dubai Municipality 25
Contractors & Owners User Guide BPCS

6.1 Creating a New Application (Generic)


An application is always associated with a project. So, before you can create a new
application, you either have to create a new project or select an existing project.

To create a new application:

Step Action

1. Click the Working Area tab on the homepage. The working area screen is
displayed. Click on the Project Number for which you will create an application.
2. You can create a new project and add an application. For details refer to the
“Creating a new project” section in the About Projects chapter.
3. Alternatively, you can click the View Application link against the project you
want to create a new application for, in the working area. The Applications
screen, listing all the application in the selected project is displayed. Click the
New Application button. The following screen is displayed.

Figure 6-1: Project Information


4. Click the New Application button. The following screen is displayed.

Dubai Municipality 26
Contractors & Owners User Guide BPCS

Figure 6-2: Permit Application


It is mandatory to fill out the fields with an asterisk (*) against the field name.

5. Select a group from the Process Group drop down box. You can choose from
any of the six groups.
6. Select an application type from the Application Type drop down box. Depending
on the process group you select, the application type is displayed.
7. Enter a description for the application.
8. Click the Save Application button. The new application is created for the
selected project and you are prompted to fill in further details.
The above is a generic procedure for creating an application. As stated earlier, for each
of the six process groups selected during application creation different application types
are displayed. The application creation procedure for each of the group and its application
type is given in the following sections of the manual.

Dubai Municipality 27
Contractors & Owners User Guide BPCS

7 Application for Building Demolition

A building demolition application is submitted when you have to demolish for complete
demolition or partial demolition. In complete demolition, the whole building is brought
down where as in partial demolition either some floors or a part of the building is
demolished.
Building Demolition can be accomplished manually or mechanically. This section
describes the steps to submit an application for Manual and Mechanical building
demolition.

Dubai Municipality 28
Contractors & Owners User Guide BPCS

7.1 Building Demolition Permit – Manual

To submit a manual building demolition permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application screen
is displayed.

Figure 7-1: Permit Application

Dubai Municipality 29
Contractors & Owners User Guide BPCS

2. Select the Adjustment Addition Demolition Permit application option from the
process group drop down box.
3. Select the Building Demolition Permit option from the application type drop
down box.
4. Enter a Description for the application.
5. Select the type of contract work from the Cont. Work Type drop down box. You
can choose from Minor, Medium, Major, and Special Works option. Here, we
have chosen the Medium Works option.
6. Enter name of the insurance company in the Insurance Company field.
7. Enter the policy number in the Policy Number field.
8. Enter the insured amount in the Insurance Amount field.
9. Select the type of demolition from the Demolition Type drop down box. You can
choose between Manual, Mechanical and According to approved demolition
drawings option. Here, we have chosen the Manual option.
10. Click the Save Application button. The Permit Application screen is displayed.
11. Click the Building Card link. The following screen is displayed.

Figure 7-2: Select Building Card Screen


Only building with the status Completion Certificate Issued can be selected for building demolition.

12. Select the building you want to demolish and select the Complete Building
Demolition option from the Select Operation drop down box. Click Go button.
The following screen is displayed.

Dubai Municipality 30
Contractors & Owners User Guide BPCS

Figure 7-3: Confirm Building Demolition


13. To continue with the building demolition, click OK. The following screen is
displayed.

Figure 7-4: Changed Status


14. You will notice that the modified status for the selected building is Yes. Click the
Permit application button and return to the Permit Application screen. Scroll
down and click the Submit button. The following screen is displayed.

Dubai Municipality 31
Contractors & Owners User Guide BPCS

Figure 7-5: Application Summary


15. Click the Submit Now button. The following screen is displayed.

Figure 7-6: Create Charges


16. If you want to make some changes to the permit application, click cancel. Else,
click Ok.
17. The application is submitted and a message prompting you to pay the charges is
displayed. For details refer to the section 13.1 Creating Charges in the appendix.
After paying charges return to the permit application page by clicking the Permit
Application link. The following screen is displayed.

Dubai Municipality 32
Contractors & Owners User Guide BPCS

Figure 7-7: Submitted Permit Application


18. You will notice that a task has been generated for the DM official and a message
about your application submission is displayed.
19. Also, the final status of the application is changed from New to Submitted
20. You can also view the application submission message in the application follow
up screen.
21. This step marks the end of creating an application to demolish a building
manually.

Dubai Municipality 33
Contractors & Owners User Guide BPCS

7.2 Building Demolition Permit – Mechanical

To submit a mechanical building demolition permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 7-8: Permit Application

Dubai Municipality 34
Contractors & Owners User Guide BPCS

2. Select the Adjustment Addition Demolition Permit application option from


the process group drop down box.
3. Select the Building Demolition Permit option from the application type drop
down box.
4. Enter a Description for the application.
5. Select the type of contract work from the Cont. Work Type drop down box.
You can choose from Minor, Medium, Major, and Special Works option.
Here, we have chosen the Medium Works option.
6. Enter name of the insurance company in the Insurance Company field.
7. Enter the policy number in the Policy Number field.
8. Enter the insured amount in the Insurance Amount field.
9. Select the type of demolition from the Demolition Type drop down box. You
can choose between Manual, Mechanical and According to approved
demolition drawings option. Here, we have chosen the Mechanical option.
10. Click the Save Application button. The Permit Application screen is
displayed.
11. Click the Building Card link. The following screen is displayed.

Figure 7-9: Building Card


Only building with the status Completion Certificate Issued can be selected for building demolition.

12. Select the building you want to demolish and select the Demolish Floors
option from the Select Operation drop down box. Enter the total number of
floors you want to demolish and Click the Go button. The following screen is
displayed.

Dubai Municipality 35
Contractors & Owners User Guide BPCS

Figure 7-10: Confirm Demolition


13. To continue with the building demolition, click Ok. The following screen is
displayed.

Figure 7-11: Modified Building Status


14. You will notice that the modified status for the selected building is Yes. Click
the Permit application button and return to the Permit Application screen.
Scroll down and click the Submit button. The following screen is displayed.

Dubai Municipality 36
Contractors & Owners User Guide BPCS

Figure 7-12: Application Summary


15. Click the Submit Now button. The following screen is displayed.

Figure 7-13: Create Charges


16. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
17. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 37
Contractors & Owners User Guide BPCS

Figure 7-14: Submitted Permit Application


18. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
19. Also, the final status of the application is changed from New to Submitted
20. You can also view the application submission message in the application
follow up screen.
21. This step marks the end of creating an application to demolish a building
mechanically.

Dubai Municipality 38
Contractors & Owners User Guide BPCS

8 Miscellaneous Service Request


Miscellaneous services refer to services such as requesting building numbers, letters
from municipality, renewing permits, canceling permits, unblocking parcels and
more.
The permit application process for the miscellaneous services differs on the type of
service required. The miscellaneous services handled by contractors are:
• Permit to increase power supply
• Permit for additional meters
• Permit for building number
• To Whom It May Concern letter
• Photocopying and stamping blueprints
• Extending approval validity
• Renewing permit for 6 months
• Requesting a building permit cancellation before start of work
• Unblocking a parcel; and
• Requesting permit cancellation
This section describes the application process for each of the miscellaneous services.

Dubai Municipality 39
Contractors & Owners User Guide BPCS

8.1 Requesting an Increase in Electric Power

To increase the power supply in buildings, contractors are required to submit an


application to DM. The DM reviews the application and can either approve or reject the
application.

To submit a request to increase electric power:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process. Follow steps 1-3. The Permit Application
screen is displayed.

Figure 8-1: Application to Increase Electricity

Dubai Municipality 40
Contractors & Owners User Guide BPCS

2. Select the Miscellaneous services regarding permit application option from


the process group drop down box.
3. Select the Request to Increase Electricity Power option from the application
type drop down box.
4. Enter a Description for the application.
5. Enter the applicant’s mobile number in the Applicant Mobile Number field.
6. Enter the applicant’s telephone number in the Applicant Telephone Number
field.
7. Enter the applicants email id in the Applicant Email field and click the Save
Application button. The following screen is displayed.

Figure 8-2: Permit Application

Dubai Municipality 41
Contractors & Owners User Guide BPCS

8. Click the Click here to Increase Power Supply link as shown in figure 8-2
against the Increase Electrical Power field. The following screen is displayed.

Figure 8-3: Select Building


9. Select the building(s) you want to increase the electric supply and click the
Close button. The following screen is displayed.

Figure 8-4: Increase Electricity Details


10. You will notice that the selected building(s) are displayed against the Select
Buildings field.
11. Enter details such as the Units of Electricity required per floor, the Increased
Load and the reason for the increase and click Add. The following screen is
displayed.

Dubai Municipality 42
Contractors & Owners User Guide BPCS

Figure 8-5: Add Building Details


12. You will notice that the entered street details are displayed below. Click the
Done button. The permit application screen is displayed.
13. To edit an entry, select the radio button against the meters you want to edit,
and click the edit link. Make the required changes and click the Done button.
14. To remove a request, select the radio button against the meters you want to
remove, select the check box under Delete and click the Delete link. The
electric power detail is removed from the list.
15. Scroll down and click the Submit Application button. The following screen
is displayed.

Dubai Municipality 43
Contractors & Owners User Guide BPCS

Figure 8-6: Submit Application


16. Click Submit Now button. The following dialog box is displayed.

Figure 8-7: Create Charges


17. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
18. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 44
Contractors & Owners User Guide BPCS

Figure 8-8: Submitted Application to increase Electricity


19. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
20. Also, the final status of the application is changed from New to Submitted
21. You can also view the application submission message in the application
follow up screen.
22. This step marks the end of creating an application to increase electric power.

Dubai Municipality 45
Contractors & Owners User Guide BPCS

8.2 Requesting Additional Meters

This application is for the applicants (contractor/owner) to get the NOC for
additional/new electricity/water meters. As the electricity or water meter has the same
application form, and has same details so system will have one application type for both
type of meters.

To submit a request for additional meters:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 8-9: Application to Request Additional Meters

Dubai Municipality 46
Contractors & Owners User Guide BPCS

2. Select the Miscellaneous Services Regarding Permit Application option


from the process group drop down box.
3. Select the Request Additional Meters option from the application type drop
down box.
4. Enter a Description for the application.
5. Enter the applicant mobile number in the Applicant Mobile Number field.
6. Enter the applicant telephone number in the Applicant Telephone Number
field.
7. Enter the applicant email in the Applicant Email field and click the Save
Application button. The following screen is displayed.

Figure 8-10: Permit Application


8. Click the Click here to add extra meters link against the Additional Meters
field. The following screen is displayed.

Dubai Municipality 47
Contractors & Owners User Guide BPCS

Figure 8-11: Request Meter Details


9. Select the water meter option from the Meter Type drop down box. You can
choose from the following options:
a. Water Meter,
b. Electricity Meter
c. Shared Water Meter
d. Shared Electricity Meter
10. Click the Select button and select the building(s) you are requesting the
additional meters for.
11. Select the floor and enter Unit Details for the floor you are adding the new
meters too.
12. Enter the number of New Meters required and click Add. The following
screen is displayed.

Figure 8-12: Add Meter details

Dubai Municipality 48
Contractors & Owners User Guide BPCS

13. You will notice that the entered building details are displayed below. Click the
Done button. The permit application screen is displayed.
14. To edit an entry, select the radio button against the meters you want to edit,
and click the edit link. Make the required changes and click the Done button.
15. To remove an added meter, select the radio button against the meters you want
to remove, select the check box under Delete and click the Delete link. The
meter is removed from the list of added meters.
16. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 8-13: Application Summary


17. Click Submit Now button. The following dialog box is displayed.

Figure 8-14: Create Charges


18. If you want to make some changes to the permit application, click cancel.
Else, click Ok.

Dubai Municipality 49
Contractors & Owners User Guide BPCS

19. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Figure 8-15: Submitted application to request additional meters


20. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
21. Also, the final status of the application is changed from New to Submitted
22. You can also view the application submission message in the application
follow up screen.
23. This step marks the end of submitting an application to request additional
meters.

Dubai Municipality 50
Contractors & Owners User Guide BPCS

8.3 Requesting a Building Number

This application is for the applicants (Consultant/Contractor or Owner) to get the


Building number allocated by buildings department to uniquely identify the
building/compound buildings.
To request for a building number:

It is mandatory to fill out the fields with an asterisk (*) against the field name

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 8-16: Application to Request Building Number

Dubai Municipality 51
Contractors & Owners User Guide BPCS

Only buildings with status permit delivered and completion certificate issued qualify for
building number requests.

2. Select the Miscellaneous Services Regarding Permit Applications


option from the process group drop down box.
3. Select the Request Building Number option from the application type
drop down box.
4. Enter a Description for the application.
5. Enter the applicant’s mobile number in the Applicant mobile number
field.
6. Enter the applicant’s telephone number in the Applicant Telephone
Number field.
7. Enter the applicants email id in the Applicant Email field and click the
Save Application button. The following screen is displayed.

Figure 8-17: Permit Application

Dubai Municipality 52
Contractors & Owners User Guide BPCS

8. Click the Add/View Building Number requests link as shown in figure


8-17 against the building number requests field. The following screen is
displayed.

Figure 8-18: Request Building Number


9. Select direction of the street from the Street Directions drop down box
and enter details such as the number of gates the building has.
10. If the building is surrounded by a compound wall, select the Is
Compound check box. Else leave it unchecked.
11. Click the select button adjacent to the select building field. The following
screen is displayed.

Figure 8-19: Select Building


12. Select the check box against the building(s) you are requesting the
number for. Click the close button.
13. If the building is surrounded by a compound wall, select the Is
Compound checkbox.
14. The request for building number screen is displayed. Click Add. The
following screen is displayed.

Dubai Municipality 53
Contractors & Owners User Guide BPCS

Figure 8-20: Add Building Details


15. To edit an entry, select the radio button against the meters you want to
edit, and click the edit link. Make the required changes and click the Done
button.
16. To remove a building number, select the radio button against the meters
you want to remove, select the check box under Delete and click the
Delete link. The building number detail is removed from the list of
building number requests.
17. You will notice that the added street and building details are displayed in
the screen below. Click the Done button. The permit application screen is
displayed.
18. Scroll down and click the Submit Application button. The following
screen is displayed.

Dubai Municipality 54
Contractors & Owners User Guide BPCS

Figure 8-21: Application Summary


19. Click the Submit Now button. The following dialog box is displayed.

Figure 8-22: Create Charges


20. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
21. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 55
Contractors & Owners User Guide BPCS

Figure 8-23: Submitted Application to request Building Number


22. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
23. Also, the final status of the application is changed from New to
Submitted
24. You can also view the application submission message in the application
follow up screen.
25. This step marks the end of submitting an application to request a building
number.

Dubai Municipality 56
Contractors & Owners User Guide BPCS

8.4 Requesting a To Whom It May Concern Letter

This process is for the applicants to request for a letter attested by DM authorities.
To request for a to whom it may concern letter:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 8-24: Application to request a letter


2. Select Miscellaneous services regarding permit applications option
from the process group drop down box.

Dubai Municipality 57
Contractors & Owners User Guide BPCS

3. Select the To Whom It May Concern option from the application type
drop down box.
4. Enter a Description for the application
5. You will notice that the name of the applicant appears automatically in
both English and Arabic.
6. Enter the applicant’s mobile number in the Applicant Mobile Number
field.
7. Enter the applicant’s telephone number in the Applicant Telephone
Number field.
8. Enter the applicants email id in the Applicant Email field and click the
Save Application button. The permit application screen is displayed.
9. Scroll down and click the Submit Application button. The following
screen is displayed.

Figure 8-25: Application Summary


10. Click the Submit Now button. The following dialog box is displayed.

Dubai Municipality 58
Contractors & Owners User Guide BPCS

Figure 8-26: Create Charges


11. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
12. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 59
Contractors & Owners User Guide BPCS

Figure 8-27: Submitted Application for whom it may concern letter


13. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
14. Also, the final status of the application is changed from New to
Submitted
15. You can also view the application submission message in the application
follow up screen.
16. This step marks the end of submitting an application for the to whom it
may concern letter.

Dubai Municipality 60
Contractors & Owners User Guide BPCS

8.5 Photocopying and Stamping Blueprints

This application is for the applicants (Consultant/Contractor/owners) to get the photocopy


of the permit drawings/blueprints and also the official stamping of drawings. There is no
change in process depending on the handing over of blueprints.

To submit blueprints for photocopying and stamping:

It is mandatory to fill out the fields with an asterisk (*) against the field name:

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 8-28: Application for Photocopying & Stamping

Dubai Municipality 61
Contractors & Owners User Guide BPCS

2. Select Miscellaneous services regarding permit applications option


from the process group drop down box.
3. Select the Blue Print Photocopying and Stamping option from the
application type drop down box.
4. Enter a Description for the application
5. Enter the applicant’s mobile number in the Applicant Mobile Number
field.
6. Enter the applicant’s telephone number in the Applicant Telephone
Number field.
7. Enter the applicants email id in the Applicant Email field.
8. Select the Photocopy with Stamping option against the Request For field.
You can choose from Only Photocopy, Photocopy and Stamping and
Only Stamping option.
9. Select the desired option from the Photocopy Type drop down box. You
can choose from Hardcopy, CD and Online options.
10. Select the shop you are getting the blueprints photocopied and stamped.
You can choose from pre-defined list of shops that is suitable for
applicant. Click the Save Application button. The permit application
screen is displayed.
11. Click the Select Permits for Photocopying/Stamping link against the
blueprint photocopying field. The following screen is displayed.

Figure 8-29: Blue prints & photocopying details


12. To select all the permits on the parcel or plot, select the checkbox against
Select All the permits on this parcel/plot.
13. To select specific permits, enter the permit number and select the
appropriate building type from the drop down box. If you choose a multi
storey or a public building, you will be prompted to enter the number of
floors. Click the Save button. The building permit screen is displayed.

You can select a maximum of 3 permits that are not available in the system.

Dubai Municipality 62
Contractors & Owners User Guide BPCS

If the permit you want to stamp is not listed, enter the permit number and select the building
below and save the details.

14. Scroll down and click the Submit Application link. The following screen
is displayed.

Figure 8-30: Application Summary


15. Click Submit Now button. The following dialog box is displayed.

Figure 8-31: Create Charges


16. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
17. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 63
Contractors & Owners User Guide BPCS

Figure 8-32: Submitted Application for photocopying & stamping blueprints


18. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
19. Also, the final status of the application is changed from New to
Submitted
20. You can also view the application submission message in the application
follow up screen.
21. This step marks the end of creating a permit application for photocopying
and stamping blueprints.

Dubai Municipality 64
Contractors & Owners User Guide BPCS

8.6 Renewing Permit for 6 Months

Applications with the status permit delivered are valid for six months from the date of
issue. If the Contractors haven’t begun construction work by the fifth month, they can
request DM to renew the permit for 6 months. Contractors submit a request to DM to
renew the permit. DM reviews the application and can either approve or reject the
same.
To submit a request to renew the permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 8-33: Application to renew permit

Dubai Municipality 65
Contractors & Owners User Guide BPCS

2. Select the Miscellaneous services regarding permit applications from the


process group drop down box.
3. Select the Renew permit for 6 months option from the application type drop
down box.
4. Enter a Description for the application and a valid Explanation for extending
the approval.
5. Select the application you want to renew the permit validity for from the
Application for renewal drop down box.

Only application with the status permit delivered and about to expire in a month’s time are
displayed in the application for renewal drop down box.

6. Click the Save Application button. The permit application screen is


displayed.
7. Scroll down and click the Submit Application screen. The following screen
is displayed.

Figure 8-34: Application Summary


8. Click the Submit Now button. The following dialog box is displayed.

Dubai Municipality 66
Contractors & Owners User Guide BPCS

Figure 8-35: Create Charges


9. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
10. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 67
Contractors & Owners User Guide BPCS

Figure 8-36: Submitted application to renew permit


11. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
12. Also, the final status of the application is changed from New to Submitted
13. You can also view the application submission message in the application
follow up screen.
14. This step marks the end of submitting an application to renew the permit for 6
months.

Dubai Municipality 68
Contractors & Owners User Guide BPCS

8.7 Extending Approval Validity


Approved permit applications are valid for nine months from the date of approval.
Contractors can apply to extend the approval validity one month before the expiry
period. It is recommended to submit the approval extension a month before the expiry
date. Contractors submit a request to DM to extend the approval. DM reviews the
application and can either approve or reject the same.
To submit a request to extend the approval validity:

It is mandatory to fill out the fields with an asterisk (*) against the field name

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 8-37: Application to extend approval validity

Dubai Municipality 69
Contractors & Owners User Guide BPCS

2. Select the Miscellaneous services regarding permit applications from


the process group drop down box.
3. Select the Extending Approval Validity option form the application type
drop down box.
4. Enter a Description for the application and a valid Explanation for
extending the approval.
5. Select the application you want to extend the approval for from the
Application for renewal drop down box.

Only approved application, about to expire in a month’s time are displayed in the application
for renewal drop down box.

6. Click the Save Application button. The permit application screen is


displayed.
7. Scroll down and click the Submit Application screen. The following
screen is displayed.

Figure 8-38: Application Summary


8. Click the Submit Now button. The following dialog box is displayed.

Dubai Municipality 70
Contractors & Owners User Guide BPCS

Figure 8-39: Create Charges


9. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
10. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 71
Contractors & Owners User Guide BPCS

Figure 8-40: Submitted Application t to extend approval


11. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
12. Also, the final status of the application is changed from New to
Submitted
13. You can also view the application submission message in the application
follow up screen.
14. This step marks the end of submitting a request to extend the approval
validity.

Dubai Municipality 72
Contractors & Owners User Guide BPCS

8.8 Requesting Permit Cancellation before Start of Work

Contractors can request DM to cancel permit application before start of work. However,
Contractors will have to provide a valid reason for requesting the cancellation.
To request a cancellation of a delivered work permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 8-41: Application to request permit cancellation before work begins

Dubai Municipality 73
Contractors & Owners User Guide BPCS

2. Select the Miscellaneous services regarding permit applications from


the process group drop down box.
3. Select the Permit Cancellation before Start of Work option form the
application type drop down box.
4. Enter a Description for the application.
5. Select the application whose permit you want to cancel from the
Application for Cancellation drop down box and click the Save
Application button. The permit application screen is displayed.

Only applications with the status permit delivered can be selected for cancellation.

6. Scroll down and click the Submit Application screen. The following
screen is displayed.

Figure 8-42: Application Summary


7. Click Submit Now button. The following dialog box is displayed.

Dubai Municipality 74
Contractors & Owners User Guide BPCS

Figure 8-43: Create Charges


8. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
9. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 75
Contractors & Owners User Guide BPCS

Figure 8-44: Submitted application to request permit cancellation before work begins
10. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
11. Also, the final status of the application is changed from New to
Submitted
12. You can also view the application submission message in the application
follow up screen.
13. This step marks the end of submitting an application to request the permit
cancellation before start of work.

Dubai Municipality 76
Contractors & Owners User Guide BPCS

8.9 Applying for Building Permit Application Cancellation

Contractors can request DM to cancel approved permit application after the


application is approved. However, Contractors will have to provide a valid reason for
requesting the cancellation. Contractors submit a cancellation application to DM, who
review the same and either approve or reject the application.

To submit a building permit cancellation application request:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 8-45: Application to cancel building permit application

Dubai Municipality 77
Contractors & Owners User Guide BPCS

2. Select the Miscellaneous services regarding permit applications from


the process group drop down box.
3. Select the Building Permit Application Cancellation option form the
application type drop down box.
4. Enter a Description for the application and a valid explanation for
extending the approval.
5. Select the application you want to cancel from the Application for
renewal drop down box.

Only approved application are displayed in the application for renewal drop down box.

6. Click the Save Application button. The permit application screen is


displayed.
7. Scroll down and click the Submit Application screen. The following
screen is displayed.

Figure 8-46: Application Summary


8. Click Submit Now button. The following dialog box is displayed.

Dubai Municipality 78
Contractors & Owners User Guide BPCS

Figure 8-47: Create Charges


9. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
10. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 79
Contractors & Owners User Guide BPCS

Figure 8-48: Submitted Application for building permit application cancellation


11. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
12. Also, the final status of the application is changed from New to
Submitted
13. You can also view the application submission message in the application
follow up screen.
14. This step marks the end of submitting an application to cancel the building
permit application.

Dubai Municipality 80
Contractors & Owners User Guide BPCS

9 Permit Application for Owners & Decor Companies


Contractors have to take permission from DM to begin the decoration or interior work
in the buildings. Contractors can apply for this type of permit either for a new
building or a building under construction.
This section describes the application process for the following:
• Requesting an adjustment permit (simple owner)
• Maintenance permit
• Painting permit
• Normal decor permit
• Simple decor permit and
• Decor permit before the completion certificate issue

Dubai Municipality 81
Contractors & Owners User Guide BPCS

9.1 Requesting an Adjustment Addition Permit (Simple –


Owner)

This application is used to make simple modifications in either a new building or an


existing building. By simple modifications we mean that the contractor can carry out
decor work, or painting work and other simple tasks. The contractor will not be able
to add new buildings or floors, or modify the floor plan etc.
To request an adjustment addition permit (simple –owner):

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 9-1: Application for Simple owner adjustment/addition permit


2. Select the Application for owners and decor companies’ option from the
process group drop down box.

Dubai Municipality 82
Contractors & Owners User Guide BPCS

3. Select the Adjustment and Addition permit (Simple-Owner) option from


the application type drop down box.
4. Enter a Description for the application and click the Save Application
button. The permit application screen is displayed.

Figure 9-2: Building Card


5. Scroll down and click the Building Card link. The following screen is
displayed.

Figure 9-3: Building on Parcel


Besides modifying buildings, you can view and modify building details, floor details, and
existing modifications, fix building details, fix floor details, and fix building summary details.
For details refer to section 13.2 Viewing Modification Options in the appendix.

6. Select the building(s) you want to make decor changes to by clicking the
checkbox in the left column and click the Save Selected building button. The
following screen is displayed.
7. Scroll down and click the Submit Application button. The following screen
is

Dubai Municipality 83
Contractors & Owners User Guide BPCS

Figure 9-4: Modified Building


8. You will notice that the status for the selected building in the modified
column is changed to Yes. Click the permit application button. The permit
application screen is displayed.
9. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 9-5: Application Summary

Dubai Municipality 84
Contractors & Owners User Guide BPCS

10. Click Submit Now button. The following dialog box is displayed.

Figure 9-6: Create Charges


11. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
12. The application is submitted and a message prompting you to pay the charges
is displayed.
13. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 85
Contractors & Owners User Guide BPCS

Figure 9-7: Submitted application for Simple Owner adjustment addition permit
14. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
15. Also, the final status of the application is changed from New to Submitted.
16. You can also view the application submission message in the application
follow up screen.
17. This step marks the end of submitting an application for a simple owner
adjustment/addition permit.

Dubai Municipality 86
Contractors & Owners User Guide BPCS

9.2 Requesting a Maintenance Permit

Contractors and owners can apply for maintenance permits for the works that are not
considered as modification the building. After reviewing the application, DM either
accepts or rejects the application.
To request a maintenance permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 9-8: Application for maintenance

Dubai Municipality 87
Contractors & Owners User Guide BPCS

2. Select the Application for owners and decor companies’ option from the
process group drop down box.
3. Select the Maintenance permit by Owner option from the application type
drop down box.
4. Enter a Description for the application and click the Save Application
button. The permit application screen is displayed.
5. Select the Major Works option from the Contr. Work type drop down box.
You can choose from Minor, Medium, and Major and Special Case options.
6. Click the Save Application button. The permit application screen is
displayed.
7. Scroll down and click the Building Card link. The following screen is
displayed.

Figure 9-9: Building on Parcel


8. Besides making modifications, you can View building details, Floor details,
and Details of maintenance, Fill building summary, Fix floor and usage
info, and Fix building details.
9. To view the building details, select the View Building Details option from the
Select Operation drop down box and click the Go button. The following
screen is displayed.

Dubai Municipality 88
Contractors & Owners User Guide BPCS

Figure 9-10: Building Details Screen.


10. To return to the building card details screen, click the Close button.
11. To view the floor details, select the view building details option from the
Select Operation drop down box and click the Go button. The following
screen is displayed.

Figure 9-11: View Floor Details


12. To return to the building card details screen, click the Close button.

Dubai Municipality 89
Contractors & Owners User Guide BPCS

13. To view the details of maintenance, select the Maintenance Details option
from the Select Operation drop down box and click the Go button. The
following screen is displayed.

Figure 9-12: Maintenance Details


14. Select the checkbox against the floors you want to view maintenance details
for and click the View button. The following screen is displayed.

Figure 9-13: Maintenance Details

Dubai Municipality 90
Contractors & Owners User Guide BPCS

15. The screen displays the maintenance details. To return to the building card
details screen, close the screen.
16. To fill the building summary details, select the Fix Building Summary
details option from the Select Operation drop down box and click the Go
button. The following screen is displayed.

Figure 9-14: Fix Building Summary


17. To add or remove floors, click the + /- button against the floor type and click
the Save button. To return to the building card details screen, click the close
button.
18. To fix floor and usages info, select the Fix Floor and Usages info option
from the Select Operations drop down box and click the Go button. The
following screen is displayed.

Dubai Municipality 91
Contractors & Owners User Guide BPCS

Figure 9-15: Fix floor and Usage Details


19. To make changes to the floor and usage details, enter the required information
and click the Save button. To return to the building card details screen, click
the close button.
20. To fix building details, select the Fix Building Details option from the Select
Operation drop down box and click the Go button. The following screen is
displayed.

Dubai Municipality 92
Contractors & Owners User Guide BPCS

Figure 9-16: Fix Building Details


21. To make changes to the building details, enter the required information and
click the Save button. To return to the building card details screen, click the
close button.
22. Select the building(s) you want to undertake maintenance work for by clicking
the check box on the left and click the Save Selected building button. The
following screen is displayed.

Figure 9-17: Modified Building

Dubai Municipality 93
Contractors & Owners User Guide BPCS

23. You will notice that the status for the selected building in the modified
column is changed to Yes. Click the permit application button. The permit
application screen is displayed.
24. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 9-18: Application Summary


25. Click Submit Now button. The following dialog box is displayed.

Figure 9-19: Create Charges


26. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
27. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 94
Contractors & Owners User Guide BPCS

Figure 9-20: Submitted Application for maintenance


28. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
29. Also, the final status of the application is changed from New to Submitted.
30. You can also view the application submission message in the application
follow up screen.
31. This step marks the end of submitting an application for maintenance permit
by the owner.

Dubai Municipality 95
Contractors & Owners User Guide BPCS

9.3 Requesting a Painting Permit

To submit a painting request:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 9-21: Application for painting


2. Select the Application for owners and decor companies’ option from the
process group drop down box.
3. Select Painting permit by Owner (if applicant is owner) or Painting Permit
(if applicant is contractor) option from the application type drop down box.

Dubai Municipality 96
Contractors & Owners User Guide BPCS

4. Enter a Description for the application.


5. Select one of the contractor work type option from the Contr. Work type
drop down box. You can choose from Minor, Medium, and Major and
Special Case options.
6. Select the Internal and External option from the painting type drop down
box. You can choose from Internal, External and Internal and External
option to specify the painting. Click the Save Application button. The permit
application screen is displayed.

Figure 9-22: Building Card


7. Scroll down and click the Building Card link. The following screen is
displayed.

Figure 9-23: Building on Parcel


Besides modifying buildings, you can view and modify building details, floor details, and existing
modifications, fix building details, fix floor details, and fix building summary details. For details
refer to section 13.2 Viewing Modification Options in the appendix.

8. Select the building(s) you want to paint by clicking the checkbox in the left
column and click the Save Selected building button. The following screen is
displayed.

Dubai Municipality 97
Contractors & Owners User Guide BPCS

Figure 9-24: Modify Building


9. You will notice that the status for the selected building in the modified
column is changed to Yes. Click the permit application button. The permit
application screen is displayed.
10. Scroll down and click the Submit Application button. The following screen
is displayed

Figure 9-25: Application Summary

Dubai Municipality 98
Contractors & Owners User Guide BPCS

11. Click Submit Now button. The following dialog box is displayed.

Figure 9-26: Create Charges


12. If you want to make some changes to the permit application, click cancel.
Else, click Ok. The application is submitted and a message prompting you to
pay the charges is displayed.
13. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 99
Contractors & Owners User Guide BPCS

Figure 9-27: Submitted Application for painting


14. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
15. Also, the final status of the application is changed from New to Submitted.
16. You can also view the application submission message in the application
follow up screen.
17. This step marks the end of submitting an application for painting permit.

Dubai Municipality 100


Contractors & Owners User Guide BPCS

9.4 Requesting a Normal Decor Permit

A normal decor permit refers to an application submitted by Contractors to DM to begin


interior works after the building construction is complete or after the completion
certificate issued.
To request a normal decor permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 9-28: Application for Normal Decor Permit

Dubai Municipality 101


Contractors & Owners User Guide BPCS

2. Select the Application for owner and decor companies’ option from the
process group drop down box.
3. Select the Normal Decor permit option from the application type drop
down box.
4. Enter a Description for the application and select the type of work from
the cont work type drop down box.
5. Enter the commercial name in the Commercial Name field.
6. Enter the owner name in the Unit permit owner Name field.
7. Enter the permit number in the Unit permit Number field.
8. Enter the telephone number of the owner in the Unit owner telephone
number field and click the Save Application button. The permit
application screen is displayed.

Figure 9-29: Building Card


9. Scroll down and click the Building Card link. The following screen is
displayed.

Figure 9-30: Building on Parcel


Besides modifying buildings, you can view, add and modify building details, floor details, and
existing modifications, fix building details, fix floor details, and fix building summary details. For
details refer to section 13.2 Viewing Modification Options in the appendix.

Dubai Municipality 102


Contractors & Owners User Guide BPCS

10. Select the building you want to apply a decor permit for and select the
Modify building option from the Select Operation drop down box and
click the Go button. The building form usage selection screen is displayed.
scroll down and click the Add Usages/Sub Usages button. The following
screen is displayed.

Figure 9-31: Floor Information


11. Select the floor(s) you want to add make decor changes to and click the
Modify button. A message confirming the save is displayed. Click one of
the usages links, for instance Offices, adjacent to floor info. The following
screen is displayed.

Figure 9-32
12. Enter the Area you want to add decor to and click the Details link
adjacent to the Variation field. The following screen is displayed.

Dubai Municipality 103


Contractors & Owners User Guide BPCS

Figure 9-33: Select Operations on Unit


13. Click the Select Operations on Unit drop down box. You can perform the
following operations on the building: select units for décor, add units for
decor, split units, remove units and merge units.
14. To select units for decor, select the Select Units for Décor option from
the Select operations on unit drop down box as shown in figure 11-6 and
select the number of units you want to add decor to. Click the Save button.
You will notice that the selected units are displayed in the lower pane of
figure 11-6.

Figure 9-34: Select Unit for Décor

Dubai Municipality 104


Contractors & Owners User Guide BPCS

15. . Enter details such as the Name, Number and Contact number for the
unit, and the Electric and Water meter details and click the Save button.
Continue from step 20 for submitting the application.
16. To add a new unit to décor, select the Add Unit option from the select
operations drop down box as show in figure 11-6. The following screen is
displayed.

Figure 9-35: Add New Units


17. Enter details such as the Name, Number and Contact number for the
unit, and the Electric and Water meter details and click the Save button.
Continue from step 20 for submitting the application.
18. To split one to two or more units, select the Split Units option from the
Select Operations on unit drop down box. The following screen is
displayed.

Dubai Municipality 105


Contractors & Owners User Guide BPCS

Figure 9-36: Select Units to Split


19. Select the unit you want to split by select the radio button against the
building and click the Select button. The following screen is displayed.

Figure 9-37: Split Units


20. Enter the number of units you want to split the unit into in the Enter No of
Units to be Split into field as shown in figure 11-9 and click the Split
button. The following screen is displayed.

Dubai Municipality 106


Contractors & Owners User Guide BPCS

Figure 9-38: Split Unit Details


21. Enter details such as the Name, Number and Contact number for the
unit, and the Electric and Water meter details and click the Save button.
Continue from step 20 for submitting the application.
22. To remove a unit, select the Remove Unit option from the select
operations on unit drop down box. The following screen is displayed.

Figure 9-39: Remove Units


23. Select the unit you want to remove by selecting the checkbox against the
unit and click the Select button. The following screen is displayed.

Dubai Municipality 107


Contractors & Owners User Guide BPCS

Figure 9-40: Removed Unit Details


24. You will notice that the selected unit is removed and displayed in the
removed unit details pane. Continue from step 22 to submit the
application.

To merge one or more units, select the merge units operation from the select operations on unit.
Select one or more units and click the select button. The selected units are merged.

25. Close the screen. The office usages screen is displayed. Click the Close
button. The building on parcel screen is displayed. Refresh the building on
parcel screen. The following screen is displayed.
26. Close the screen. The office usages screen is displayed. Click the close
button. The building on parcel screen is displayed. Refresh the building on
parcel screen. The following screen is displayed.

Dubai Municipality 108


Contractors & Owners User Guide BPCS

Figure 9-41: Modified Building


27. You will notice that the status for the selected building in the modified
column is changed to Yes. Click the permit application button. The permit
application screen is displayed.
28. Scroll down and click the Submit Application button. The following
screen is displayed.

Figure 9-42: Submit Application


29. To modify or recheck the modifications, click Ok. To submit the
application, click Cancel. The following screen is displayed.

Dubai Municipality 109


Contractors & Owners User Guide BPCS

Figure 9-43: Application Summary


30. Click Submit Now button. The following dialog box is displayed.

Figure 9-44: Create Charges


31. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
32. The application is submitted and a message prompting you to pay the
charges is displayed.
33. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 110


Contractors & Owners User Guide BPCS

Figure 9-45: Submitted application for normal décor permit


34. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
35. Also, the final status of the application is changed from New to
Submitted.
36. You can also view the application submission message in the application
follow up screen.
37. This step marks the end of submitting an application for normal decor
permit.

Dubai Municipality 111


Contractors & Owners User Guide BPCS

9.5 Requesting a Simple Decor Permit

To submit a simple decor request:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 9-46: Application for simple décor


2. Select the application for owners and decor companies’ option from the
process group drop down box.

Dubai Municipality 112


Contractors & Owners User Guide BPCS

3. Select the Simple Décor Permit option from the application type drop down
box.
4. Enter the commercial name in the Commercial Name field.
5. Enter the owner name in the Unit permit owner Name field.
6. Enter the permit number in the Unit permit Number field.
7. Enter the telephone number of the owner in the Unit owner telephone
number field.
8. Select the type of décor work type from the décor type drop down box. To
select more than one options listed, use the ctrl key on the keyboard and mark
selections. Click the Save Application button. The permit application screen
is displayed.

Figure 9-47: Building Card


9. Scroll down and click the Building Card link. The following screen is
displayed.

Figure 9-48: Building on Parcel


Besides modifying buildings, you can view and modify building details, floor details, and existing
modifications, fix building details, fix floor details, and fix building summary details. For details
refer to section 13.2 Viewing Modification Options in the appendix.

Dubai Municipality 113


Contractors & Owners User Guide BPCS

10. Select the building(s) you want to make decor changes to by clicking the
checkbox in the left column and click the Save Selected building button. The
following screen is displayed.

Figure 9-49: Floors Info


11. Select the floor(s) you want to add make décor changes to and click the
Modify button. A message confirming the save is displayed. Click the offices
link adjacent to floor info. The following screen is displayed
12. Enter the area you want to add decor to and click the Details link adjacent to
the Variation field. The following screen is displayed.

Figure 9-50: Building Units

Dubai Municipality 114


Contractors & Owners User Guide BPCS

13. Click the select units for décor option from the Select operations on unit drop
down box and select the number of units you want to add décor to. Click the
Save button.
14. Enter details such as the name, number and contact number for the unit, and
the electric and water meter details and click the Save button.
15. Close the screen. The office usages screen is displayed. Click the close button.
The building on parcel screen is displayed. Refresh the building on parcel
screen. The following screen is displayed.

Figure 9-51: Modified Building


16. You will notice that the status for the selected building in the modified
column is changed to Yes. Click the permit application button. The permit
application screen is displayed.
17. Scroll down and click the Submit Application button. The following screen
is displayed

Dubai Municipality 115


Contractors & Owners User Guide BPCS

Figure 9-52: Application Summary

18. Click Submit Now button. The following dialog box is displayed.

Figure 9-53: Create Charges


19. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
20. The application is submitted and a message prompting you to pay the charges
is displayed.
21. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 116


Contractors & Owners User Guide BPCS

Figure 9-54: Submitted Application for a Simple décor permit


22. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
23. Also, the final status of the application is changed from New to Submitted.
24. You can also view the application submission message in the application
follow up screen.
25. This step marks the end of submitting an application for a simple décor
permit.

Dubai Municipality 117


Contractors & Owners User Guide BPCS

9.6 Requesting a Decor Permit before Issue of Completion


Certificate

To begin decor works in the building while the construction is on in the building,
Consultants can request DM to issue a decor permit before the completion certificate
is issued. The decor before completion certificate application should be submitted in
the same project that the building belongs to.
To request a decor permit before the completion certificate is issued:
It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 9-55: Application for décor permit before issue of completion certificate

Dubai Municipality 118


Contractors & Owners User Guide BPCS

2. Select the Application for owner and decor companies’ option from the
process group drop down box.
3. Select the Decor permit before issuing completion certificate option from
the application type drop down box.
4. Enter a Description for the application and select the type of work from the
cont work type drop down box.
5. Enter the commercial name in the Commercial Name field.
6. Enter the owner name in the Unit permit owner Name field.
7. Enter the permit number in the Unit permit Number field.
8. Enter the telephone number of the owner in the Unit owner telephone
number field and click the Save Application button. The permit application
screen is displayed.

Figure 9-56: Building Card


9. Scroll down and click the Building Card link. The following screen is
displayed.

Figure 9-57: Building on Parcel


10. Select the building(s) you want to begin the decor works on by clicking the
checkbox in the left column and click the Save Selected Buildings button.
The following screen is displayed.

Dubai Municipality 119


Contractors & Owners User Guide BPCS

Figure 9-58: Modified Building


11. You will notice that the status for the selected building in the modified
column is changed to Yes. Click the permit application button. The permit
application screen is displayed.
12. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 9-59: Application Summary

Dubai Municipality 120


Contractors & Owners User Guide BPCS

13. Click Submit Now button. The following dialog box is displayed.

Figure 9-60: Create Charges


14. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
15. The application is submitted and a message prompting you to pay the charges
is displayed.
16. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 121


Contractors & Owners User Guide BPCS

Figure 9-61: Submitted Application for permit before issue of completion certificate
17. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
18. Also, the final status of the application is changed from New to Submitted
19. You can also view the application submission message in the application
follow up screen.
20. This step marks the end of submitting an application to issue a décor permit
before completion certificate.

Dubai Municipality 122


Contractors & Owners User Guide BPCS

10 Acquiring Permission for Road Service and


Temporary Works
Contractors need approval from DM for all road service and temporary works.
Contractors can submit applications for booking walk sides, installing temporary tents,
requesting electricity cables and planting trees outside.
This section describes the application process to request the following:
• Walk side booking permit
• Install temporary tents
• Request electricity cables
• Road signboard permit
• Roof signboard permit
• Occupy Parcel
• Pavement Permit and
• Outside planting permit

Dubai Municipality 123


Contractors & Owners User Guide BPCS

10.1 Walk Side Booking Permit

This application is for the applicants (Only Contractor) to get the Permit to use the
wayside of the parcel. This permit will be for a temporary period and can be renewed.
To request a walk side booking permit:

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 10-1: Application for walk side booking


2. Select the Permissions for road services and temporary works option
from process group drop down box.
3. Select the Walk side booking permit option from the application type
drop down box.
4. You can either be applying for a new permit, or renewing an existing
permit. Select the New option from the submission type drop down box.
5. Enter a Description for the application.
6. Enter details such as the applicants Permit number, Area to be
occupied.

Dubai Municipality 124


Contractors & Owners User Guide BPCS

7. Select the source of permit issue from the Permit issue source drop down
box. You can choose from DEWA and RTA. Source of permit refers to
the department you are requesting the permit from.
8. Select the usage for the walk side booking from the occupational usage
drop down box. You can choose from Building material, Temporary
structures and Others. Occupational usage refers to the reason why you
are booking the walk side. If you choose others option, enter the reason in
the text box.
9. Enter the applicant mobile number in the Applicant Mobile Number
field.
10. Enter the applicant telephone number in the Applicant Telephone
Number field.
11. Enter the applicant email in the Applicant Email field and click the Save
application button.
12. The permit application screen is displayed. Scroll down and click the
Submit Application button. The following screen is displayed.

Figure 10-2: Application Summary


13. Click the Submit Now button. The following dialog box is displayed.

Dubai Municipality 125


Contractors & Owners User Guide BPCS

Figure 10-3: Create Charges


14. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
15. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 126


Contractors & Owners User Guide BPCS

Figure 10-4: Submitted application for walk side booking


16. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
17. Also, the final status of the application is changed from New to
Submitted.
18. You can also view the application submission message in the application
follow up screen.
19. This step marks the end of submitting an application for a walk side
booking permit.

Dubai Municipality 127


Contractors & Owners User Guide BPCS

10.2 Temporary Tents Permit

This application is for the applicants (Contractor or Owner) to get the Permit for putting
up temporary tent or structures on the plot or roadsides.
To request a temporary tent permit:

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 10-5: Application for Temporary Tents

Dubai Municipality 128


Contractors & Owners User Guide BPCS

2. Select the Permissions for road services and temporary works option
from process group drop down box.
3. Select the Temporary tent permit option from the application type drop
down box.
4. Enter a Description for the application.
5. You can either be applying for a new permit, or renewing an existing
permit. Select the New option from the submission type drop down box.
6. If you are renewing an existing permit, select the Renew option from the
drop down box. When you are requesting a renewal for the permit, you are
prompted to select the permit that requires renewal from the select permit
to renew drop down box.
7. Select the type of tent you are requesting a permit for from the from the
Tent Type drop down box. You can choose from Ramadan, Wedding,
Grievance, Commercial, DSF tents, and others option. If you choose
others option, enter the reason in the text box.
8. Enter From and To dates in the (date/month/year format) for the
temporary tent in the Validity Period fields. Alternatively, you can click
the calendar icon and select from and to dates for the temporary tents.
9. Enter the applicant mobile number in the Applicant Mobile Number
field.
10. Enter the applicant telephone number in the Applicant Telephone
Number field.
11. Enter the applicant email in the Applicant Email field and click the Save
Application button.
12. The permit application screen is displayed. Scroll down and click the
Submit Application button. The following screen is displayed.

Dubai Municipality 129


Contractors & Owners User Guide BPCS

Figure 10-6: Application Summary

13. Click the Submit Now button. The following dialog box is displayed.

Figure 10-7: Create Charges


14. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
15. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 130


Contractors & Owners User Guide BPCS

Figure 10-8: Submitted Application for Temporary tents


16. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
17. Also, the final status of the application is changed from New to
Submitted.
18. You can also view the application submission message in the application
follow up screen.
19. This step marks the end of submitting an application for temporary tents
permit.

Dubai Municipality 131


Contractors & Owners User Guide BPCS

10.3 Electricity Cable Permit

This application is for the applicants (Contractor/ Owner or other applicants) to get the
Permit for electricity cable to be used on the road or tents or some other functions.
To request an electric cable permit:

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 10-9: Application for Electricity Cable Permit

Dubai Municipality 132


Contractors & Owners User Guide BPCS

2. Select the Permissions for road services and temporary works option
from process group drop down box.
3. Select the Electricity Cable Permit option from the application type drop
down box.
4. Enter a Description for the application.
5. Enter From and To Dates in the date/month/year format for the temporary
tent in the Validity Period fields. Alternatively, you can click the calendar
icon and select from and to dates for the temporary tents.
6. Enter the applicant mobile number in the Applicant Mobile Number
field.
7. Enter the applicant telephone number in the Applicant Telephone
Number field.
8. Enter the applicant email in the Applicant Email field and click the Save
Application button.
9. The permit application screen is displayed. Scroll down and click the
Submit Application button. The following screen is displayed.

Figure 10-10: Application Summary


10. Click the Submit Now button. The following dialog box is displayed.
11. If you want to make some changes to the permit application, click cancel.
Else, click Ok.

Dubai Municipality 133


Contractors & Owners User Guide BPCS

12. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Figure 10-11: Submitted Application for electricity cable


13. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
14. Also, the final status of the application is changed from New to
Submitted.
15. You can also view the application submission message in the application
follow up screen. This step marks the end of submitting an application for
electric cable permit.

Dubai Municipality 134


Contractors & Owners User Guide BPCS

10.4 Road Signboard Permit

This application is for the applicants (Consultant/Contractor/owners) to get the Permit for
installing signboards at the roadside of the parcel.
To submit a request for road sign boards:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed

Figure 10-12: Application for road sign board

Dubai Municipality 135


Contractors & Owners User Guide BPCS

2. Select the Permission for Road Services and Temporary Works


application option from the process group drop down box.
3. Select the Permit for Road Signboards option from the application type drop
down box.
4. Enter a Description for the application.
5. Enter the applicant mobile number in the Applicant Mobile Number field.
6. Enter the applicant telephone number in the Applicant Telephone Number
field.
7. Enter the applicant email in the Applicant Email field and click the Save
Application button. The following screen is displayed.

Figure 10-13: Permit Application

Dubai Municipality 136


Contractors & Owners User Guide BPCS

8. Click the Click here to add signboards link against the Details field. The
following screen is displayed.

Figure 10-14: Road Signboard Details


9. Select the Street number from the building street number drop down box.
Alternatively, you can enter the street number in the adjacent text box.
10. Select the relevant option from the Types of signboards drop down box.
11. Enter details such as the Length, Depth, Height of the signboard against the
dimensions field.
12. If the signboard will be placed with the parcel or plot, select Yes. Else, select
No.
13. Enter details such as the Height, Electricity load and Description for the
signboard and click Add. The following screen is displayed.

Figure 10-15: Add Signboard details

Dubai Municipality 137


Contractors & Owners User Guide BPCS

14. To edit an entry, select the radio button against the meters you want to edit,
and click the edit link. Make the required changes and click the Done button.
15. To remove a signboard entry, select the radio button against the meters you
want to remove, select the check box under Delete and click the Delete link.
The signboard detail is removed from the list.
16. You will notice that the entered signboard details are displayed below. Click
the Done button. The permit application screen is displayed.
17. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 10-16: Application Summary


18. Click Submit Now button. The following dialog box is displayed.

Figure 10-17: Create Charges


19. If you want to make some changes to the permit application, click cancel.
Else, click Ok.

Dubai Municipality 138


Contractors & Owners User Guide BPCS

20. The application is submitted and a message prompting you to pay the charges
is displayed.
21. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Figure 10-18: Submitted application to request additional meters


22. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
23. Also, the final status of the application is changed from New to Submitted.
24. You can also view the application submission message in the application
follow up screen.
25. This step marks the end of submitting an application for road sign boards

Dubai Municipality 139


Contractors & Owners User Guide BPCS

10.5 Roof Signboard Permit

This application is for the applicants (Consultant/Contractor/owners) to get the Permit for
installing signboards at the roof of the building(s).
To submit a request for roof sign boards:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed

Figure 10-19: Application for road sign board

Dubai Municipality 140


Contractors & Owners User Guide BPCS

2. Select the Permissions for Road Services and Temporary Works option
from the process group drop down box.
3. Select the Permit for Roof Signboards option from the application type drop
down box.
4. Enter a Description for the application.
5. Enter the applicant mobile number in the Applicant Mobile Number field.
6. Enter the applicant telephone number in the Applicant Telephone Number
field.
7. Enter the applicant email in the Applicant Email field click the Save
Application button. The following screen is displayed.

Figure 10-20: Permit Application

Dubai Municipality 141


Contractors & Owners User Guide BPCS

8. Click the Click here to add signboards link against the Details field. The
following screen is displayed.

Figure 10-21: Roof Signboards Details


9. Enter the building name in the building Name field. To select a building, click
the Select link. The following screen is displayed.

Figure 10-22: Select Building for Signboard


10. Select the radio button against the building you want to add a sign board on
and click the Close button.
11. Select the relevant option from the types of signboards drop down box. You
can choose between Big Advertisement and Commercial.
12. Enter details such as the Length, Depth, Height of the signboard against the
dimensions field.
13. Enter details such as Front, Side1, and Side2 size of the signboard against the
Setback feet as show in figure 10-21.

Dubai Municipality 142


Contractors & Owners User Guide BPCS

14. Enter the Standard Height and the Electrical Load of the signboard in the
respective fields.
15. Enter a note or description in the Notes/Description field click Add. The
following screen is displayed.

Figure 10-23: Add Signboard details


16. To edit an entry, select the radio button against the meters you want to edit,
and click the edit link. Make the required changes and click the Done button.
17. To remove a signboard entry, select the radio button against the meters you
want to remove, select the check box under Delete and click the Delete link.
The signboard detail is removed from the list.
18. To view the signboard details after adding, click the bulb icon as show in the
figure10-23. The following screen is displayed.

Figure 10-24: Roof Signboard Details

Dubai Municipality 143


Contractors & Owners User Guide BPCS

19. Click the Close button to return to the Add/View Roof signboard details
screen.
20. You will notice that the entered signboard details are displayed below. Click
the Done button. The permit application screen is displayed.
21. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 10-25: Application Summary


22. Click Submit Now button. The following dialog box is displayed.

Figure 10-26: Create Charges


23. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
24. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 144


Contractors & Owners User Guide BPCS

Figure 10-27: Submitted application to request additional meters


25. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
26. Also, the final status of the application is changed from New to Submitted.
27. You can also view the application submission message in the application
follow up screen.
28. This step marks the end of submitting an application for roof sign boards

Dubai Municipality 145


Contractors & Owners User Guide BPCS

10.6 Occupy Parcel

This application is for the applicants (Only Contractor) to get the Permit to use the parcel
for some other owner. This permit will be for a temporary period and can be renewed.
To submit an application to occupy a parcel:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed

Figure 10-28: Permit Application

Dubai Municipality 146


Contractors & Owners User Guide BPCS

2. Select the Permissions for road services and temporary works option from
process group drop down box.
3. Select the Occupy Parcel Permit option from the application type drop down
box.
4. Enter a Description for the application.
5. Enter details such as the Applicants Permit number, and select the permit
issuer from the Permit Issued by drop down box. You can choose between
BPCS and RTA.
6. You can either be applying for a new permit, or renew or modify an existing
permit. Select the New option from the submission type drop down box
7. To view details of the parcel, click the View Details link adjacent to the
Occupied Parcel Id field.
8. Select the Occupational Usage from the occupational usage drop down box.
You can choose from Building Maintenance, Pavement and Others option.
9. If you have the owner’s approval for occupying the parcel select the Yes else
select No.
10. Enter the applicant mobile number in the Applicant Mobile Number field.
11. Enter the applicant telephone number in the Applicant Telephone Number
field.
12. Enter the applicant email in the Applicant Email field and click the Save
Application button.
13. The permit application screen is displayed. Scroll down and click the Submit
Application button. The following screen is displayed

Dubai Municipality 147


Contractors & Owners User Guide BPCS

Figure 10-29: Application Summary


14. Click the Submit Now button. The following screen is displayed.

Figure 10-30: Create Charges


15. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
16. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 148


Contractors & Owners User Guide BPCS

Figure 10-31: Submitted Application

17. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
18. Also, the final status of the application is changed from New to Submitted.
19. You can also view the application submission message in the application
follow up screen.
20. This step marks the end of submitting an application for occupying a parcel
permit.

Dubai Municipality 149


Contractors & Owners User Guide BPCS

10.7 Pavement Permit

This application is for the applicants (Consultant/ Contractor or Owner) to get the Permit
for paving the plot fully or partially.
To submit pavement permit:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed

Figure 10-32: Permit Application

Dubai Municipality 150


Contractors & Owners User Guide BPCS

2. Select the Permissions for road services and temporary works option from
process group drop down box.
3. Select the Pavement permit option from the application type drop down box.
4. Enter a Description for the application.
5. Select the paving type from the Paving Type drop down box. You can choose
between full paving and partial paving. Here, we have selected the Full
paving option.
6. Select the building type you want to pave from the building type drop down
box. You can choose from the six basic building types. Here, we have selected
the Industrial Building option.
7. Enter the applicant mobile number in the Applicant Mobile Number field.
8. Enter the applicant telephone number in the Applicant Telephone Number
field.
9. Enter the applicant email in the Applicant Email field and click the Save
Application button.
10. The permit application screen is displayed. Scroll down and click the Submit
Application button. The following screen is displayed

Figure 10-33: Application Summary


21. Click the Submit Now button. The following screen is displayed.

Dubai Municipality 151


Contractors & Owners User Guide BPCS

Figure 10-34: Create Charges


22. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
23. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 152


Contractors & Owners User Guide BPCS

Figure 10-35: Submitted Application


24. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
25. Also, the final status of the application is changed from New to Submitted.
26. You can also view the application submission message in the application
follow up screen.
27. This step marks the end of submitting an application for pavement permit.

Dubai Municipality 153


Contractors & Owners User Guide BPCS

10.8 Outside Planting Permission

This application is for the applicants (owner or other users) to get the NOC for increasing
the electrical power for the building.

10.8.1 Permission for Full Planting

To submit an application for full planting permission:


It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application screen
is displayed.

Figure 10-36: Application for full planting

Dubai Municipality 154


Contractors & Owners User Guide BPCS

2. Select the Permissions for road services and temporary works option from
process group drop down box.
3. Select the Outside planting permit option from the application type drop down
box.
4. Enter a Description for the application.
5. Select the Full planting option from the planting type drop down box.
6. Enter the applicant mobile number in the Applicant Mobile Number field.
7. Enter the applicant telephone number in the Applicant Telephone Number field.
8. Enter the applicant email in the Applicant Email field and click the Save
Application button. The following screen is displayed.

Figure 10-37: Permit Application


9. Click the Add Outdoor planting requests link. The following screen is
displayed.

Dubai Municipality 155


Contractors & Owners User Guide BPCS

Figure 10-38: Outdoor Planting Request


10. Enter the street number in the Street Number field.
11. Enter the width of the planting area in the Planting Width field.
12. Select the direction the street is facing form the Street Direction drop down box
and click Add. The following screen is displayed.

Figure 10-39: Add planting details


13. To edit an entry, select the radio button against the meters you want to edit, and
click the edit link. Make the required changes and click the Done button.
14. To remove a request,, select the radio button against the meters you want to
remove, select the check box under Delete and click the Delete link. The planting
detail is removed from the list of planting details.
15. You will notice that the entered street details are displayed below. Click the Close
button. The permit application screen is displayed.
16. Click the Submit Application button. The following screen is displayed.

Dubai Municipality 156


Contractors & Owners User Guide BPCS

Figure 10-40: Application Summary


17. Click the Submit Now button. The following dialog box is displayed.

Figure 10-41: Create Charges


18. If you want to make some changes to the permit application, click cancel. Else,
click Ok.
19. The application is submitted and a message prompting you to pay the charges is
displayed. For details refer to the section 13.1 Creating Charges in the appendix.
After paying charges return to the permit application page by clicking the Permit
Application link. The following screen is displayed.

Dubai Municipality 157


Contractors & Owners User Guide BPCS

Figure 10-42: Submitted Application for full planting


20. You will notice that a task has been generated for the DM official and a message
about your application submission is displayed.
21. Also, the final status of the application is changed from New to Submitted.
22. You can also view the application submission message in the application follow
up screen.
23. This step marks the end of submitting an application for outside planting permit.

Dubai Municipality 158


Contractors & Owners User Guide BPCS

10.8.2 Permission for Partial Planting

To submit an application for partial planting permission:


It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application screen
is displayed

Figure 10-43: Application for partial planting


2. Select the Permissions for road services and temporary works option from
process group drop down box.

Dubai Municipality 159


Contractors & Owners User Guide BPCS

3. Select the Outside planting permit option from the application type drop down
box.
4. Enter a Description for the application.
5. Select the Partial Planting option from the planting type drop down box.
6. Enter the applicant mobile number in the Applicant Mobile Number field.
7. Enter the applicant telephone number in the Applicant Telephone Number field.
8. Enter the applicant email in the Applicant Email field and click the Save
Application button. The following screen is displayed.

Figure 10-44: Permit Application


9. Click the Add Outdoor planting requests link. The following screen is
displayed.

Dubai Municipality 160


Contractors & Owners User Guide BPCS

Figure 10-45: Outside Planting Request


10. Enter the street number in the Street Number field.
11. Enter the width of the planting area in the Planting Width field.
12. Select the direction the street is facing form the street direction drop down box
and click Add. The following screen is displayed.

Figure 10-46: Add Planting details


13. To edit an entry, select the radio button against the meters you want to edit, and
click the edit link. Make the required changes and click the Done button.
14. To remove a request, select the radio button against the meters you want to
remove, select the check box under Delete and click the Delete link. The planting
detail is removed from the list of panting requests.
15. You will notice that the entered street details are displayed below. Click the Close
button. The permit application screen is displayed.
16. Click the Submit Application button. The following screen is displayed.

Dubai Municipality 161


Contractors & Owners User Guide BPCS

Figure 10-47: Application Summary


17. Click the Submit Now button. The following dialog box is displayed.

Figure 10-48: Create Charges


18. If you want to make some changes to the permit application, click cancel. Else,
click Ok.
19. The application is submitted and a message prompting you to pay the charges is
displayed. For details refer to the section 13.1 Creating Charges in the appendix.
After paying charges return to the permit application page by clicking the Permit
Application link. The following screen is displayed.

Dubai Municipality 162


Contractors & Owners User Guide BPCS

Figure 10-49: Submitted Application for partial planting


20. You will notice that a task has been generated for the DM official and a message
about your application submission is displayed.
21. Also, the final status of the application is changed from New to Submitted.
22. You can also view the application submission message in the application follow
up screen.
23. This step marks the end of submitting an application for a partial planting permit.

Dubai Municipality 163


Contractors & Owners User Guide BPCS

11 Availing Special Services & Exceptions


Contractors request for special approvals from the DM. The consultant however has to
give valid reasons for the exception request. Based on the contractors’ credentials, DM
approves or rejects the special request for the consultant.
This section describes the process to obtain permit for exceptions, new building style
verifications and special requests.

11.1 Requesting New Building Style Verification Permit


Contractors submit applications to verify the new building styles. DM reviews the
application and either accept or reject the same.
To submit a new building style verification request:

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a
new application (Generic)” process .Follow steps 1-3. The Permit
Application screen is displayed.

Figure 11-1: Application to verify new building style

Dubai Municipality 164


Contractors & Owners User Guide BPCS

2. Select the Special services and Exceptions option from process group
drop down box.
3. Select the New building style verification option from the application
type drop down box.
4. Enter a Description for the application.
5. Enter the name of the local company in the Local Company field.
6. Enter the name of the parent company in the Parent Company field.
7. Enter the site details in the Site Location field.
8. Enter the building system name details in the Building System Name
field.
9. Enter a description for the application in the Description field.
10. Enter the applicant mobile number in the Applicant Mobile Number
field.
11. Enter the applicant telephone number in the Applicant Telephone
Number field.
12. Enter the applicant email in the Applicant Email field and click the Save
Application button.
13. The permit application screen is displayed. Scroll down and click the
Submit Application button. The following screen is displayed.

Dubai Municipality 165


Contractors & Owners User Guide BPCS

Figure 11-2: Application Summary


14. Click the Submit Now button. The following dialog box is displayed.

Figure 11-3: Create Charges


15. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
16. The application is submitted and a message prompting you to pay the
charges is displayed.

After the application is approved by DM, a site visit is scheduled and the engineers from DM
either invite the contractor for a meeting or will visit the site to verify the building style.

17. The application is submitted and a message prompting you to pay the
charges is displayed. For details refer to the section 13.1 Creating Charges
in the appendix. After paying charges return to the permit application page
by clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 166


Contractors & Owners User Guide BPCS

.
Figure 11-4: Submitted application to verify new building style
18. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
19. Also, the final status of the application is changed from New to
Submitted.
20. You can also view the application submission message in the application
follow up screen.
21. This step marks the end of submitting an application for new building
verification.

Dubai Municipality 167


Contractors & Owners User Guide BPCS

11.2 Requesting Exceptions

To submit a request for exception:

It is mandatory to fill out the fields with an asterisk (*) against the field name

Step Action

1. Create a new application. For details, refer to the section 6.1 “Creating a new
application (Generic)” process .Follow steps 1-3. The Permit Application
screen is displayed.

Figure 11-5: Application to request for exceptions

Dubai Municipality 168


Contractors & Owners User Guide BPCS

2. Select Special Services and Exceptions from the process group drop down
box.
3. Select Request for exceptions option from the application type drop down
box.
4. Enter a Description for the application
5. Select the building type you want an exception for, from the Building type
drop down box.
6. Enter the applicant mobile number in the Applicant Mobile Number field.
7. Enter the applicant telephone number in the Applicant Telephone Number
field.
8. Enter the applicant email in the Applicant Email field and click the Save
Application button. The following screen is displayed.

Figure 11-6: Application Permit

Dubai Municipality 169


Contractors & Owners User Guide BPCS

9. Click the Click here to define exceptions button adjacent to exceptions field.
The following screen is displayed.

Figure 11-7: Exception Details


10. Select the type of exception from the Exception Type drop down box.
11. To view the fee calculation details for the selected exception type, click the
Click Here button. The following screen is displayed.

Dubai Municipality 170


Contractors & Owners User Guide BPCS

Figure 11-8: Calculate Fee Details

12. The screen displays the explanation for the selected exception and the
projections of the fee for the exception. To return to the Parcel Exception
screen, exit the excel sheet.
13. Select the Sub type of the exception from the exception sub type drop down
box.
14. Enter details such as the Exception you want, and Exception Description in
the respective fields.

Dubai Municipality 171


Contractors & Owners User Guide BPCS

15. Select the building you want to apply the exception to from the buildings
listed in related buildings. To select more than one building, press Ctrl key on
the key board and select the buildings.
16. Enter a Valid reason for the exception.
17. The expected cost per square feet cannot be edited as it is provided by the land
department.
18. Enter details such as the area added as a result of exception, parcel area and
the total allowed build up area on the parcel.
19. These details are used to calculate the fee DM charges to approve an
exception. Click Add. The following screen is displayed.

Figure 11-9: Parcel Exceptions


20. To edit an entry, select the radio button against the exception you want to edit,
and click the edit link. Make the required changes and click the Done button.
21. To remove a request, select the radio button against the exception you want to
remove, select the check box under Delete and click the Delete link. The
exception detail is removed from the list of exceptions.
22. You will notice that the entered street details are displayed below. Click the
Close button. The permit application screen is displayed.

Dubai Municipality 172


Contractors & Owners User Guide BPCS

23. Click the Submit Application button. The following screen is displayed.

Figure 11-10: Exception Fee


24. The total fee to pay for the exception is displayed. If you don’t want to accept
the fees click Cancel. Else click Ok. The following screen is displayed.

Figure 11-11: Application Summary


25. Click the Submit Now button. The following dialog box is displayed.

Dubai Municipality 173


Contractors & Owners User Guide BPCS

Figure 11-12: Create Charges


26. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
27. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 174


Contractors & Owners User Guide BPCS

Figure 11-13: Submitted application for exceptions


28. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
29. Also, the final status of the application is changed from New to Submitted.
30. You can also view the application submission message in the application
follow up screen.
31. This step marks the end of creating a permit application to request exceptions.

Dubai Municipality 175


Contractors & Owners User Guide BPCS

12 Other Applications

Besides the applications grouped under the various application process types, we have
three applications which are common to all and are grouped as others. The three
application types are: Request Statistical Info, to whom it may concern letter and
Unblocking Services.

12.1 Viewing Other Applications


To view other applications group:

Step Action

1. Click the Other Application tab on the homepage. The following screen is
displayed.

Figure 12-1: Other Applications


2. The screen is divided into two blocks. The upper block lists the links to create
different application types. The lower block lists all the existing applications
with details such as Permit Number, Application Type, Status, Permit Date
and application description.
3. The steps to apply for other applications are described in the following
sections.

Dubai Municipality 176


Contractors & Owners User Guide BPCS

12.2 Request Statistical Info

Consultants request for statistical information about their projects from DM. To request
for this information, the consultants submit a request to DM.
To request for statistical info:

Step Action

1. Click the Request for Statistical Info link on the Other Applications page as
shown in figure 12-1. The following screen is displayed.

Figure 12-2: Request Statistical Info


2. Enter a description for the type of information you are requesting in the
Application Description field.
3. Enter a valid reason for the request in the Reason field.
4. Enter the applicant’s mobile number and telephone number in the Applicant
Mobile No and Applicant Telephone No field.
5. Enter the applicants email id in the Applicant Email field.
6. Enter the applicants name in English and Arabic in the Applicant Name-
English and Applicant Name-Arabic field.

Dubai Municipality 177


Contractors & Owners User Guide BPCS

7. Enter the applicant’s company name in the Company Name field and click
the Save Application button.
8. The permit application screen is displayed. Scroll down and click the Submit
Application button. The following screen is displayed.

Figure 12-3: Application Summary


9. Click the Submit Now button. The following dialog box is displayed.

Figure 12-4: Create Charges


10. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
11. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed

Dubai Municipality 178


Contractors & Owners User Guide BPCS

Figure 12-5
12. You will notice that a message about your application submission is
displayed.
13. Also, the final status of the application is changed from New to Submitted.
14. You can also view the application submission message in the application
follow up screen.
15. This step marks the end of submitting an application for to request statistical
info.

Dubai Municipality 179


Contractors & Owners User Guide BPCS

12.3 To Whom It May Concern letter

Consultants can request letters from DM. However, DM will charge consultants a fee for
issuing such letters.
To request for a to whom it may concern letter:

It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Click the Request for To Whom It May Concern letter link on the Other
Applications page as shown in figure 12-1. The following screen is displayed.

Figure 12-6: Application for a to whom it may concern letter


2. Enter a Description for the application
3. You will notice that the name of the applicant appears automatically in both
English and Arabic.

Dubai Municipality 180


Contractors & Owners User Guide BPCS

4. Enter details such as the Company Name, Applicant mobile number,


Applicant telephone number and Email Id in the respective fields and click
the Save Application button. The permit application screen is displayed.
5. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 12-7: Application Summary


6. Click the Submit Now button. The following dialog box is displayed.

Figure 12-8: Create Charges


7. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
8. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 181


Contractors & Owners User Guide BPCS

Figure 12-9: Submitted application for a to whom it may concern letter


9. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
10. Also, the final status of the application is changed from New to Submitted.
11. You can also view the application submission message in the application
follow up screen.
12. This step marks the end of submitting an application for a to whom it may
concern letter.

Dubai Municipality 182


Contractors & Owners User Guide BPCS

12.4 Unblocking Services

DM blocks or restricts parcels, communities and even users on some sites. To remove the
restrictions, consultants have to submit an application to unblock the parcel.
To unblock the parcel:
It is mandatory to fill out the fields with an asterisk (*) against the field name.

Step Action

1. Click the Request for Unblocking link on the Other Applications page as
shown in figure 12-1. The following screen is displayed.

Figure 12-10: Application to Unblock Parcel


2. Enter a Description for the application.
3. Enter details such as mobile and telephone number of the applicant in the
Applicant mobile number and Telephone number field.
4. Enter the email id of the applicant in the Email Id field and click the Save
Application button. The permit application screen is displayed.

Dubai Municipality 183


Contractors & Owners User Guide BPCS

5. Scroll down and click the Submit Application button. The following screen
is displayed.

Figure 12-11: Application Summary


6. Click the Submit Now button. The following dialog box is displayed.

Figure 12-12: Create Charges


7. If you want to make some changes to the permit application, click cancel.
Else, click Ok.
8. The application is submitted and a message prompting you to pay the charges
is displayed. For details refer to the section 13.1 Creating Charges in the
appendix. After paying charges return to the permit application page by
clicking the Permit Application link. The following screen is displayed.

Dubai Municipality 184


Contractors & Owners User Guide BPCS

Figure 12-13: Submitted Application for Unblocking


9. You will notice that a task has been generated for the DM official and a
message about your application submission is displayed.
10. Also, the final status of the application is changed from New to Submitted.
11. You can also view the application submission message in the application
follow up screen.
12. This step marks the end of submitting an application for unblocking a parcel.

Dubai Municipality 185


Contractors & Owners User Guide BPCS

13 Appendix

Some actions are common to all application types. For instance, to create charges after
submitting an application. This section describes the following common actions:
• Creating Charges after submitting an application
• Viewing modification details
• Creating versions of a returned application
• Resubmitting a CFR application
• Responding to Engineer Notes
• Printing Screens from the application
:

Dubai Municipality 186


Contractors & Owners User Guide BPCS

13.1 Creating Charges

DM generates charges to for all the applications submitted by the consultant. The charges
vary based on the application type. After the consultant has submitted the application (it
could be an application for any process), the charges screen is displayed.
To pay charges:

Step Action

1. After the application is submitted (irrespective of the categories), the


following screen is displayed.

Figure 13-1: Application Charges


2. The screen displays the details of the charges DM has generated for the
submitted application type.
3. It gives details such as the type of charge, the total payment, the payee
name, the application version, the application and building type.
4. To view the invoice details, click the link listed under the Voucher Number
column. The following screen is displayed.

Dubai Municipality 187


Contractors & Owners User Guide BPCS

Figure 13-2: Invoice


5. The screen displays the actual break of the charges with the applicant’s
details. KDF here refers to Knowledge Dirham Fee, which is charged by DM
for all application that is submitted. However, the charges vary depending on
the type of application that’s submitted.
6. Click the Close button. The application charges screen is displayed. Click the
click here to view and pay online link on the application charges screen as
shown in figure 14-1. The following screen is displayed.

Figure 13-3: E-Payment

Dubai Municipality 188


Contractors & Owners User Guide BPCS

7. To proceed with the payment, click the Pay Online button. And follow the
instructions that appear on the screen.
8. Sometime, you might receive an error instead of viewing the application
charges. The error is displayed below.

Figure 13-4: Error


9. When you see this error, make sure you make the payments by coming in
person to DM.

Dubai Municipality 189


Contractors & Owners User Guide BPCS

13.2 Viewing Modification Options

You can view modifications on buildings and the floor and other information. This
operation is common for all applications that have been modified and includes simple
decor, normal decor and all adjustment addition applications.
To view the modification options for the selected application type:

Step Action

1. Select the modified application, click the Building Card link. The following
building card details screen is displayed.

Figure 13-5: View Building Modifications


2. To view modifications on a building, select the building by clicking the radio
button against the same and select the View Building Modification option
from the select operation drop down box. Click the Go button. The following
screen is displayed.

Figure 13-6: View Building Modifications

Dubai Municipality 190


Contractors & Owners User Guide BPCS

3. To view the modifications, click the View Modification link as shown in


figure 13-6. The following screen is displayed.

Figure 13-7: Modification Details


4. This screen displays the floor variations and other modifications on the
selected building. To modify details, make the changes and click the Save
Modification button.
5. Click Close to return to the building card details screen.
6. To view building details, select the building by clicking the radio button
against the same and select the View Building Details option from the select
operation drop down box. Click the Go button. The following screen is
displayed.

Dubai Municipality 191


Contractors & Owners User Guide BPCS

Figure 13-8: Building Details


7. To view floor details, select the building by clicking the radio button against
the same and select the View Floor Details option from the select operation
drop down box. Click the Go button. The following screen is displayed.

Figure 13-9: View Floor Details

Dubai Municipality 192


Contractors & Owners User Guide BPCS

8. Click the Close button to return to the building card details screen.
9. To fix building details, select the building by clicking the radio button against
the same and select the Fix Building Details option from the select operation
drop down box. Click the Go button. The following screen is displayed.

Figure 13-10: Fix Building Details


10. To modify details, make the changes and click the Save Modification button.
11. Click the Close button to return to the building card details screen.
12. To fix floor and usage details, select the building by clicking the radio button
against the same and select the Fix Floor & Usage Details option from the
select operation drop down box. Click the Go button. The following screen is
displayed.

Dubai Municipality 193


Contractors & Owners User Guide BPCS

Figure 13-11: Fix Usages & Sub Usages


13. To modify details, make the changes and click the Save Modification button.
14. Click the Close button to return to the building card details screen.
15. To fix building summary details, select the building by clicking the radio
button against the same and select the Fix Building Summary option from
the select operation drop down box. Click the Go button. The following
screen is displayed.

Dubai Municipality 194


Contractors & Owners User Guide BPCS

Figure 13-12: Fix Building Summary


16. To modify details, make the changes and click the Save Modification button.
To add floors, click the + button and to remove floors, click the – button.
17. Click the Close button to return to the building card details screen.

Dubai Municipality 195


Contractors & Owners User Guide BPCS

13.3 Creating Versions of a Returned Application

Building dept engineers who review the application submitted by consultants and owners
can return the applications if they don’t conform to the dm standards. They also leave a
reason for returning the same. This section describes the steps to resubmit a returned
application by creating a new version of the application.
To view a returned application and resubmit the same:

Step Action

1. Locate the project which has the returned application and click the view
application link. For details refer to section 5.2 View Project Details. The
following screen is displayed.

Figure 13-13: List of Application


2. This screen lists all the application in the selected project. Locate the project
with the status Returned and click the version number. The following screen
is displayed.

Dubai Municipality 196


Contractors & Owners User Guide BPCS

Figure 13-14: Application Versions


3. Click the New Version button. The following screen is displayed.

Figure 13-15: Confirm New Version Creation


4. To create a new version of the application click Ok. Else click Cancel. The
following screen with the confirmation message is displayed.

Figure 13-16: New Version Created


5. Click the Go To New Version Application link. The following screen is
displayed.

Dubai Municipality 197


Contractors & Owners User Guide BPCS

Figure 13-17: New Version Permit Application


6. This permit application screen is the new version of the returned application.
7. To view the engineer comments or noted of the previous version, click the
Previous Version Notes link. The following screen displaying the engineer
notes is displayed.

Dubai Municipality 198


Contractors & Owners User Guide BPCS

Figure 13-18: Previous Version Notes


8. Make sure you adhere to the notes and take care of the comments.
9. To respond to the engineers message, enter the response in the reply message
text box and click Save.
10. Return to the permit application screen, complete the application and submit
the application.
11. A message stating the submission of the application is displayed.
12. This step marks the end of creating a new version of a returned application.

Dubai Municipality 199


Contractors & Owners User Guide BPCS

13.4 Re submitting a CFR Application

If you have received a CFR from DM after submitting the application, you are required to
make the changes given in the notes that are in the application and resubmit the
application.
To resubmit a CFR application:

Step Action

1. Locate the project which has the returned application and click the view
application link. For details refer to section 5.2 View Project Details. The
following screen is displayed.

Figure 13-19: CFR Application


2. Click the View link against the CFR application. The following screen is
displayed.

Dubai Municipality 200


Contractors & Owners User Guide BPCS

Figure 13-20: Permit Application


3. Make the changes suggested by the engineers and save the application.
4. You can also leave a note for the engineer to indicate that the changes have
been made.
5. To create a comment, click the Create Comment link. The following screen
is displayed.

Dubai Municipality 201


Contractors & Owners User Guide BPCS

Figure 13-21: Comments


6. Enter the comments and click the Save button. The permit application screen
is displayed.

Figure 13-22: CFR Completed

7. To resubmit the application, select the CFR completed checkbox. When the
CFR completed checkbox is selected, the Resubmit button is enabled.
8. Click the Resubmit button. The application is resubmitted to DM and a task is
generated for the counter clerk.

Dubai Municipality 202


Contractors & Owners User Guide BPCS

Figure 13-23: Submitted CFR application


9. You will notice that the status of the application has been changed from CFR
to CFR Completed.
10. This step marks the end of re submitting a CFR application.

Dubai Municipality 203


Contractors & Owners User Guide BPCS

13.5 Responding to Engineer Notes

Engineers return applications with notes and comments. Contractors/Consultants make


changes to the application based on the comments and resubmit the same. The contractors
can also leave notes to engineers or respond to engineers.
To respond to engineer notes:

Step Action

1. Locate the project with the returned application or an application with notes.
Open the application. The following screen is displayed.

Figure 13-24: Permit Application with Notes

Dubai Municipality 204


Contractors & Owners User Guide BPCS

2. Click the View All Notes link in the Follow up DM Engineers pane as show
in figure 13-25. The following screen is displayed.

Figure 13-25: Engineer Notes


3. The screen displays the notes given by the engineer or the DM employee who
is processing the application.
4. To respond to the engineers notes, select the subject from the drop down box
in the Notes Reply column.
5. Enter the message or comment in the text box in the Reply Message column.
6. Click the Save button.
7. The note is saved and is visible to employee who is processing your
application.
8. This step marks the end of responding to engineer notes process.

Dubai Municipality 205


Contractors & Owners User Guide BPCS

13.6 Printing Screens from BPCS

You can print the applications or different windows from the BPCS system.
You can print any screen from BPCS.

Step Action

1. To print the task/messages, list of applications in the project or any screen, go


the required screen. This example displays printing a list of applications. The
Permit application screen, with the applications in the project is displayed.

Figure 13-26: Application List


2. Click the Print button displayed on the left menu. The following screen is
displayed.

Dubai Municipality 206


Contractors & Owners User Guide BPCS

Figure 13-27: Print Setup


3. Select the printer you want to print on and click the Print button.
4. This step marks the end of printing screens from BPCS.

Dubai Municipality 207

You might also like