MAIN BUILDING ₱291,115,154.58 94% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80%
LANDSCAPING ₱4,198,950.00 1% 0.143% 0.143% 0.143% 0.143%
BOATING LAGOON ₱6,346,000.00 2% 0.25% 0.25% 0.25% 0.25%
PLAYCOURTS ₱4,827,000.00 2% 0.67% 0.67% 0.67%
HARDSCAPE ₱2,067,000.00 1%
TOTAL 2.80% 2.80% 2.80% 3.86% 3.86% 3.86% 3.19%
3% 6% 8% 12% 16% 20% 23%
WK 8 WK 9 WK 10 WK 11 WK 12 WK 13 WK 14 WK 15 WK 16 WK 17 WK 18 WK 19 WK 20 WK 21 WK 22 WK 23
2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80%
0.143% 0.143% 0.143%
2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80% 2.80%
72% 75% 78% 81% 83% 86% 89% 92% 95% 97% 100%