You are on page 1of 5

Subcontractor/ Material Procurement Register

Budget Spec / Details / Dwgs. Site


Description Quantity Unit Requesiti Send out Enquiry
on

Rate L/S Compliant Alternate Days Date


- #VALUE! #VALUE!
Time for Procurement Process

Material Approval
Tender Period Quotation Analysis Negotiation Submit QCS by Client/
Consultant

Days Date Days Date Days Date Days Date Days Date
10 #VALUE! 3 #VALUE! 2 #VALUE! 1 #VALUE! #VALUE!
ocess

Management Submit PO for Management Issue PO or S/C Submit Design /


Approval Approval Approval (Date) Shop Drawings

Days Date Days Date Days Date Days Date Days Date
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Time for Delivery Process

Testing,
Fabrication /
Approvals Commisioning, Ex Works Shipping
Manufacturing Painting, Inspection

Days Date Days Date Days Date Days Date Days Date
Internal Target
Port Clearance Transport Total Delivery
Days to site

Days Date Days Date