Professional Documents
Culture Documents
Revision of Arbitration and Contract
Revision of Arbitration and Contract
The Client
The Engineer
The Contractor
The Project
Work
Scene 1
Choice of Contract
Money
Drawings
1. Design
2. Construction
3. Quality control
4. Supervision
5. Dispute Resolution
6. Certification
Roles may be allocated to an individual or to several parties.
Arbitration
Supervision
Certification
As mentioned before the choice of contract will depend on mainly the allocation of risk,
responsibility for design, the responsibility for financing and the valuation of work done.
1. Re-measurement Contract
1. Risk is taken on by the employer this is significant due to the unpredictability of construction
projects
2. Estimated quantities are often different from the actual quantities
3. The bill of quantities is used to estimate the value of the works as well as calculating the final
contract price
4. The employer must require a detailed makeup of the rates of quantities during tendering
and any changes to rates during the execution of the works must be approved by the
engineer
5. There is no warranty the measurements of the quantities are accurate
6. The preliminary items has a major impact on the final contract price. If the prelim items only
form part of fixed expenditure the a recalculation of the contract price should be acceptable
but if the prelim items form a major part of the contract then only adjusting the contract
items may lead to an incorrect evaluation of calculation of the contract price.
Bill of Quantities
1. It is a document used to calculate the cost of items and activities required for the
completion of the project.
Apportionment of Responsibilities
2.
Changes to quantities are a common feature in contracts and it is important to device methods for
dealing with such situations when they arise.
It is important to ascertain methods to price the difference between estimated quantities and actual
quantities.
4. Target price
Lump Sum
Allocation of Risks
Risks are a common feature of project. A principle function of the contract is to allocate risks
- Risks allocation philosophy is concerned with who is to bear a risk if it is out of the control of
one or the other party
4. Ability to foresee
5. Likely to benefit
Specifications
Design Specification
1. Gives a description of the materials and the manner of in which work should be carried out
2. Relieves the contractor of any responsibility because it implies building according to its
instructions should result in expected performance
Performance Specifications