ETC job of 245 kV Circuit Breakers at Vizag Steel Plant, Visakhapatnam

Scope of work
Sl No Particulars Unit Qty Rate (Rs) Amount (Rs) Remarks

1 Unloading of 245kV SF6 Circuit Breaker. No 18 6,300 113,400

2 Dismantling of existing Circuit Breaker. No 18 27,900 502,200

3 shifting of CBs to VSp stores 18 7,200 129,600


4 erection of new CB & LCC 18 39,600 712,800

5 connecting of conductor 18 6,300 113,400

6 Laying & conneting of control cables. lot 1080 225 243,000

Assisting in gas filling, testing and


7 commissioning of KV SF6 Circuit Breaker. No 100 450 45,000 Rate per Man Day.

8 FOUNDATION FOR PLATFORMS AND LCC NO 18 27,000 486,000

9 Minor civil modification 216 1,500 324,000

10 clearing of debris 18 1,500 27,000

11 earthing connection 900 63 56,700

12 Security Guard 32 6,300 201,600 Rate per Man Month

TOTAL 2,954,700

A Service Tax Extra @ 10.3%.


B Works Contract Tax Extra @ 4%.
PG POWER SYSTEMS PVT. LTD.
No. 28-9-8/6, Suryabagh.
Visakhapatnam.(AP).
Offer & Terms (20.3.2010) - ERECTION WORKS for M/s.AREVA T & D India
Ltd at Vizag Steel Plant.

1 Price Basis:
Installation and assisstance during testing , commissioning of 18 sets of 220kV,
1.1
SF6 Circuit Breakers with accessories - as quoted in the Price Format.
1.2 Service Tax extra at 10.3% on the above quoted Basic prices.
1.3 WC Tax extra at 4% on the above quoted Basic prices.
1.4 Validity: This offer is valid for a period of 45 days only.

2 Payment Terms:
2.1 80% against monthly running bills based on work done at site.
2.2 20% on completion of work within 30 days.
2.3 Part payments to be made for part shipments/ work done.

Payments to be made within 30 days of our bills by electronic transfer to our


2.4
designated Bank.

3 Mobilisation time required is 25 days.

We shall depute sufficient number of manpower to complete the scope of


work given in the enquiry, however the time for completion of the project
4
depends entirly on the availability of TOTAL POWER SHUT DOWN time and
availability of equipemts for erection at site.

Only minor chipping or grouting if required during erection of the Circuit breakers
5 will be done by us, if any civil work is involved / required, the same shall be
charged extra on mutually agreed rates.

All other materials like - structures, fastners, clamps,conductor, control cables,


6 glands, lugs etc., hardaware and consumables required for erection shall be
provided by M/s. AREVA.

Our rates are based on "Free supply of Electricity " by AREVA / Client at
7
respective erection site.

Statuatory obligations like- Minimum Wages Act, PF, ESI / Workmen Insurance will
8
be taken care by us.

Electrical Inspection Charges and Approvals by State or Central Electricity


9
Authority is excluded in the scope of our offer.

Personal Protective Equipment like Safety shoes, helmets, safety belts will be
10
provided for our workmen .