Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Installation of Door Shutters & Architrave 1 No / 12 Manhours
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden


10 Carpenter Day / Room
Box etc.
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Door Shutters & Architrave 1 No / 12 Manhours


Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Installation of Door Shutters & Architrave 1 No / 12 Manhours
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Door Shutters & Architrave 1 No / 12 Manhours


Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Installation of Door Shutters & Architrave 1 No / 12 Manhours
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room