You are on page 1of 1

EMPLOYER DOC NO 20-F201007-SC-055 PROJ.

NO 142901

REVISION D

EMPLOYER’S REPRESENTATIVE APL JOB NO. F201007

SHT NO. SHEET 1 OF 34

CONTRACTOR PROJECT TITLE BPGIC FUJAIRAH TERMINAL, PHASE 1

LOCATION FUJAIRAH, UAE

DESIGN CALCULATION FOR HOLDING TANK

FOR

BPGIC FUJAIRAH TERMINAL – PHASE 1

ISSUED FOR APPROVAL

REFERENCE TO MUCOG DOCUMENT NO.: (if any)

REVISION NO DESCRIPTIONS PREPARED BY CHECKED BY APPROVED BY

Saravanan Saravanan Ravichandran


D ISSUED FOR APPROVAL 05-Feb-17 05-Feb-17 05-Feb-17
Capital Khalidass M.Ansar
C ISSUED FOR APPROVAL
12-Mar-17 12-Mar-17 12-Mar-17

Capital Khalidass M.Ansar


B ISSUED FOR APPROVAL
08-Mar-17 08-Mar-17 08-Mar-17

A ISSUED FOR APPROVAL Capital Khalidass M.Ansar


04-Mar-17 04-Mar-17 04-Mar-17

THIS DOCUMENT IS THE PROPERTY OF AUDEX PTE LTD


THE INFORMATION CONTAINED HEREON MAY NOT BE USED OR COPIED IN ANY MANNER
WITHOUT THE WRITTEN PERMISSION OF AUDEX PTE LTD