Professional Documents
Culture Documents
Q4. Solve problem 23, page 233 of Mantel (be sure to read the entire problem). Note that your
choice is only between activities d and c.
a. Minimum slack:
b. Most followers:
c. Most critical followers:
d. Shortest task first:
e. As late as possible:
SOLUTION:
According to the Question,
We know that:
CV = EV – AC
SV = EV – PV
CPI = EV / AC
SPI = EV / PV
Q6. Answer the following questions concerning the Palmstar Enterprises, Inc Case Study on
page 270 of Mantel.
a. What has the largest impact on Palmstar’s profits, delaying the 2000’s
introduction by 3 months or increasing the project’s budget by 30 percent?
Assume that the end of the product life will occur three years after the scheduled
deployment, regardless of whether the deployment is delayed or not.
b. Are there other factors you would consider in addition to profit?
c. What should Palmstar do? Why?
d. How generalizable do you think the results of your analysis in this particular case
are to other situations?
Q7. You are preparing a project to lay fiber optic cable. The first task is to mobilize the team.
You estimate this will take one week and cost $3000. The second task is to lay the cable. This
will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last
task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At
the end of the first week, you have completed mobilization, but it cost a total of $4500. At the
end of the third week, you have completed five miles of cable at a total cost of $28,000
(installation only). It takes you a total of 10 weeks to complete the entire project, for a total cost
of $65,000.
e. At the end of week 1:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?
f. At the end of week 3:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?
g. At the end of the project:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?
Suggestion: You may want to go back to Answer 2 of IA-3 and use the excel setup in that file
adjusted, of course, for this network.
SOLUTION:
Step 1: Draw the diagram:
1
D
A B 3
F
1 2 5 6
C 4
E
The critical path is 1-A 2-C 4-E 5-F 6. It’s the path with the longest time.
To make it easier to see which activities are in each path, got to cell A20 and type
=IF(A15=1,A$2,"")
In cell G17 type "MAX"
In cell H17, type =MAX(H15:H16)
This shows how long the slowest path takes.
In cell H20 type =IF(H15=H$17,"CRITICAL","")
Copy cell to H20:H21
The critical path will be labeled as “CRITICAL”
Click on OK in the Solver Options dialog box. And Solve in the Solver Parameters dialog box.
To get finished in 17 weeks(H17 now has 17). We need to spend $1350 (G14 now has 1350)