8 Maintenance
8 Maintenance
8.1 Introduction
General
Instructions
‘These maintenance instructions give recommendations for care and guidelines for
‘maintenance of high-voltage circuit breakers,
The instructions are divided into:
+ Inspection intervals
+ Instructions for preventive maintenance of circuit breakers
+ Instructions for preventive maintenance of operating mechanisms
‘The periodic maintenance is to be carried out at specified time intervals or number of
‘operations.
Equipment is to be overhauled in line with specified criteria such as a certain number of
operations. Overhauls are to be made by authorized service personnel.
TASBIDOET Gen
oID0S 7078 Maintenance
8.2 Description of maintenance categories
Maintenance categories
Action/explanation Interval Condition of Requirement
Circuit breaker
'B Preventive maintenance i
+ General overhaul of circuit 15 years or 5 000
breaker and operating mechanism Perations
+ _ Heat measurement
Overhaul of breaking chamber ct a
Overhaul of line and transformer circuit Enxi2=20 000
breaker
‘Overhaul of capacitor bank circuit
breakers, reactor cicult breakers and
fiter circuit breakers
+ Without pointion-wave control 2,500 operations
+ With point-on-wave control )
General overnaul ‘After 30 years or dt a
40 000 operations 7)
Explanations
Maintenance, circuit breaker pole on page 116 .
2) Special requirements for resistance checks for circuit breakers; executed >100 Close and
tripping operations per year.
Condition of circuit breaker
The following specifies the condition in which the circuit breaker should be for the various,
maintenance activities.
+ al) circuit breaker in operation.
+ 1) Closing spring discharged, circuit breaker open, disconnected and earthed. If heat
‘measurement is part of the maintenance activity, this should be done during normal load
before the circuit breaker trips.
+ cl) Closing spring discharged, circuit breaker open, disconnected and earthed. The
circuit breaker poles/breaking units are dismantled and transported to the workshop.
+ dl) Closing spring discharged, circuit breaker open, disconnected and earthed. The
entire circuit breaker with operating mechanism is transported to the workshop.
Competence requirements
‘The following describes the necessary requirements for personnel carrying out maintenance
work.
*+ a2) substation personnel without special training.
+ b2) personnel authorized by ABB to carry out assembly, commissioning and
maintenance work.
+ ¢2) personnel authorized by ABB to carry out assembly, commissioning and
‘maintenance work. In some cases support may be necessary from ABB.
oo) D2OET THSBADOOSE Sen
NOAA AAA AAA Ae.8 Maintenance
8.3 Maintenance schedule
General
The following inspection schedule includes important control points, acceptable tolerances,
functional values for certain adjustments and recommended inspection intervals. In corrosive
or polluted air and in climates with high humidity, it may be necessary to half the inspection
interval. The specified inspection intervals are o be regarded as recommended guidelines that
er be extended or shortened depending on local conditions.
ficance of the various categories are explained in section Description of maintenance
categories on page 108.
Category A
Maintenance category A takes place at an interval of 1-2 years
Inspected Action |
circu breaker ‘Check:
: | Exterorcleaningon page 118 and Gas
nal cleanin
| == Bene teenies | systom and density moniter on page
+ Heating element function | 10
| + Gas pressure No special tools needed
+_Valves and draining holes
Category B
Maintenance category B takes place at an interval of 15 years or 5,000 mechanical close/open
operations.
Inspected ‘Action Instructions/Tools
‘ireut breaker ‘Check: This is covered in section:
‘ Exterior cleaning on page 118 and Gas
nin |
External cleanness system and densily monitor on page 10
+ Gas pressure [No special tools needed.
+ _Valves and draining holes
Operating ‘Check:
mechanism eden
+ Heating element function
+ _Oilleaksfror
Rating plates Note serial number. —
‘Operation counter | Note the number of operations.
‘SF 988 ‘Check
ean ‘See Gas fling with SF6-goson page 91
necessary) Dew point meter.
+ Dew pint fornorna ges |D2W/Pont ma, °C at specie ng
pressure in the circuit | Pressure an
breaker.
insulators | Check: Wash and dry the insulators.
pris andais Rinsing equipment, drying cloths, torque
wrenches.
This is described in Exterior cleaning on
age 118
THSBADBOEE Sen 201205 7058 Maintenance
Inspected
‘Composite insulators
Main circuit
Heat measurement
Mechanism
Function times
Action
Check:
Check:
Check:
(Check:
Resistance measurement
Resistance bridge, using a
test current of 200-400 A
oc
Instructions/Tools
Resisiance values as epedfedin secon
Operating values on age 4,
Intho case of reat breakers wih a lood
Curent of ss than 400 A reltance
| ate of upto 1000 uOhm is permite per
[Beata
| Caries out at ced pir to
| disconnection of the circuit breaker.
The temperature increase |
In the outer parts of the
breaking unit,
Reference hole in outer
lever and mechanism
housing
Opening time
Closing time
Close-Open time
Deviations betwee.
phases
Auxiliary switch
Travel curve
Contact damping
The highest permitted temperature
difference between the phases is 5°C.
Thermal camera.
Consideration must be taken to the load
Current during measurement, both to the
larger variations ofthe load current 3-4
hours prior to measurement. See the
‘manual forthe thermal camera,
‘Measuring with electronic timing,
[Nominal control voliage
For times, see Operating values on page
44,
‘Maximum time deviation between the
phases, 4 ms at closing and 3 ms at
opening,
70
DODO
THSBADGOGE Ten
QANNNNNNANNNRAANNANNKHNANHRNAANNnANNnnnnnnnnnen.8 Maintenance
[Action | Instructions/Toots
Rod aystem
oe Check ot hteing torque for nus inthe
tod eyo
* Control safety ‘See Fitting of rod system on page 71.
+ Astipumping relay Control satety:
Measurement of minimal contel votage
Closing cot < 85% IEC (<72% ANS) of
nina value Tepping ol < 70h ee
(£864 ANSI) of anal value Variable
Deswotage unt
_antipumpng rte:
Wit he cut breaker in Open poston
andthe operating mechanism charged, 8
Simultaneous Close and Open operon s
produced (Chae buon presse),
|The cic breaker aries outa Closer
| | Open operation and must not Close when
| the operating mechanism is charged.
The ant-pump funeton must be activated
along asthe dose impulse lasts, The
‘owes contol vatiag stobe measured for
the rely (85 of tomna)
FT motor eurent must be measured
towards to ond of he charging process
The maximum permite motor currents
110 %oftremaasuroment valves recoved
dhtng route lots,
“The permitted variation in charge ie is
30% ofthe measurement valve obtaned
ding routine tests.
The moto must be abet charge the
Sorings aa minimum of 85% of nominal
votage (as par IEC)
| | see inspection o dive unt on page 123
Lath doco Vaal inepesionfestinas For vetioatgan te a even ae
‘Soriaces on Shas and atsne te
‘overs ving renner See wean
"Types of graze on page 37
oa ~The col resistance and curentsalowed
Col Check The col resistance and curtis ol
to vary £10% ofthe measurement vale
Obtained during rouine test
init eich Function contol Inthe final phase ofthe charging proces of
ue the spring, the closing circuit must be
Cloeed before cating the motor curt
See Check oft atch end aury
contact on page 128.
“Motor current
+ Motor current
+ Coil resistance and current
+ Rasistence measiremant [spercabie.
‘See fspection orheadng efementon page
122,
,
THSBAT05- Sen 2012-05-11 Tr8 Maintenance
Instructions Tools
Small cabinet:
48 W, HOV R= 330 ohm 210%
|48.W, 220 Re 1000 ohm 210%
“Medium-sized or large cabinet:
| 140 W, 110V R= 86 ohm 210%
Inspected
Central control
cabinet (f applicable)
+ Resistance measurement
‘Check that the thermostat is adjusted to
‘comply with the set value
Pre-commissioning check lston page
Thermostat (if
applicable)
104.
‘Check that bolts and clamps are property
tightened.
“Terminal blocks
| Check the signal for voltage drop, if any.
switch
‘Check the density monitors as regards
pressure indicator and signal/break
contacts.
+ Signal for voltage drop
‘Check:
+ Density monitoring
SealsiSFe gas
NoTE!
‘The test must take place in normal
‘conditions, +20 °C and 101.3 KPa
(1,013 mbar),
| Remove the density monitor from the
| Sreut eater check he tuncton,
Minimum permed voltage when
| hocking 20
See Assen of gas montoringsysomon
eo _|page 78
Blocking relays ‘Check: |
|The relays must break when a denaty
|Inontor's moved fom a creat breaker
pote, pressured a ling pressure,
Nore!
May ony be cared out when te ccut
+ Relays
Corrosion Check:
: a Make a special check ofthe protected
Operating mechanism | components inthe unheated areas, pull-
rod system, forks and springs
Treat wih ane-ust agent where necessary.
See Cleaning, ubvicaton, and rust
protection of operating mechanism on
page 121
Lubrication Cheek: Chock and ubriate the latches using
| | grease“
| CCheck and lubricate the worm gear using
| + Worn gear grease "M"
i
Dae TASBADGS Sen
DAHAHAAHANAAANHAAAAAAANDRAAAAANAnnnnAction
Inspected
Tightening torque | Check:
‘Cheek
‘Operation
Al bot joints
8 Maintenance
InstructionsrTools
| Check the tightening torque on all bot
|ioints
See Tight 40.
‘Operation ination (if possible)
with operating time measurement (inc
ee eat ‘open/close operation time).
+ Operating time
measurement
Category C
Intra Instructionsools
“Overhaul of Breaking un Instructions:
= Line and transformer circuit 0.000 | Evacuate the gas, dismante the cuit
breaker breaker poles and transport to clean
| workshop. Dismant the breaking chamber
| “insulator ft anew contact set and new PTFE
- Capacitor, reactor and fiter “components.
circu breaker | equipment:
+ without pointonave |2,500 operations. | Standard equpment ht ting face mask or
contol dust protection, long sleoved overal,
«ain peanton-wio = [1p protective gloves of plastic or rubber.
contol See Ovortaulof breaking unit on page 151.
AAltypes of maintenance During diagnostic
testing with non- |
oe [contortion e -
Overhaul of complete creut | 80 years or 10,000 | Dismanting of cru breaker pole and
breaker and operating mechanical lose! | mechanism. Assembly of nw contact set
mechanism ‘Open operations | Replacement o ther worn components,
[ihe cet breaker andthe operating
| mechanism are being overhauled fora further
2,000 operations, all wear parts must be
replaces
| Ifthe circuit breaker and the operating
mechanism are overhauled fora further
40,000 operations, the entre cel breakeris
| to be reconditioned
[Protection against crevice products as per
standard equipment above
Instructions:
See chaptor Overhaul on page 196.
For operating mechanism, with instructions
4 guidance from ABB
” See Maintenance, circuit breaker pole on page 116.
FSET Ten WET 738 Maintenance
8.4 Maintenance, circuit breaker pole
8.4.1 The service life of the circuit breaker
General
Assuming that the recommended inspection intervals and actions have been observed, the
circuit breaker will have a service life greater than 30 years or 10,000 mechanical operations.
Maintenance points
‘The following points ensure a long service life
Maintenance points
breaker
Bearings in the
4 [The seals are designed with a double sealing ring
Opening the breaking unit
In general there are only two reasons for opening the breaking units:
1 Ifthe number of shor-circults x short-circuit current (KA) approaches the curve, see figure No. of
__operations on page 117.
2 Ifthe number of operations atthe line, reactor or capacitor connection, as well as the switching of
load current’) has reached the number under the heading "Interval in Description of maintenance
categories on page 108.
') The load currents from normal Close and Open operations are not calculated in the formula.
‘These are only calculated when counting the total number of mechanical Close and Open
operations.
‘Another reason for opening the breaking units is limited to mechanical faults/faulty adjustment
of the drive system, that could damage the components inside the breaking units.
NoTe!
A Opening the breaking unit calls for special instructions and may only be carried out by
qualified and authorized personnel.
Calculations
‘The graph that shows the restriction to the number of permitted short circuits can be given
roughly as
Formula Explanation
Enx l= 20000, ‘n= number of short circuits
|= short-circuit current KA (RMS)
In the formula, all levels of short-circuit current are included.
E.g. 10x307+20x207+20x10" = 19,000.
WT Dia THSBA20054-G0n
ONAAAOAAAAAADAAAAAAnnnnen
Nannnnnnnnnn8 Maintenance
8.4.2 The service life of the arcing contacts in the event of short circuit breaking
The diagram shows the number of breaks asa function of the breaking current that the contacts
{n a circuit breaker can undergo before burn-off is so great that they must be replaced.
Wo. of operations —
5000
2000
1000
500
20 30 4050 63
c002855
1n__|No.of operations
Short-circuit current
TASBAROS en DODO
TS8 Maintenance
8.4.3 Cleaning and lubrication of circuit breakers
Exterior cl
The circuit breaker's porcelain insulators are to be cleaned of salt and dirt deposits in
connection with cleaning of other insulators in the substation. The time interval for this
cleaning depends on local conditions, ie. the degree of air pollution.
‘Wash and dry the insulators using rinsing equipment and drying cloths.
WARNING!
A Work on the circuit breaker when there is a risk for mechanical damage to the insulators is to
be executed at reduced gas pressure, 0.125 MPa (abs)
NoTe!
FD acest wit ein ints complet west ite ii
breakers in use can be cleaned using water without any tisk of moisture penetrating and
damaging important parts.
Composite insulators do not normally require cleaning. Solvents or water rinsing with high
pressure could damage the silicone surface on the insulator.
Cleaning the mechanism hou:
9
Clean the mechanism housing where necessary through vacuuming. The time interval for this
cleaning depends on local conditions, i.. the degree of air pollution.
Lubricant
Only use lubricants recommended in section Types of grease on page 37. This
important at temperatures below -25°C.
particularly
Lubrication of circuit breakers
The circuit breaker bearings are lubricated with grease on delivery and do not normally need
to be lubricated other than for larger overhauls.
See Treatment of sealing surfaces and seals on page 161
Rust protection
‘The closing springs are surface treated through manganese phosphating agent and anti-rust
protected by being dipped in oil. The trip springs are anti-ust protected with two-component
paint.
See Rust protection on page 134.
Te DOID0S-TT THSBADOSE SER8 Maintenance
8.5 Maintenance, operating mechanism and link system
8.5.1 Preparatory measures and overview of the operating mechanism
General
This section describes the actions that mustican be made prior to commencing maintenance
work.
WARNING!
A Do not operate the operating mechanism without a load! Operation must not be conducted until
the device has been connected and adjusted as appropriate for the associated pressurized circuit,
breaker,
Operating mechanism
‘The components in the operating mechanism are integrated into a cabinet that also contains an
control panel with control equipment.
cooert4
1 {Drive unit
2 [Mechanism
3___ [Control pane!
4 [Closing spring
‘5 [Heating element
THSBADOEA en DID0S- 78 Maintenance
Control panel
co076a
Control pane!
[Control switch, Close/Open
Switch, LocalRemote/Disconnected
‘Spring indicator
Protective motor switch
Before commencing maintenance the following must be done:
Action Note
2. Disconnect the motor curent using the
[protective motor switch,
3. Perform a close-open operation o ensure that
the operating mechanism spring discharges.
4. | Cut the control voltage and where necessary
the heater votage os wel
5. Disconne rth,
.
1 Move the circuit breaker tothe open position.
To facilitate maintenance, the following can be performed:
Action
Remove te top ofthe operating cabinet. = _
2. Open the control panel. Tt
ie DORIS THSBADSISS Sen8 Maintenance
8.5.2 Cleaning, lubrication, and rust protection of operating mechanism
Safety - = 7
WARNING!
A ‘Work on the operating mechanism with the circuit breaker in closed position and charged
springs always represents a risk.
Its therefore important to observe the safety instructions before commencing work, See
Hazardous working situations on page 28.
Lubricant - -
‘The table below shows the greases and oils that are needed for this maintenance. For suppliers
and trade names of oils and greases, see sections Oil types on page 35 and Types of grease on
page 37.
Lubricant
5316 381-4
[ss 36t - —
+HSB875318-C
Cleaning _ 7
Clean the operating mechanism and mechanism housing where necessary through vacuuming.
The time interval for this cleaning depends on local conditions, ic. the degree of air pollution.
(Check thatthe filters in the valves are clean, Replace them if they are overly dirty.
Lubrication - -
The operating mechanism’s ball, roller, and needle bearings and worm gear are permanently
lubricated and require no maintenance. Shafts in latch devices are to be lubricated with grease
"L"; see Maintenance schedule on page 108.
AS part of the overhaul, the slide surfaces for the damper are to be lubricated with grease "G"
‘The dampers are filled with “S” oil on delivery.
Rust protection
On delivery, the operating mechanism is treated with desiccant as transport protection against
moisture,
Despite good anti-rust treatment, minor corrosion may occur, particularly if the circuit breaker
is installed in a highly corrosive environment.
Rust spots must be polished off and new anti-rust agent applied, see Rus? protection on page
134
Spare parts
Spare parts must be stored indoors in an approved storage area!) and in original packaging.
‘This applies especially to rubber components (seals etc.) that must also be protected against
sunlight to prevent drying out. Gaskets can be stored only for a limited period, so avoid
stocking them. Supports ean be stored outdoors
D Approved storage areas: Roof, solid ground, sir huamicity below 50%,
temperature 420°C (410°C),
TASBA200543en DIRS 78 Maintenance
TD DODO THSEA2OGSESen8 Maintenance
8.5.3 Inspection of heating element
Operating mechanism is fitted with a heating element to prevent moisture, and this must
always be connected.
Heating element
conaTe6 v
1__|Heating element
Instructions
Action Note
1 Measure the element's resistance in order 10 element intact
2. | Measure the power supply to the element
Data 7
See se
Heating element on page 23 for values.
‘The 70 W heating element is always connected, while the 140 W or 2x 140 W heating
elements, for temperatures below -25°C, are thermostat controlled.
THSBADIOEE en 2OIZ0ETT Tai8 Maintenance
8.5.4 Inspection of drive unit
General
This section describes how to check the drive unit, and overhaul of the motor.
Drive unit
cooze19
Closing lever
Roller
Bolt MGX75 (2 pos), washer 6.4x12x1.5 (2 pes)
Drive unit,
Requisite equipment
Equipment Part number Note
“Standard tools :
Locking fuid
Torque wrench :
269 0014-408
ir DIDO THSBA20GS4 Sen