Place Concrete”
Presented By:
Brundage-Bone Concrete Pumping, Inc.
Safety Department
1
Concrete Pump Trucks…
2
Concrete Pump Trucks…
¾ Hydraulic reciprocating pumps.
3
High Pressure Hydraulic Lines…
4
Rear Transition Cover…
5
Grate (covers the agitator and concrete valve)…
6
Concrete Pump Trucks...
¾ Concrete pressure during pumping
operations generally from 600 psi to 1233
p.s.i.
7
Wired Remote Control Box…
8
Job-Site Conditions Checklist…
9
How Close Are They?...
¾ Distribution lines
¾ 7,200 volts, phase to ground, is most common
¾ Service drops
¾ 220 volts average; 440 in some industrial
settings
10
Service Drop – 220-440 Volts…
11
Transmission Line 50,000 to 1,000,000 Volts…
Paths to Ground…
12
An Example of “Path-To-Ground”…
An Example of “Path-To-Ground”…
13
An Example of “Path-To-Ground”…
Electrical Burn…
¾ Most Common Exit Wound
14
Why/How Contact With Lines Occurs…
¾ Working in area below lines - pump
operator tries to reach over lines
15
Look Up and Live!!!…
¾ Florida, January 2006
¾ 1 Fatality
16
Look Up and Live!!!…
17
Look Up and Live!!!…
17 Feet!
18
Control Measures…
¾ Site survey ahead of time
Control Measures…
¾ De-energize lines
19
Electrical Awareness Barrier (Cone Policy)…
20
Job-Site Conditions Checklist…
¾ Adequate access and egress routes for
Ready Mix trucks have been established.
Ready-Mix established
21
Job-Site Conditions Checklist…
¾ A staging area has been established for
ready mix trucks.
ready-mix trucks
22
Job-Site Conditions Checklist…
¾A clean out area for the ready-mix and
pump truck has been established.
established
23
Job-Site Conditions Checklist…
¾ Ground Stability has been considered:
¾ Soils Condition - Will the ground support the
weight of a pump truck and ready- mix truck?
Ground Stability…
24
Ground Stability…
¾ Example of virgin soil w/ inadequate
cribbing
Ground Stability…
¾ Virgin soil ALWAYS needs extra cribbing
25
Ground Stability…
52m Outrigger
¾ Exerts 60
60,000
000 lbs of downward force
Ground Stability…
26
Ground Stability…
Ground Stability…
27
Ground Stability…
Ground Stability…
28
Ground Stability…
29
Communication…
¾ Pre-task planning sessions for the up-
coming pour should include
representatives from the contractor,
concrete pumping company, and redi-mix
company.
Communication…
¾ Between the Redi-mix company and
concrete pumping company regarding the
delivery and status of trucks.
30
Communication…
¾ Between the redi-mix driver and pump
operator/hopper watch to ensure
personnel safety while trucks are pulling
up, backing in, and pulling out.
Communication…
31
Communication…
Communication…
32
Communication…
Communication…
33
Communication…
¾ Between the redi-mix driver and pump
operator/hopper watch to maintain the
proper level of concrete in the hopper.
¾ How to locate and activate the horn on
the truck.
g y stop
¾ The location of the emergency p
switches.
Communication…
¾ Full Hopper
34
Communication…
¾ Emergency Stop & Horn
Communication…
¾ Emergency Stop (E-Stop)
35
Communication…
¾ Between Pump Operator and Placing Crew
Communication…
¾ Between Pump Operator and Placing Crew
36
Communication…
¾ Between Pump Operator and Placing Crew
¾ To keep hose moving smoothly and at the proper height
over the concrete…not in it.
37
Hose/Pipe – Size & Selection…
¾ Mix Design
38
Hose/Pipe – Size & Selection…
¾ Ease of Use
39
Hose/Pipe – Size & Selection…
¾ Double-Ended Tip Hose….Never!
40
Air In The System…
41
Blockages In The System…
¾ Dirty Hoses
42
Blockages In The System…
¾ Foreign objects from concrete mixer
trucks (barrel chips,
trucks…(barrel chips oversized aggregate,
aggregate
etc.) can get into the system and cause a
blockage that results in the concrete
plugging.
43
Blockages In The System…
¾ Long delays on the jobsite can allow the
concrete to set up and cause a blockage.
blockage
44
Blockages In The System…
¾ Extreme caution must be taken whenever
a blockage occurs.
occurs The operator must get
all personnel must get back beyond the
reach of the tip hose before he can
attempt to free the blockage.
45
Clamp Opened Under Pressure
46
Blockages In The System…
¾ Kinked Hoses…Will Straighten!
47