You are on page 1of 2

EQUIP K1 K2 K3 B1 B2 FP FM FBM CPO

RD 3.4974 0.4485 0.1074 2.25 1.82 4.182 3.11 25.921 32523.2


T-101 3.4974 0.4485 0.1074 2.25 1.82 1.3425 1 4.693 16882.47
T-102 3.4974 0.4485 0.1074 2.25 1.82 1.055 3.11 8.222 73994.26
Tray RD 2.9949 0.4465 0.3961 - - - - 1.8 1136.788

TrayT-101 2.9949 0.4465 0.3961 - - - - 1 942.0056

TrayT-102 2.9949 0.4465 0.3961 - - - - 1.83 2808.51

RD

Specification
Pressure bar 30 C 0P (2015)
Volume m3 42.46 47023.458
Trays m2 1.327 1643.618
Material Stainless Steel -
Tray 50 tray fq =1

CBM (2015) for RD = FBM * Cp˚ (2015) = 25.921*47023.458 = $ 1218895

CBM (2015) for RD trays = FBM *N*fq Cp˚ (2015) = 1.8**50*1*1643.618 = $147925

T-101

Specification
Pressure bar 3 C 0P (2015)
Volume m3 17.78 24409.415
Trays m2 0.89 1361.99
Material carbon Steel -
Tray 39 tray fq =1

CBM (2015) for RD = FBM * Cp˚ (2015) = 4.693*24409.415 = $ 114553

CBM (2015) for RD trays = FBM *N*fq Cp˚ (2015) = 1*39*1*1361.99 = $53117
T-101

Specification
Pressure bar 2.5 C 0P (2015)
Volume m3 112.5 106984
Trays m2 4.424 4060
Material carbon Steel -
Tray 50 tray fq =1

CBM (2015) for RD = FBM * Cp˚ (2015) = 8.222*106984 = $ 879623

CBM (2015) for RD trays = FBM *N*fq Cp˚ (2015) = 1.83*50*1*4060 = $371490

Total Equipment cost=Σ All CBM (2015) for all equipment = $ 2785603