You are on page 1of 37

Supplement H  Measuring Output Rates

Supplement

H Measuring Output Rates

TRUE/FALSE

1. A work standard is the time required for a trained worker to perform a task following a prescribed
method with normal effort and skill.
Answer: True
Reference: Introduction
Difficulty: Easy
Keywords: work, standard

2. Work measurement is the process of creating labor standards based on the judgment of skilled
observers.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Easy
Keywords: work, measurement, labor, standard

3. A time study is the method most often used for setting time standards for a job.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: study, time, standards

4. The select time is the average observed time based only on representative times.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: select, time

5. The snap-back method of time study resets the stopwatch to zero on the completion of each work
element.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: snap-back, method, time, study

109
Supplement H  Measuring Output Rates

6. The standard time for a work element is found by multiplying the select time by a performance-rating
factor.
Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time, work, element

7. The performance-rating factor in a time study is a totally objective measure.


Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: performance, rating, factor

8. Fatigue, rest, or unavoidable delays are factored into a work standard by the performance-rating
factor.
Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: allowance, time

9. The normal time adjusts the select time by the regularity of occurrence and a performance rating
factor.
Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: allowance, time, normal, frequency

10. Time studies are appropriate for setting time standards for tasks that are different each time.
Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study, standards

11. Elemental standard time data can help managers develop time standards for new work before
production begins.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: elemental, standard, time

12. The methods time measurement system is a predetermined data system.


Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: MTM, methods, time, measurement

110
Supplement H  Measuring Output Rates

13. The predetermined data approach eliminates the need for time studies.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: predetermined, data, approach, time, studies

14. A predetermined data approach to time standards can be completed before actual production begins.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: methods, time, measurement, predetermined

15. The methods time measurement approach assumes that a sequence of motions will take the same
amount of time regardless of the order in which they are performed.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: methods, time, measurement

16. Work sampling can be used to estimate the proportion of time spent by people or machines on
activities.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling, proportion

17. When using work sampling, the times of day when the analyst collects the sample data should be
selected at random over the length of the study.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling, data

18. The more frequently the activity occurs, the longer the time period should be when conducting a work
sampling study.
Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling, frequency

19. Special training is required for observers using work sampling.


Answer: False
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling

111
Supplement H  Measuring Output Rates

20. As the sample size increases in a work sampling study, the maximum error decreases.
Answer: True
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size, maximum, error

21. Traditional work measurement techniques often are viewed as repressive.


Answer: True
Reference: Managerial Considerations in Work Measurement
Difficulty: Moderate
Keywords: work, measurement

MULTIPLE CHOICE

22. Which of these drawbacks would be considered a hidden cost of work standards?
a. Assigning tasks to workers and machines to utilize resources.
b. Increased conflict between labor and management.
c. Ability to compare alternative process designs.
d. Determination of current and projected capacity requirements.
Answer: b
Reference: Work Standards
Difficulty: Easy
Keywords: work, standards, cost

23. Work standards would NOT be helpful for management in which area?
a. Developing costs for current and new products.
b. Determining current and projected capacity requirements for a given demand.
c. Comparing different routings for an item and evaluating new work methods and equipment.
d. Forecasting demand for current products.
Answer: d
Reference: Work Standards
Difficulty: Moderate
Keywords: work, standards

24. When a work analyst needs a high degree of precision in comparing actual work method results to 
standard, the best method to use would be:
a. a stopwatch study.
b. work sampling.
c. the elemental standard data approach.
d. the historical data approach.
Answer: a

112
Supplement H  Measuring Output Rates

Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: stopwatch, study

113
Supplement H  Measuring Output Rates

25. The method used most often for setting time standards for a job is:
a. the elemental standard data approach.
b. the time study method.
c. the predetermined data approach.
d. the work sampling method.
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: stopwatch, study

26. Timing the work elements using the snap­back method requires:
a. the worker to perform each job element as quickly as possible.
b. a larger sample size than using the continuous method.
c. the use of two stopwatches.
d. a smaller sample size than using the continuous method.
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: stopwatch, study, snap­back

27. The continuous method of timing work elements:
a. is more accurate than the snap­back method.
b. is best combined with the work sampling method.
c. will always result in increasing recorded times for successive work elements.
d. requires a greater sample size than the snap­back method.
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: stopwatch, study, continuous

28. Garman observes a worker assembling peanut valves and records the data displayed in the 
table. What is the select time for this job element if the worker is rated at 80%?
Time (seconds) Observations
20 15
25 12
30 12
a. 15 seconds
b. 20 seconds
c. 25 seconds
d. 30 seconds
114
Supplement H  Measuring Output Rates

Answer: c
Reference: Methods of Work Measurement
Difficulty: Easy
Keywords: stopwatch, study, select, time

115
Supplement H  Measuring Output Rates

29. Garman observes a worker assembling peanut valves and records the data displayed in the table. 
During one of the cycles, the worker knocked the shaft out of the fixture and had to realign the 
fixtures. What is the select time for this job element if the worker is rated at 80%?
Time (seconds) Observations
20 15
25 12
30 12
240 1
a. Less than 23 seconds
b. Greater than or equal to 23 seconds but less than 26 seconds
c. Greater than or equal to 26 seconds but less than 29 seconds
d. Greater than or equal to 29 seconds
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: stopwatch, study, select, time

30. Keith assembles peanut valves and the recorded data is displayed in the table. What is the select time 
for this job element if he is rated at 75%?
Time (minutes) Observations
2.5 15
3.0 23
3.5 27
a. Greater than or equal to 3 minutes
b. Less than 3 minutes but greater than or equal to 2.7 minutes
c. Less than 2.7 minutes but greater than or equal to 2.4 minutes
d. Less than 2.4 minutes
Answer: a
Reference: Methods of Work Measurement
Difficulty: Easy
Keywords: stopwatch, study, select, time

116
Supplement H  Measuring Output Rates

31. Keith assembles peanut valves and the recorded data is displayed in the table. During one of the 
cycles, he pauses to answer a phone call from his friend who suggests that he seek employment 
elsewhere. Keith fields calls with some regularity, but that’s not considered part of his routine job 
responsibilities. What is the select time for this job element if Keith is rated at 75 %?
Time (minutes) Observations
2.5 15
3.0 23
3.5 25
10 1
a. Greater than or equal to 3.2 minutes
b. Less than 3.2 minutes but greater than or equal to 2.8 minutes
c. Less than 2.8 minutes but greater than or equal to 2.4 minutes
d. Less than 2.4 minutes
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: stopwatch, study, select, time

32. Which one of the following statements about work­measurement methods is TRUE? 
a. The two methods of using a stopwatch in time studies are historical and snap­back. 
b. The time­study method is usually used for less­repetitive work with no definite work cycle. 
c. With the time­study method, the analyst assigns a performance rating factor (RF) to the work’s 
performance. A value of RF greater than 1 means the worker is slower than a standard worker. 
d. The work­sampling method needs many observations. 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: measurement, methods, sampling

33. Which one of the following statements about the time­study method is TRUE? 
a. It is most appropriate for “thinking” jobs such as an automobile mechanic’s diagnosis of a problem.
b. It is used most often for setting time standards. 
c. Using the time­study method technique, time standards can be set for new jobs before production 
begins. 
d. Performance ratings are not needed in the derivation of time standards. 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study, standards

117
Supplement H  Measuring Output Rates

34. Which one of the following statements about work measurement is TRUE? 
a. Work sampling is a technique to determine the proportion of time spent on different activities. 
b. In determining the normal time for the cycle, using a rating factor less than one (1.0) will increase 
the total time allowed for a job to be performed, relative to the select time. 
c. Machine standards are more difficult to develop than labor standards. 
d. The time­study method is most appropriate for non­repetitive jobs in which the nature of the task 
differs each time. 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, measurement, sampling

35. A time­study analyst is attempting to determine the standard time for a work element. She or he 
observes a worker performing the work element at a higher­than­average pace. How will this fact be 
reflected in the time standard that is eventually created? 
a. The frequency of the work element per cycle will be increased. 
b. The proportion of allowance time will be increased above 1.0. 
c. The performance rating factor will be set greater than 1.0. 
d. The normal time for the work element will be increased. 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: performance, rating

36. A manager is interested in setting a time standard for a machining operation. Which one of the 
following is LEAST likely to be of use? 
a. Time­study method
b. Elemental standard data approach 
c. Predetermined data approach
d. Work sampling method 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling

37. With a time­study approach, the:
a. nature of the task can be different with each replication, and the standards will still be good. 
b. skill of the observer is not very important. 
c. sample size is a function of the desired precision of the time estimate. 
d. sample size is typically larger than required for the work sampling approach. 
118
Supplement H  Measuring Output Rates

Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study, sample, size, precision

119
Supplement H  Measuring Output Rates

38. When using a time­study approach, the standard time is: 
a. the normal time per cycle multiplied by 1.0 plus the allowance. 
b. the select time multiplied by the rating factor, summed over all work elements. 
c. the select time plus z times the standard deviation. 
d. the normal time plus z times the standard deviation. 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study, standard

39. An analyst using a time­study approach: 
a. observes the worker at random times, categorizing what he or she is doing at that time. 
b. must rate the performance of the worker on each element of the total task. 
c. divides the total task into micro­motions such as “reach” and “grasp” and then times the worker on 
each one. 
d. should use all observations in determining the standard, regardless of how irregular they might be, 
to be fair to the worker. 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study, performance, rating

40. An advantage of the elemental standard data approach is that there is: 
a. a reduction in the number of time studies needed. 
b. no need to estimate allowances. 
c. no need to use time­study methods. 
d. no need to estimate the variable characteristics of jobs. 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: elemental, standard, data

41. With the use of the elemental standard data approach: 
a. there is no need to estimate allowances. 
b. managers can develop standards for new work before production begins. 
c. time studies are not needed. 
d. the need to specify job variables that affect times for each work element is eliminated. 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
120
Supplement H  Measuring Output Rates

Keywords: elemental, standard, data

121
Supplement H  Measuring Output Rates

42. The advantage of using the predetermined­data approach for setting standards is that: 
a. it allows the setting of standards for a new job before production begins. 
b. the predetermined data are representative of all workers, without question. 
c. it does not require any special training to use it. 
d. it can be used on jobs in which the times to perform the micro­motions are sequence dependent. 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: predetermined, data, standards

43. Which of the following is not an advantage of the predetermined­data approach to work 
measurement? 
a. Standards can be set before production begins. 
b. New work methods can be compared without conducting a time study. 
c. Performance ratings are not needed to derive standards. 
d. The approach is particularly applicable to firms with a flexible flow strategy. 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: predetermined, data

44. Which work­measurement technique breaks down tasks into a series of generic micro­motions? 
a. Time­study method
b. Elemental standard data approach 
c. Predetermined­data approach
d. Work­sampling method 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: micro­motion, work, measurement

45. With the use of the methods time measurement approach: 
a. stopwatches are needed to time the elements that go together to make a task. 
b. there is a problem of biased judgment because performance ratings are needed to derive standards. 
c. work must be broken down into micro­motions. 
d. an analyst consults tables that contain the select times for a variety of work elements. 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: methods, time, management, micro­motions
122
Supplement H  Measuring Output Rates

46. Which of the following is TRUE regarding the MTM approach?
a. A performance rating factor greater than 1.0 means the worker under observation is working 
slowly.
b. A frequency of less than 1.0 means that the job element is not performed during every cycle.
c. A performance rating factor less than 1.0 means the worker under observation is not producing 
output that has high quality.
d. A negative allowance time means that the worker under observation is taking excessive breaks.
Answer: b
Reference: Methods of Work Measurement
Difficulty: Easy
Keywords: methods, time, measurement, MTM, frequency

47. When using the MTM approach: 
a. stopwatches are needed to time the elements that go together to make a task. 
b. there is a problem of biased judgment because performance ratings are needed to derive standards. 
c. an analyst consults tables that contain the select times for a variety of work elements. 
d. new work methods can be compared without conducting a time study. 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: methods, time, measurement, MTM

48. When using a work­sampling study: 
a. the underlying assumption is that the proportion of time during which the activity is observed in the
sample will be the proportion of time spent on the activity in general. 
b. the underlying assumption is that small samples of an activity can provide accurate measures of 
time spent on the activity. 
c. an advantage is that the study can normally be concluded in a day or less. 
d. the analyst must be highly trained in statistical observation. 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling, proportion

49. Work sampling is most often used in situations in which: 
a. a time standard is needed for a repetitive job. 
b. an estimate of the proportion of the time spent on a particular activity is needed. 
c. it is important to keep the sample size down. 
d. special training is required for the observer, and stopwatches must be used. 
Answer: b
123
Supplement H  Measuring Output Rates

Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling

124
Supplement H  Measuring Output Rates

50. Work sampling is one method of work measurement. A major disadvantage of this method is that: 
a. observers must be specially trained. 
b. only one study can be conducted at a time. 
c. it can be used only in hospital settings. 
d. a large number of observations are often required. 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling

51. During a time study, the following times were observed for a particular job using the continuous 
(non­snapback) method: 22, 51, 72, 98, 128, and 150 seconds. There is only one element per cycle. 
The sample standard deviation of the observed times has already been computed as 3.9 seconds. If an 
estimate for the average time that is within 4 percent of the true long­range average 95 percent of the 
time is desired, how many additional observations are needed? 
a. Fewer than or equal to 40 
b. Greater than 40 but fewer than or equal to 55 
c. Greater than 55 but fewer than or equal to 70 
d. Greater than 70 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size, stopwatch

52. An industrial engineer is conducting a time study for a work element. The select time is 7.5 minutes, 
and the sample standard deviation of the observed time is one minute. What is the appropriate sample 
size if the estimate is to be 3 percent of the true average time 95 percent of the time? 
a. Fewer than or equal to 70
b. Greater than 70 but fewer than or equal to 80 
c. Greater than 80 but fewer than or equal to 90 
d. Greater than 90
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size, time study

53. An industrial engineer is conducting a time study for a work element. The select time is 4.5 minutes, 
and the sample standard deviation of the observed time is 20 seconds. What is the appropriate sample 
size if the estimate is to be 5 percent of the true average time 95 percent of the time? 
a. Fewer than or equal to seven
125
Supplement H  Measuring Output Rates

b. Greater than seven but fewer than or equal to eight
c. Greater than eight but fewer than or equal to nine 
d. Greater than nine
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size, time study

126
Supplement H  Measuring Output Rates

54. A worker was observed for four cycles of a repetitive task. The observer used the continuous method 
for recording the times. The continuous times (in seconds) for each element are:

Which one of the following are the “select times” ( t ) for each element? The first number is the 
select time for the first element, the second number is the select time for the second element, and 
so on. 
a. 19.5, 23, 25, 30
b. 1.5, 3.5, 5, 2
c. 2, 3, 2, 5
d. 1.5, 3.5, 2, 5 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: select, time

55. A time­study analyst is determining the standard time for a work element. The select time is 6.0 
minutes, and the standard deviation of the select time is 2.2 minutes, based on a pilot sample of 20 
observations. What is the appropriate sample size if the estimate for the select time is to be within 10 
percent of the true average time 95 percent of the time? 
a. Fewer than 30 observations 
b. Greater than or equal to 30 observations but fewer than 40 observations 
c. Greater than or equal to 40 observations but fewer than or equal to 50 observations 
d. Greater than or equal to 50 observations 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size

127
Supplement H  Measuring Output Rates

Table H.1
A worker was observed for four cycles in a repetitive task that contains four distinct elements. 
The observer recorded the following items in seconds, using the continuous method.

Element Cycle 1 Cycle 2 Cycle 3 Cycle 4


1 12 66 111 168
2 21 75 122 185
3 37 86 133 200
4 53 89 146 209

56. Use the information in Table H.1. What is the select time for work element 3? 
a. Fewer than 12 seconds 
b. Greater than or equal to 12 seconds but fewer than 13 seconds 
c. Greater than or equal to 13 seconds but fewer than or equal to 14 seconds 
d. Greater than or equal to 14 seconds 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: select, time, element

57. Use the information in Table H.1. Assuming that work element 4 receives a performance­rating factor
of 1.2 and is performed once per cycle, what is the normal time for this work element? 
a. Fewer than 10 seconds 
b. Greater than or equal to 10 seconds but fewer than 11 seconds 
c. Greater than or equal to 11 seconds but fewer than 12 seconds 
d. Greater than or equal to 12 seconds 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: normal, time, rating

58. Use the information in Table H.1. Work element 1 receives a performance­rating factor of 1.4 and is 
performed every other cycle. If the company uses an allowance time of 15 percent, what is the 
standard time for this work element?
a. Fewer than 12 seconds 
b. Greater than or equal to 12 seconds but fewer than 13 seconds 
c. Greater than or equal to 13 seconds but fewer than 14 seconds 
d. Greater than or equal to 14 seconds 
128
Supplement H  Measuring Output Rates

Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time, allowance

129
Supplement H  Measuring Output Rates

59. Use the information in Table H.1. What is the select time for work element 2? 
a. Fewer than 12 seconds 
b. Greater than or equal to 12 seconds but fewer than 13 seconds 
c. Greater than or equal to 13 seconds but fewer than or equal to 14 seconds 
d. Greater than or equal to 14 seconds 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: select, time, element

60. Use the information in Table H.1. Assume that work element 1 receives a performance­rating factor 
of 1.1 and all other elements receive a rating of 1.2. If work elements 1 and 3 are performed every 
other cycle, and elements 2 and 4 are performed every cycle, what is the normal time for the complete
cycle? 
a. Fewer than 45 seconds 
b. Greater than or equal to 45 seconds but fewer than 48 seconds 
c. Greater than or equal to 48 seconds but fewer than 51 seconds 
d. Greater than or equal to 51 seconds 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Hard
Keywords: normal, time, rating, cycle

61. Use the information in Table H.1. Assume that work element 1 receives a performance rating factor 
of 1.2 and all other elements receive a rating of 1.1. If work element 2 is performed every other cycle 
but every other element is performed every cycle, and the company has an allowance time of 0.10, 
what is the standard time for the complete cycle?
a. Fewer than 45 seconds 
b. Greater than or equal to 45 seconds but fewer than 50 seconds 
c. Greater than or equal to 50 seconds but fewer than 55 seconds 
d. Greater than or equal to 55 seconds 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Hard
Keywords: standard, time, allowance, cycle

130
Supplement H  Measuring Output Rates

Table H.2

Work Element t (sec) RF F


1 5.6 1.1 1
2 3.1 1.0 1
3 1.9 1.1 1
4 4.0 0.8 2

62. Use the information in Table H.2. Which work element will take the longest for an average worker to 
perform per cycle? 
a. Work element 1
b. Work element 2
c. Work element 3
d. Work element 4 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: normal, standard, time

63. Use the information in Table H.2. If the allowance for this task is 20 percent, what is the standard 
time for the entire task? 
a. Fewer than 20 seconds 
b. Greater than or equal to 20 seconds but fewer than 22 seconds 
c. Greater than or equal to 22 seconds but fewer than 24 seconds 
d. Greater than 24 seconds 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time

64. A time­study analysis was performed on a task with two work elements. The select times for these 
work elements are 21.0 seconds and 13.0 seconds, with rating factors of 1.1 and 1.2, respectively. 
Each work element is performed twice per cycle. If an allowance of 20 percent is used, what is the 
standard time for this task? 
a. Fewer than 50 seconds 
b. Greater than or equal to 50 seconds but fewer than 70 seconds 
c. Greater than or equal to 70 seconds but fewer than 90 seconds 
d. Greater than or equal to 90 seconds 
Answer: d

131
Supplement H  Measuring Output Rates

Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time

132
Supplement H  Measuring Output Rates

65. If a worker spends 10 hours per day performing a task, and the allowance for this task is 19 percent, 
how many hours during the average day is the worker involved in nonproductive activities? 
a. Fewer than 1.75 
b. Greater than or equal to 1.75 hours but fewer than 5 hours 
c. Greater than or equal to 5.00 hours but fewer than 8.25 
d. Greater than or equal to 8.25 hours 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time

Table H.3
A worker was observed for four cycles in a repetitive task. The observer recorded the following 
times, in seconds, using the continuous method. The ratings for each element and frequency it is
performed are also indicated in the table. The allowance fraction is 20 percent.

Element Cycle 1 Cycle 2 Cycle 3 Cycle 4 Rating Frequency


1 15 106 208 309 1.10 1.0
2 37 131 234 334 1.05 0.5
3 47 143 245 348 1.20 0.5
4 90 190 293 392 1.15 1.0

66. Use the information in Table H.3. What is the select time for work element 4?
a. Fewer than 40 seconds 
b. Greater than or equal to 40 seconds but fewer than 60 seconds 
c. Greater than or equal to 60 seconds but fewer than or equal to 80 seconds 
d. Greater than or equal to 80 seconds 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: select, time, element

67. Use the information in Table H.3. What is the normal time for work element 2? 
a. Fewer than 10 seconds 
b. Greater than or equal to 10 seconds but fewer than 11 seconds 

133
Supplement H  Measuring Output Rates

c. Greater than or equal to 11 seconds but fewer than 12 seconds 
d. Greater than or equal to 12 seconds 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: normal, time, rating

134
Supplement H  Measuring Output Rates

68. Use the information in Table H.3. What is the standard time for work element 1?
a. Fewer than 18 seconds 
b. Greater than or equal to 18 seconds but fewer than 20 seconds 
c. Greater than or equal to 20 seconds but fewer than 22 seconds 
d. Greater than or equal to 22 seconds 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time, allowance

69. Use the information in Table H.3. What is the select time for work element 2? 
a. Fewer than 17 seconds 
b. Greater than or equal to 17 seconds but fewer than 22 seconds 
c. Greater than or equal to 22 seconds but fewer than or equal to 27 seconds 
d. Greater than or equal to 27 seconds 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: select, time, element

70. Use the information in Table H.3. What is the normal time for the complete cycle? 
a. Fewer than 85 seconds 
b. Greater than or equal to 85 seconds but fewer than 95 seconds 
c. Greater than or equal to 95 seconds but fewer than 105 seconds 
d. Greater than or equal to 105 seconds 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Hard
Keywords: normal, time, rating, cycle

71. Use the information in Table H.3. What is the standard time for the complete cycle?
a. Fewer than 90 seconds 
b. Greater than or equal to 90 seconds but fewer than 97 seconds 
c. Greater than or equal to 97 seconds but fewer than 104 seconds 
d. Greater than or equal to 104 seconds 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Hard
Keywords: standard, time, allowance, cycle

135
Supplement H  Measuring Output Rates

72. A time­study analyst has found the select time for a work element to be 14.0 minutes, with a sample 
standard deviation of 3.2 minutes. What is the minimum sample size needed if the estimate is to be 
within 4 percent of the average 95 percent of the time? 
a. Fewer than 100 
b. Greater than or equal to 100 but fewer than 140 
c. Greater than or equal to 140 but fewer than 180 
d. Greater than or equal to 180 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size

73. At a new watch assembly plant, a job is divided into three work elements. The element times for the 
first four cycles are recorded by the continuous method and are presented below along with a 
performance rating factor (RF) for each element.

Observation (time in min)


Work Element 1 2 3 4 RF
1 0.50 2.32 4.22 6.16 1.0
2 1.45 3.24 5.20 7.06 1.1
3 1.87 3.62 5.61 7.49 0.9

The standard time for this job, assuming that the allowance is 18 percent, is: 
a. fewer than or equal to 1.9 minutes. 
b. greater than 1.9 minutes but fewer than or equal to 2.0 minutes. 
c. greater than 2.0 minutes but fewer than or equal to 2.1 minutes. 
d. greater than 2.1 minutes. 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time

136
Supplement H  Measuring Output Rates

74. An observer has recorded the following select ( t ) for a five­part task and has applied a rating factor 


(RF) to each. The times are in seconds. If there is a 15 percent allowance for “nonproductive” 
activities, compute the standard time for the total task.

Element t RF
1 6.2 0.9
2 1.7 1.1
3 4.5 1.2
4 1.2 0.8
5 5.0 1.2

The standard time for the task is: 
a. fewer than or equal to 21 seconds. 
b. greater than 21 seconds but fewer than or equal to 23 seconds. 
c. greater than 23 seconds but fewer than or equal to 25 seconds. 
d. greater than 25 seconds. 
Answer: b
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time

75. A worker was observed for four cycles of a repetitive operation. The observed times for work 
elements are 11, 10, 8, and 11 seconds, respectively. What sample size is appropriate for estimating 
the time for this work element within + 3 percent of the true mean time with 95 percent confidence? 
a. Fewer than or equal to 70 
b. Greater than 70 but fewer than or equal to 75 
c. Greater than 75 but fewer than or equal to 80 
d. Greater than 80 
Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size

76. The following times in seconds were observed for a particular one­element job using the continuous 
method: 12, 22, 35, and 50. The worker’s rating factor is 1.1. What is the standard time for the job if 
an allowance of 20 percent is provided? 
a. Fewer than or equal to 14 seconds 
b. Greater than 14 but fewer than or equal to 15 seconds 
c. Greater than 15 but fewer than or equal to 16 seconds 
d. Greater than 16 

137
Supplement H  Measuring Output Rates

Answer: d
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: standard, time

138
Supplement H  Measuring Output Rates

77. A manager wants to determine the proportion of time a cashier is idle. A work­sampling method was 
used, and the idle time was found to be 20 percent based on 100 observations. If the manager wants a 
+ 0.05 with a 95 percent confidence level, how many MORE observations are needed? 
a. Fewer than or equal to 200 
b. Greater than 200 but fewer than or equal to 300 
c. Greater than 300 but fewer than or equal to 400 
d. Greater than 400 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size

78. A work­sampling method is used to determine the proportion of the time a worker is idle. The 
following information was gathered on a random basis.

Day No. Times Total No.


Clerk Idle Observations
Monday 4 12
Tuesday 2 8
Wednesday 4 10
Thursday 2 10

If the manager wants a 95 percent confidence level and a degree of precision of + 0.03, how 
many more observations are needed? 
a. Fewer than or equal to 600 
b. Greater than 600 but fewer than or equal to 800 
c. Greater than 800 but fewer than or equal to 1,000 
d. Greater than 1,000 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Hard
Keywords: sample, size

79. A supermarket administrator suspects that idle time is about 20 percent for the cashier and 15 percent 
for the office clerk. If the administrator wants a 95 percent confidence level and a degree of precision 
of + 0.05 for both cashier and office clerk, how many TOTAL observations are needed?  
a. Fewer than or equal to 200 
b. Greater than 200 but fewer than or equal to 300 
c. Greater than 300 but fewer than or equal to 400 
d. Greater than 400 
Answer: b
Reference: Methods of Work Measurement

139
Supplement H  Measuring Output Rates

Difficulty: Moderate
Keywords: sample, size

140
Supplement H  Measuring Output Rates

80. A job shop manager wants to determine the proportion of time the workers are idle. The shop 
employs two types of workers. Type 1 includes three workers and Type 2 includes two workers. The 
manager suspects that the proportion of idle time is about 20 percent for Type 1 workers and 15 
percent for Type 2 workers. If the manager wants a 95 percent confidence level and a degree of 
precision of + 0.05, how many trips will the observers have to take through the group? 
a. Fewer than or equal to 80 
b. Greater than 80 but fewer than or equal to 90 
c. Greater than 90 but fewer than or equal to 100 
d. Greater than 100 
Answer: c
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sample, size

81. A work­sampling method is used to determine the proportion of the time a worker is idle. The 
following information was gathered on a random basis.

Day No. Times Total No.


Clerk Idle Observations
Monday 8 26
Tuesday 8 32
Wednesday 7 28
Thursday 7 34

If the manager wants a 95 percent confidence level and a degree of precision of + 0.03, how 
many MORE observations are needed? 
a. Fewer than or equal to 700 
b. Greater than 700 but fewer than or equal to 800 
c. Greater than 800 but fewer than or equal to 900 
d. Greater than 900 
Answer: a
Reference: Methods of Work Measurement
Difficulty: Hard
Keywords: sample, size

FILL IN THE BLANK

82. A(n) ____________ is the time required for a trained worker to perform a task following a prescribed
method with normal effort and skill.
Answer: work standard
Reference: Introduction
Difficulty: Easy
Keywords: work, standard

141
Supplement H  Measuring Output Rates

83. ____________ is the process of creating labor standards based on the judgment of skilled observers.
Answer: Work measurement
Reference: Methods of Work Measurement
Difficulty: Easy
Keywords: work, measurement

84. The key to creating a work standard is defining ____________.


Answer: normal performance
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, standard, normal, performance

85. The most commonly used method for setting a time standard is called a(n) ____________.
Answer: time study
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study, standard

86. The ____________ is a measurement found by multiplying the select time, the frequency of work,
and the rating factor.
Answer: normal time, NT
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: normal, time

87. The time added to adjust for factors such as fatigue or equipment malfunction is called
____________.
Answer: allowance time
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: allowance, time

88. Using the ____________, the analyst divides each work element into a series of micro-motions
common to a variety of tasks.
Answer: predetermined-data approach
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: predetermined, data, approach, micromotion

89. The ____________ system features a database with micromotions such as reach, move, apply
pressure, grasp, and turn.
Answer: MTM/methods time measurement/MTM-1
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: predetermined, data, approach, micromotion, MTM, methods, time, measurement

142
Supplement H  Measuring Output Rates

90. ____________ involves estimating the proportion of time spent by people and machines on activities,
based on a large number of observations.
Answer: Work sampling
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling

SHORT ANSWERS

91. What are the advantages and disadvantages of establishing and enforcing work standards? 
Answer: Establishment of work standards allows managers to set prices and costs, motivate 
workers, compare alternative process designs, schedule, plan capacity, and conduct performance 
appraisals. In short, these objective standards allow for a scientific management approach to be 
implemented. The disadvantages of work standards include the dehumanizing aspects of having 
work closely monitored and the overhead required to establish and enforce the standards. If 
workers feel the standards are not achievable, they may suffer a decline in morale or may rush to 
meet them at the expense of quality and safety.
Reference: Work Standards and Managerial Considerations in Work Measurement
Difficulty: Moderate
Keywords: work, standard

92. Are time standards more useful for manufacturing or service processes? Why?
Answer: Answers will vary.
Reference: Work Standards
Difficulty: Moderate
Keywords: time, standards

93. How can work standards be developed for higher level services and creative processes?
Answer: Answers will vary.
Reference: Work Standards
Difficulty: Moderate
Keywords: time, standards, work

94. What are the four steps in a time study? 
Answer: The four steps are selecting work elements, timing the elements, determining the sample
size, and setting the standard.
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, study

95. Explain why a sampling schedule is important in a work sampling study. 

143
Supplement H  Measuring Output Rates

Answer: A sampling schedule should determine when the workers are to be observed because the
observations are just snapshots of time. In addition, the observation times should be randomized 
to avoid biases in worker performance.
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: sampling, work, schedule

96. Compare and contrast the method of time study to the method of work sampling. What are the 
strengths and limitations of each, and for which applications are they best suited?
Answer: Both are direct observation methods. However, a time study observes several cycles of 
work elements to determine a time standard, whereas work sampling takes “snapshots” of the 
facility to determine the percentage of time engaged in an activity. Time studies require 
experienced analysts, should not be used for tasks that vary each time, and are many times found 
to be objectionable to workers. Work sampling does not require special training and is generally 
accepted by workers because it tends to examine activities of the group rather than of the 
individual. In addition, many work­sampling studies can be conducted simultaneously.
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: method, time, study, work, sampling

PROBLEMS

97. A pilot work study has been conducted on a new operation with four work elements. The following 
times, in seconds, were obtained using the continuous method.

Observations
Element 1 2 3 4 5 RF
1 11.00 45.00 80.00 117.00 153.00 1.10
2 20.00 54.00 89.00 125.00 161.00 1.05
3 25.00 58.00 95.00 131.00 166.00 0.85

a. What is the normal time for this operation? 
b. If an allowance of 20 percent is used, what is the standard time for this task? 
c. What sample size is appropriate for estimating the time for element 3 within + 3 percent of the true 
mean time with 95 percent confidence? 

Answer:

Precision (p) 0.03 Allowance 0.20


Standard deviations (z) 1.96

Rating Select Std. Deviation Required Normal


Work Element Factor Freq. Time (sigma) Sample Size Times
1 1.1 1 19.40 4.7749 258.58 21.34

144
Supplement H  Measuring Output Rates

2 1.05 1 8.60 0.5477 17.31 9.03


3 0.85 1 5.20 0.8367 110.50 4.42

a. Total Normal Time 34.79


b. Standard Time 41.748
c. Required Sample Size 259

a. Normal time = 34.79


b. Standard time = 41.748
c. Sample size = 259
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: time, standard, normal, sample, size

98. An undergraduate business student studies diligently in the library during dead week in anticipation 
of an outstanding performance on her final exams. She asks a friend to spy on her at random intervals 
to determine what percentage of time she is actually studying. Over the course of three days, her 
friend records the following observations:

Times Times Not


Observation Period Studying Studying Observations
Monday 20 3 23
Tuesday 21 4 25
Wednesday 10 1 11

Total 51 8 59

If the student wants a 95 percent confidence level and a degree of precision of + 0.08, how many 
more observations are needed?
Answer:
2
�z �
n = � ��p (1 - �p)
�e �
2
�1.96 �51 � 51 �
n=� � � 1 - �= 70.35
�0.08 �59 � 59 �
n = 70.35 - 59 = 11.35

There have already been 59 observations, so 12 more observations are needed.
Reference: Methods of Work Measurement
Difficulty: Moderate
Keywords: work, sampling, sample, size

145

You might also like