You are on page 1of 83

ELECTRIC

DISTRIBUTION
ESTIMATING
BOOK

2009

Avista Utilities, Distribution Design


PO Box 3727, Spokane WA 99220-3727 (509) 489-0500

2004 Avista Utilities. All Rights Reserved.


LOADED DOLLARS PER MAN-HOUR

WEIGHTED
3-Man Crew 4-Man Crew 5-Man Crew AVERAGE

ZONE1A 67.05 63.27 58.02 62.78


ZONE1B 77.53 72.93 66.75 72.41
ZONE1C 88.73 83.91 76.64 83.09
ZONE1D 102.99 96.20 87.69 95.63
ZONE1E 118.23 110.11 100.13 109.49
ZONE1F 135.38 125.72 114.11 125.07
ZONE2A 90.88 86.58 80.05 85.84
ZONE2B 105.98 100.65 92.93 99.85
ZONE2C 123.55 116.99 107.82 116.12
ZONE3A 92.71 88.91 81.58 87.73
ZONE3B 108.41 102.88 94.94 102.08
ZONE3C 126.74 119.93 110.49 119.06
ZONE4A 94.40 89.80 82.99 89.06
ZONE4B 110.59 106.56 96.80 104.65
ZONE4C 129.64 122.66 112.95 121.75
ZONE5A 96.02 91.30 84.33 90.55
ZONE5B 112.76 106.91 98.61 106.10
ZONE5C 132.52 125.32 115.36 124.40
ZONE6A 98.16 93.26 86.11 92.51
ZONE6B 115.62 109.55 100.97 108.71
ZONE6C 136.35 128.86 118.53 127.91

LOADING MULTIPLIERS FOR ESTIMATING

WEIGHTED MATERIAL MULTIPLIER


WITHOUT TRANSPORTATION
1.120

AVERAGE UNLOADED LABOR RATE PER MAN-HOUR

3-Man Crew 4-Man Crew 5-Man Crew


$35.20 $33.29 $30.57

1-1 05/09
INSTALLED COST FOR 30-FOOT POLE
(Assume Zone 1A - Wiring and Luminaire Not Included)
1 2 3 4 5 6
Purchase
Year Installed Depreciation Current Price to Retirement
Install Cost Percent Value Customer Value
1978 183.55 42.0% 77.15 1.00 183.55
1979 202.69 43.9% 88.98 1.00 202.69
1980 237.90 45.8% 108.89 1.00 237.90
1981 273.65 47.6% 130.37 1.00 273.65
1982 294.27 49.5% 145.69 12.93 294.27
1983 316.97 51.4% 162.86 30.10 316.97
1984 326.09 53.3% 173.64 40.88 326.09
1985 336.34 55.1% 185.39 52.63 336.34
1986 301.86 57.0% 172.03 39.27 301.86
1987 336.66 58.9% 198.16 65.40 336.66
1988 372.85 60.7% 226.43 93.67 372.85
1989 322.71 62.6% 202.02 69.26 322.71
1990 360.33 64.5% 232.30 99.55 360.33
1991 342.80 66.3% 227.41 94.65 342.80
1992 377.42 68.2% 257.44 124.68 377.42
1993 395.94 70.1% 277.47 144.72 395.94
1994 417.28 72.0% 300.23 167.47 417.28
1995 440.31 73.8% 325.04 192.28 440.31
1996 463.34 75.7% 350.70 217.94 463.34
1997 503.84 77.6% 390.78 258.02 503.84
1998 538.89 79.4% 428.04 295.28 538.89
1999 565.63 81.3% 459.86 327.10 565.63
2000 628.99 83.2% 523.13 412.55 628.99
2001 669.33 85.0% 569.20 480.80 669.33
2002 684.26 86.9% 594.69 528.47 684.26
2003 739.86 88.8% 656.85 612.81 739.86
2004 762.42 90.7% 691.13 669.27 762.42
2005 685.63 92.5% 634.34 634.34 685.63
2006 741.24 94.4% 699.66 699.66 741.24
2007 728.50 96.3% 701.25 701.25 728.50
2008 812.72 98.1% 797.52 797.52 812.72
2009 886.53 100.0% 886.53 886.53 886.53
COLUMN NOTES:
1 Year Installed
2 Installed Cost: All costs are for Zone 1A, with 3-man crew.
3 Depreciation Percent: Annual depreciation rate (see page 1-3).
4 Current Value: Installed cost times depreciation percent.
5 Purchase Price to Customer: CURRENT VALUE minus REMOVAL
(1.98 MH x 3-man crew-Zone 1A rate) plus SALVAGE (page 6-2).
Company property must be sold for no less than $1.00.
Obtain a Bill of Sale for our records when selling poles to customers.

1-2 05/09
UNRECOVERED COST

Refer to the following table and find the Account Number for the Depreciable
Property. Each account must be figured separately for each year.

EXAMPLE: Acct. 364 (has an average life span of 45 years)


(1) 30P85 (depreciable property) (installed cost $336.34)

2009 (present year)


- 1985 (year installed)
24 x 1.87% (Annual Dep. Rate) = 0.4488

Installed Cost x Depreciation Rate = $336.34 x 0.4488 = $150.95


Unrecovered Cost = $336.34 - $150.95 = $185.39

FERC Annual
Account Depreciation Rate
Number Account Title Rate (%)

DISTRIBUTION PLANT
361 Structures and Improvements 2.13
362 Station Equipment 2.47
364 Poles, Towers and Fixtures 1.87
365 Overhead Conductors/Devices 1.30
366 Underground Conduit 1.88
367 Underground Conductors/Devices 2.27
368 Line Transformers 2.65
369 Services 2.13
370 Meters 3.28
373 Street Lighting and Signals 2.21
373.4 High Pressure Sodium Vapor Lights 6.05

1-3 05/09
WIRE WEIGHTS—OVERHEAD CONDUCTOR
(Pounds per 1000 Feet)

COPPER - BARE SOLID ALUMINUM - ACSR


Size Pounds Size Name Pounds
8 50 4 Swanate 67
6 (SD & HD) 79 2 Sparrow 91
4 (SD & HD) 126 1/0 Raven 145
2 (SD & HD) 201 2/0 Quail 183
4/0 Penguin 291
336.4 Merlin 366
397.5 Ibis 547
COPPER - STRANDED 556.5 Parakeet 717
Size Pounds 795 Drake 1094
2 205
1/0 326
2/0 (SD & HD) 411
3/0 518 ALUMINUM - AAC
4/0 653 Size Name Pounds
250 (SD & HD) 772 6 Peachbell 25
350 1081 4 Tie Wire 39
500 1544 266.8 Laurel 250
750 2316 336.4 Tulip 316
1000 3088 556.5 Dahlia 522
795 Arbutus 746
954 Magnolia 900
1272 Narcissus 1194
COPPERWELD - BARE
Size Pounds
8 46
6 Sol 73 GUY WIRE
4A 162 Size Pounds
6A 102 9 Iron 58
8A 74 6 Iron 112
6 Iron 112 5/16 (3W) 171
6 Crapo 112 5/6 EHS 205
9-1/2 D 56 3/8 UG 273
7/16 UG 399
1/2 UG 517

COPPER - COVERED SOLID


Size Pounds
6 (SD) 87

1-4 05/09
WIRE WEIGHTS—OVERHEAD CONDUCTOR
SECONDARY 600V
(Pounds per 1000 Feet)

COPPER - INSULATED 600V ALUMINUM-INSULATED 600V


Size Pounds Size Name Pounds
2 230 6DX Sheppard 77
1/0 367 4TX Periwinkle 172
3/0 572 2TX Cockle 230
250 810 2/0TX Cavolinia 460
500 1600 4/0TX Cerapus 695
2QX Palomino 355
2/0QX Grullo 690
4/0QX Appaloosa 1034

WIRE WEIGHTS—UNDERGROUND
PRIMARY & SECONDARY
(Pounds per 1000 Feet)

ALUMINUM JACKETED with


CONCENTRIC NEUTRAL ALUMINUM-INSULATED 600V
Size Pounds Size Name Pounds
2 550 6DXUG Claflin 100
1 Sol 600 2TXUG Stephens 275
1/0 (Full N) 623 2/0TXUG Converse 525
1/0 (1/3N) 560 4/0TXUG Sweetbriar 765
350 (1/3N) 1120 350TXUG Wesleyan 1161
750 (1/3N) 2000 2/0QXUG Syracuse 705
1000 EPR (1/8N) 2160 4/0QXUG Wake Forest 1038
1 Sol TX 1800 350QXUG Slippery Rock 1552
1 (25kV) 675 (3)350 Rutgers 1350
1/0 (35kV) 920 (3)750 Sewanee 2730

MISCELLANEOUS OH & UG
SINGLE STRAND CONDUCTOR - 600V
Size Name Pounds
2AL Clemson 100
2/0AL Yale 190
4/0AL Beloit 280
350AL Rutgers 450
750AL Sewanee 910

1-5 05/09
ZONE INDICATOR
Each Zone Indicator consists of two characters which signify the location of a job
site with respect to a temporary headquarters (THQ) and/or a permanent
headquarters (HQ). All of the indicators currently in use can be interpreted from
the general form below.

X ZONE X

THQ to HQ SITE to THQ


1. No THQ exists A. 0-10 Miles
2. 31-40 Miles B. 11-20 Miles
3. 41-50 Miles C. 21-30 Miles
4. 51-60 Miles D. 31-40 Miles
5. 61-70 Miles E. 41-50 Miles
6. 71-80 Miles F. 51-60 Miles

Examples:
ZONE 1C—The job site is located within 21-30 miles of the permanent
headquarters.

ZONE 3B—The job site is within 11-20 miles of the temporary headquarters. The
THQ in turn is located within 41-50 miles of the permanent headquarters.

ASSIGNED ZONES FOR LOCATIONS SERVED FROM HEADQUARTERS (HQ)


AND FROM TEMPORARY HEADQUARTERS (THQ). ONE DAY BASIS FROM HQ
AND ONE WEEK BASIS FROM THQ.

SPOKANE AREA - S50

Miles Zone Miles Zone


From Subzone From Subzone
HQ 1A Spokane 5 1A Millwood
10 1A Airway Hts 14 1B Nine Mile Falls
20 1B Cheney 9 1B Opportunity
12 1B Colbert 11 1B S.I.P.
9 1A Dartford
17 1B Deep Creek HQ 1A Deer Park
7 1A Dishman 9 1A Chattaroy
21 1C Espanola 4 1A Clayton
14 1B Four Lakes 4 1A Denison
17 1B Liberty Lake 16 1B Deer Lake
12 1B Marshall 12 1B Elk
7 1A Mead 11 1B Loon Lake
15 1B Medical Lake 10 1A Williams Valley

1-6 05/09
COEUR D' ALENE AREA - L53

Miles Zone Miles Zone


From Subzone From Subzone
HQ 1A Coeur d'Alene 7 1A Post Falls
31 1D Blanchard 13 1B Rathdrum
1 1A Clarkville 24 1C Spirit Lake
3 1A Dalt. Gard. 14 1B State Line
38 1D Harrison 18 1B Twin Lakes
6 1A Hayden
9 1A Hayden Lake WASH
4 1A Huetter HQ 1A Coeur d'Alene
11 1B McGuire 40 1D Newport

SANDPOINT AREA - J53


Miles Zone
From Subzone
IDAHO
HQ 1A Sandpoint
25 1C Clark Fork
3 1A Douer
21 1C E-Hope
18 1B Hope
3 1A Kootenai
33 1D N. of Priest River
31 1D Old Town
2 1A Pend Oreille
22 1C Priest River
13 1B Sagle
12 1B Sunnyside

KELLOGG/ST. MARIES AREA - H53


Miles Zone Miles Zone
From Subzone From Subzone
HQ 1A Kellogg 22 1C Pritchard
11 1B Cataldo 20 1B Rose Lake
8 1A Enaville 3 1A Smelterville
7 1A Kingston 12 1B Wallace
26 1C Lane 2 1A Wardner
24 1C Lookout Pass
18 1B Mullan HQ 1A St. Maries
23 1C Murray 49 1E Avery
7 1A Osburn 27 1C Calder
4 1A Page 13 1B Harrison
5 1A Pinehurst 16 1B St. Joe

1-7 05/09
COLVILLE AREA - G50

Miles Zone Miles Zone


From Subzone From Subzone
HQ 1A Colville 14 1B Marcus
15 1B Addy 15 1B North Basin
6 1A Arden 35 1D Northport
25 1C Barstow 10 1A Onion Creek
18 1B Blue Creek 31 1D Orient
25 1C Bissell Lake 4 1A Orin
22 1C Bossburg 18 1B Pleasant Valley
20 1B Boyds 26 1C Rice
31 1D Daisy 12 1B Summit Valley
33 1D Deep Lake 8 1A Tiger Highway
6 1A Finley Gulch 45 1E Twin Lakes
35 1D Gifford
8 1A Greenwood
38 1D Inchelium 24 1C Chewelah
20 1C Kelly Hill 2 1A Burnt Valley
9 1A Kettle Falls 18 1B Deer Creek
47 1E Kewa 6 1A Grouse Creek
42 1E Laurier 2 1A Sand Canyon
27 1C Marble 10 1A Waitts Lake

1-8 05/09
LEWIS-CLARK AREA - D53

Miles Zone Miles Zone


From Subzone From Subzone
IDAHO
HQ 1A Clarkston 20 1C Stites
26 1C Culdesac 41 1E Winchester
13 1B Lapwai
2 1A Lewiston THQ 5A Elk City
45 1E Orofino 19 5B Fall Creek
19 5B Red River
HQ 1A Grangeville
15 1B Cottonwood THQ 5A Orofino
33 1D Craigmont 9 3A Greer
8 1A Denver 52 3E Headquarters
61 1F Elk City 39 3D Pierce
48 1E Fall Creek 26 3C Weippe
24 1C Ferdinand
7 1A Fern WASH
27 1C Kamiah HQ 1A Clarkston
25 1C Kooskia 6 1A Asotin
32 1D Nez Perce 8 1A Silcott
46 1E Reubens 3 1A Wilma

1-9 05/09
OTHELLO - H50 / DAVENPORT - P50 AREA

Miles Zone Miles Zone


From Subzone From Subzone
HQ 1A Othello 37 1D Hunters
36 1D Lind 28 1C Little Falls
41 1E Lotus 28 1C Long Lake
48 1E Ritzville 38 1D Odessa
24 1C Roxboro 13 1B Reardan
32 1D Schrag 62 — RIT (See Oth.)
10 1A Taunton 38 1D Sprague
16 1B Warden 46 1E Springdale
41 1E Washtucna 41 1E Tumtum
25 1C Waukon
HQ 1A Davenport 33 1D Wellpinit
41 1E Almira 30 1C Wilbur
21 1C Creston
23 1C Edwall Ritzville (HQ
30 1C Enterprise THQ 4A Oth. or Dav.)
35 1D Ford 16 4B Lind
33 1D Fruitland 31 4C Odessa
36 1D Govan 24 4C Sprague
14 1B Harrington 28 4C Washtucna

1-10 05/09
PULLMAN AREA - B53

Miles Zone Miles Zone


From Subzone From Subzone
IDAHO
HQ 1A Pull Serv. Cntr. 65 1F Fairfield
40 1D Bovill 34 1D Farmington
30 1C Deary 31 1D Garfield
59 1F Elk River 14 1B Johnson
21 1C Genesee 47 1E Lacrosse
28 1C Harvard 55 1E Latah
34 1D Helmer 45 1E Malden
10 1A Joel 37 1D Oakesdale
35 1D Juliaetta 20 1B Palouse
31 1D Kendrick 48 1E Pine City
4 1A Moscow 44 1D Plaza
22 1C Onaway 71 1F Rockford
24 1C Potlatch 40 1D Rosalia
23 1C Princeton 55 1E Spangle
18 1B Troy 45 1E Spring Valley
13 1B Viola 45 1E St. John
30 1D Steptoe
WASH 43 1E Sunset
HQ 1A Pull Serv. Cntr. 50 1E Tekoa
11 1B Albion 31 1D Thera
20 1B Colfax 35 1D Thornton
16 1B Colton 19 1B Uniontown
28 1C Diamond 50 1E Waverly
38 1D Endicott 22 1C Wawawai
52 1F Ewan 44 1D Winona

1-11 05/09
Schedule 51 Costs
WASHINGTON
The costs on this page are published in Schedule 51 and must be used
whenever they fit the situation. They are applicable to all single-phase
extensions in the company’s service territory and to all single-phase
customers up to 72,000 kWh per year.

NOTES: These are the only costs published in the tariff.


Do not apply zone multipliers to the costs on this page.

Design Fee (for each design after the first and for all $100 per
large or complex jobs) design

Tariffed Construction Costs


Type Facility Fixed Cost Variable Cost
OH Primary $3774 + $4.04 per foot
OH Secondary $253 + $4.23 per foot
OH Service $253 + $4.23 per foot
OH Transformer $1173 per xfmr

UG Primary $1384 + $8.45 per foot


UG Secondary $199 + $6.80 per foot
UG Service $199 + $6.80 per foot
UG Transformer $1659 per xfmr

DEVEL ALL $1701 per lot


Tariffed Allowances (see Page 2-5)
New Load Allowances
Temporary $0 per customer
0 to 4800 kWH Per Year $0 per customer
Mobile Home Not On An Improved Lot $0 per customer
With 4800 to 72,000 kWH/Year:
Schedule 1
Single Family Residence $1000 per customer
Duplex Residence $800 per living unit
Multiple Family Residence $600 per living unit
Schedule 11 or 12 $1300 per customer
Development Costs
Advance Payment, Credit Instrument or
Promissory Note (up to 175 ft. frontage) $1701 per lot
Cost Reductions for Work by Developer $522 Maximum per lot
Advance Payment with Maximum Cost Reduction $1179 per lot
Maximum Allowable Refund $1179 per lot
Builder Charge for Service Installation $766 per lot

2-1 WASHINGTON 05/09


General Comments on Schedule 51

The tariff covers all distribution construction in the company including


single-phase, three-phase, large and small loads, conversions from
overhead to underground, and relocations of either overhead or underground
primary or services.

The only costs in the tariff are for single-phase loads.

Other costs can be estimated from a layout of the extension or using the
average costs of construction on the following pages.

Additional information and examples are available in the Electric Line


Extension Practices manual and from the Distribution Engineering
Supervisor.

IPUC and WUTC

If the customer disagrees with your interpretation of Schedule 51 and you


have confirmed that interpretation with others in the company, you should
refer the customer to the appropriate commission.

IPUC (208) 334-0300

WUTC 1-800-562-6150

Zone Multipliers

Do not apply zone multipliers to the single-phase extension costs


published in the tariff. Those extension costs are already weighted for the zones
in which construction activity has been occurring.

However, if you use other average costs in Section 2 of the Distribution


Estimating Book, multiply by the appropriate zone multiplier below to
estimate the on-site cost.

These multipliers are averages for all normal construction including


Exceptional Costs.

Zone Multipliers for (Non-Tariffed) New OH and UG Construction

1A ….. 1.00 1C ….. 1.20 1E ….. 1.45


1B ….. 1.10 1D ….. 1.30 1F ….. 1.55

2-2 WASHINGTON 05/09


Overhead Primary Construction Costs

Average installed costs through 2/0 ACSR with dirt holes. See zone multipliers
on page 2-2.

Phases Fixed Cost Variable Cost


2 & Nt $5185 + $4.59 per foot
3 & Nt $5706 + $5.27 per foot

Add Phases To Existing Pole Line


Average costs through 2/0 ACSR. Includes crossarms but no new poles and
no hot work (see Exceptional Costs). Fixed Cost is for circuit only.

Wire Added Fixed Cost Variable Cost


3rd $806 + $1.05 per foot
4th $209 + $0.69 per foot
3rd & 4th $1095 + $1.60 per foot

If a transformer bank will be modified in the section where wire will be added,
add $523 for mounting bracket, cutout and lightning arrester for each
transformer added.

Underground Primary Construction Costs

Average installed costs for #1 or 1/0 ALCN in dirt. Variable cost includes
cable, ditch and conduit (CDT). Cost of PLOWing is assumed to be $2.50
per foot. See zone multipliers on page 2-2.

Variable Cost
Phases Fixed Cost CDT DB Plow
2 $2187 + $13.45 $10.75 $7.35 per foot
3 $2066 + $16.88 $13.15 $9.75 per foot

Cable Pulls: Use the following guideline for cable pulls in conduit. Count one
setup for every transformer and junction enclosure; and one pull for every cable
leaving the setup location.
SETUP: 1/2 man-hour
EACH PULL: 1 man-hour per cable

Note: The fixed costs are nearly the same because more materials are
provided by Avista Utilities at the load end of the 2-phase extension (i.e. 2 pads,
2 ground sleeves & 2 grounds vs. 1 ground sleeve & 1 ground). The 3-phase
concrete pad is normally provided by the customer.

2-3 WASHINGTON 05/09


Overhead Service Construction Costs

Use zone multipliers on page 2-2.

Type Source Fixed Cost Variable Cost


Parallel TX OH $126 + $6.28 per foot
QX OH $273 + $6.76 per foot
Parallel QX OH $292 + $11.64 per foot

Underground Service Construction Costs

Use zone multipliers on page 2-2.

Variable Cost
Type Source Fixed Cost DB CDT
Parallel TXUG UG $298 + $8.24 $11.06 per foot
QXUG UG $255 + $7.48 $10.30 per foot
Parallel QXUG UG $397 + $10.77 $13.59 per foot

Street Lights

Use the following cost for the Exceptional Cost for developer-contributed
street light standards. They cover the difference between the installed cost
of a wood pole and the installed cost of a metal standard with base and
grounding.

DIRECT-BURIED STEEL $1074 per standard


PEDESTAL-BASE FBRGLS GREEN $1628 per standard
PEDESTAL-BASE LONG STEEL $1726 per standard
PEDESTAL-BASE SHORT STEEL $1604 per standard

Monthly rates cover the cost of installation and maintenance of the street
light. The rates do not include ditch or conduit. If the street lights are
requested after the ditch is closed, the customer is responsible for the
cost of trenching. If conduit is required, the customer is responsible for the
cost of conduit.

2-4 WASHINGTON 05/09


Cost Reductions (System Average)

All Cost Reductions allow for inspection by Avista Utilities. Cost Reductions are
based on costs used to develop the tariffed costs. Use local bids or zone multipliers
to adjust for distance from headquarters.

For Individual Customers and Backbones:

FOR: SUBTRACT:
Plowed installation of cable* $2.46 per foot
Service ditch by customer $3.64 per foot
Primary ditch by customer $4.31 per foot
Conduit by customer (2 in.) $1.08 per foot
Avista ditch; Joint with Gas $2.01 per foot

*NOTE: Enter the cost reduction for plowing (credit) under


Exceptional Costs on the Construction Contributions page of the
Electric Service Agreement form. (See pages 3-12 and 3-13 in the
Electric Line Extension Practices manual).

For Developments:

Maximum Cost Reduction shall not exceed $522 per lot or the values below,
whichever is less.

FOR: SUBTRACT:
Ditch by Developer $522 per lot

Avista Utilities Ditch:


Conduit by Developer -- Primary $92 per lot
-- Secondary $15 per lot
Avista Utilities Ditch; Joint with Gas $173 per lot

Allowances For Large Customers


When the customer’s usage is expected to exceed 72,000 kWh per year, multiply
the expected annual usage by the appropriate factor in the following table to find the
customer’s allowance. Determine the usage from similar buildings and industries or
customer histories.
Allowance Factor
Schedule Load WA
11 or 12 General 0.09313 x kWh
21 or 22 Large General 0.04295 x kWh
31 or 32 Pumping 0.06858 x kWh
25 Extra Large General Contact Rates & Tariffs

2-5 WASHINGTON 05/09


*Exceptional/Customer-Requested Costs

Use zone multipliers on page 2-2 for items on this page.


Clearing: Light $0.35 per foot
Medium $0.70 per foot
Medium w/Cleanup $1.05 per foot
Heavy w/Cleanup $1.40 per foot
Pole Haul in Rock 30 to 55 ft. Poles $540 per pole
or Frozen Ground: 60 to 70 ft. Poles $695 per pole
Ditch Adders: Dirt Loose Rock
24 in. 0 $2.90 per foot
30 in. 0 $4.11 per foot
36 in. $0.94 $5.72 per foot
42 in. $1.90 $7.32 per foot
Cable Burial Costs: Fixed Variable
Cut & Replace Asphalt $325 + $9.09 per sq foot
Cut & Replace Concrete $662 minimum
(4 in. thick) $88 per sq yard
Boring with Conduit (1-3 phases) $20 per foot
Compaction: 90% $2.52 per foot
95% $6.05 per foot
Sandpadding $0.71 per foot
Temporary Transformer (Overhead) $559 each
Temporary Transformer (Underground) $612 each
Service Costs (N2): Fixed Variable
Reconnect OH Service $52 each
Reconnect UG Service $70 each
Temp Service 100 ft or shorter $90 each
Temp Service over 100 ft long $10.55 + $0.80 per foot
Long Ladder Jobs $401 each
UG Service in OH Area: Fixed DB in CDT
TXUG $210 $1.98 $3.17
Parallel TXUG $514 $1.96 $4.78
QXUG $422 0.95 $2.14
Parallel QXUG $653 --- $2.42
Extra Junction Enclosure: New Line Existing Line
JE1 $1211 $1682 each
JE2 $1916 $2809 each
JE3 $2664 $3978 each
Submersible Enclosures (Add to JE Cost):
SE1 $2422 extra each
SE2 $3177 extra each
SE3 $2933 extra each

2-6 WASHINGTON 05/09


*Exceptional/Customer-Requested Costs (continued)

Do not use zone multipliers for items on this page.

Rights of Way: (Contact Real Estate for more information).


On Private Property $Variable per structure/acre
On Public R/W $Variable Franchise Fee
Highway Crossing $150 to $500 per crossing
BNSF Crossing $2750 to $3750 per crossing
UPRR Crossing $1,500 per crossing
DNR Crossing/State Parks $1,500 administrative fee
DNR Crossing (variable) + 150% of land value easement fee
Overtime Rates: (N3)
1A $66.58 per manhour
1B $73.24 per manhour
1C $79.90 per manhour
1D $86.55 per manhour
1E $96.54 per manhour
1F $106.53 per manhour

Notes:

N1. Use local bids when possible.

N2. The reconnection costs that are shown apply to services disconnected
at customer’s request. If service was disconnected by Avista Utilities
because customer failed to comply with the company’s rules and
regulations (Schedule 70 Rule 14), the reconnection charge is $16.00
during working hours and $32.00 on overtime.

The rates for temporary service allow for labor and materials that cannot
be used for the permanent service.

N3. If the customer requests that work be performed before or after normal
company work hours, charge an Exceptional Cost based on the rate for
the work zone and the overtime manhours. The values in the table are
estimates.

N4. The “Ditch Adders” do not include conduit, sandpadding, compaction, etc.
Add the appropriate costs from the “Cable Burial Costs”.

2-7 WASHINGTON 05/09


Overhead Primary Removal Costs

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost

Phase Fixed Variable


1 $555 + $0.39 per circuit foot
2 $887 + $0.44 per circuit foot
3 $963 + $0.47 per circuit foot

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value

Phase Fixed Variable


1 $290 + $0.136 per circuit foot
2 $748 + $0.312 per circuit foot
3 $1125 + $0.393 per circuit foot

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.

2005 ….. 0.65 1990 ….. 0.30 1975 ….. 0.05


2000 ….. 0.45 1985 ….. 0.20 1970 ….. 0.00
1995 ….. 0.40 1980 ….. 0.10 1965 ….. 0.00

Example
A customer requests removal of a 1973 three-span tap (600 feet) of single-
phase line on his property. His cost will be Removal less Salvage plus
Remaining Value. The zone is 1C.

Removal (555 +(0.39 x 600)) x 1.40 $1105


Salvage -0-
Remaining Value:
New cost (pg 2-1) 3774 + (4.04 x 600) $6198
Rem value factor 0.05 x 0.05 _310_

Termination Cost $1415

Note: If the tap is greater than 10 years old, the salvage value is zero.

2-8 WASHINGTON 05/09


Underground Primary Removal Costs

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost
Variable
Phase Fixed DB CDT
1 $59 + $0.014 $0.15 per circuit foot
2 $111 + $0.014 $0.29 per circuit foot
3 $106 + $0.014 $0.42 per circuit foot

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value

Phase Fixed Variable


1 $352 + $0.175 per circuit foot
2 $663 + $0.039 per circuit foot
3 $332 + $0.039 per circuit foot

Remaining Value (Original Cost Depreciated)


Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.

2005 ….. 0.65 1990 ….. 0.30 1975 ….. 0.05


2000 ….. 0.45 1985 ….. 0.20 1970 ….. 0.00
1995 ….. 0.40 1980 ….. 0.10 1965 ….. 0.00

Example
A customer requests removal of a 2000 750-foot three-phase conduited UG tap
on his property. His cost will be Removal less Salvage plus Remaining Value.
The zone is 1B.

Removal (106 + (0.42 x 750)) x 1.20 $505


Salvage 332 + (0.039 x 750) -361
Remaining Value:
New cost (pg 2-3) (2066 + (16.88 x 750)) x 1.10 $16,199
Rem value factor 0.45 x 0.45 7290

Termination Cost $7434

Note: If the tap is greater than 10 years old, the salvage value is zero.

2-9 WASHINGTON 05/09


Overhead Service Removal Costs

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost

Type Average
TX $129 per service
Parallel TX $225 per service
QX $116 per service
Parallel QX $197 per service

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.85
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value

Type Average
TX $25 per service
Parallel TX $28 per service
QX $32 per service
Parallel QX $42 per service

Remaining Value (Original Cost Depreciated)

Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.

2005 ….. 0.65 1990 ….. 0.30 1975 ….. 0.05


2000 ….. 0.45 1985 ….. 0.20 1970 ….. 0.00
1995 ….. 0.40 1980 ….. 0.10 1965 ….. 0.00

2-10 WASHINGTON 05/09


Underground Service in Underground Area
Removal Costs

For removal of an underground service in an overhead area, see page 2-12.

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost
Average
Type DB CDT
TXUG $3 $60 per service
Parallel TXUG $5 $120 per service
QXUG $3 $61 per service
Parallel QXUG $7 $122 per service

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value
Average
Type DB CDT
TXUG $0 $1 per service
Parallel TXUG $0 $2 per service
QXUG $0 $5 per service
Parallel QXUG $0 $9 per service

Remaining Value (Original Cost Depreciated)

Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.

2005 ….. 0.65 1990 ….. 0.30 1975 ….. 0.05


2000 ….. 0.45 1985 ….. 0.20 1970 ….. 0.00
1995 ….. 0.40 1980 ….. 0.10 1965 ….. 0.00

2-11 WASHINGTON 05/09


Underground Service in Overhead Area
Removal Costs

For removal of an underground service in an underground area, see page 2-11.

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost
Average
Type DB CDT
TXUG $49 $106 per service
Parallel TXUG $98 $213 per service
QXUG $51 $108 per service
Parallel QXUG $101 $216 per service

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value
The DB salvage is for the riser.
Average
Type DB CDT
TXUG $52 $53 per service
Parallel TXUG $104 $106 per service
QXUG $52 $53 per service
Parallel QXUG $104 $106 per service

Remaining Value (Original Cost Depreciated)

Multiply the present new installed cost by the factor below for the closest year of
installation. Inflation and depreciation are combined in one step. Use the zone
multipliers on page 2-2.

2005 ….. 0.65 1990 ….. 0.30 1975 ….. 0.05


2000 ….. 0.45 1985 ….. 0.20 1970 ….. 0.00
1995 ….. 0.40 1980 ….. 0.10 1965 ….. 0.00

2-12 WASHINGTON 05/09


Overhead Extensions
Longer than 1500 Feet
Washington

Charge an Exceptional Cost for the overhead primary length in excess of 1500 feet.

EXAMPLE
A customer requests a 2350-foot single-phase extension. The line will be overhead
with an overhead service. Do a layout and estimate the cost of construction of the
primary for the appropriate construction Zone.

Service Transf Primary TOTAL


2 BASIC COST 40 FT 15 Kva 2310 FT
b Variable 169 9332 9501
c Fixed 253 1173 3774 5200
3 GROSS BASIC COST 422 1173 13,106 14,701
4 ALLOWANCE (422) (578) 0 (1000)
5 NET BASIC COST 595 13,106 13,701
6 EXCEPTIONAL COST
f Long OH 405 405
7 TOTAL CONSTRUCTION 14,106

14 NOTES:

Estimated Cost = $14,250 ÷ 2310 ft = $6.17 per foot


(from layout)
Primary Tariffed Cost = $13,106 ÷ 2310 ft = $5.67 per foot
Cost Difference $0.50 per foot

Exceptional Cost = (2310 ft -1500 ft) x ($6.17/ft - $5.67/ft)

= 810 ft x $0.50/ft

= $405

For more information, see the Electric Line Extension Practices manual..

2-13 WASHINGTON 05/09


Schedule 51 Costs
IDAHO
The costs on this page are published in Schedule 51 and must be used
whenever they fit the situation. They are applicable to all single-phase
extensions in the company’s service territory. Three-phase primary costs
are also published in Schedule 51 and are shown on page 2-3.

NOTES: These are the only costs published in the tariff.


Do not apply zone multipliers to the costs on this page.

Design Fee (for each design after the first and for all $185 per
large or complex jobs) design

Tariffed Construction Costs


Type Facility Fixed Cost Variable Cost
OH Primary $3774 + $4.04 per foot
OH Secondary $253 + $4.23 per foot
OH Service $253 + $4.23 per foot
OH Transformer $1173 per xfmr

UG Primary $1384 + $8.45 per foot


UG Secondary $199 + $6.80 per foot
UG Service $199 + $6.80 per foot
UG Transformer $1659 per xfmr

DEVEL ALL $1701 (Excludes service costs) per lot


Tariffed Allowances (see Page 2-5)
New Load Allowances
Temporary $0 per customer
0 to 2500 kWH Per Year $0 per customer
Mobile Home Not On An Improved Lot $0 per customer
With at least 2500 kWH/Year:
Schedule 1
Single Family Residence $1000 per customer
Duplex Residence $800 per living unit
Multiple Family Residence $600 per living unit
All other Schedules refer to page 2-5
Development Costs
Advance Payment, Credit Instrument or
Promissory Note (up to 175 ft. frontage) $1701 per lot
Cost Reductions for Work by Developer $522 Maximum per lot
Advance Payment with Maximum Cost Reduction $1179 per lot
Maximum Allowable Refund $1179 per lot
Builder Charge for Service Installation $766 per lot

2-1 IDAHO 05/09


General Comments on Schedule 51

The tariff covers all distribution construction in the company including


single-phase, three-phase, large and small loads, conversions from
overhead to underground, and relocations of either overhead or underground
primary or services.

The only costs in the Idaho tariff are for single-phase and three-phase loads.

Other costs can be estimated from a layout of the extension or using the
average costs of construction on the following pages.

Additional information and examples are available in the Electric Line


Extension Practices manual and from the Distribution Engineering
Supervisor.

IPUC and WUTC

If the customer disagrees with your interpretation of Schedule 51 and you


have confirmed that interpretation with others in the company, you should
refer the customer to the appropriate commission.

IPUC (208) 334-0300

WUTC 1-800-562-6150

Zone Multipliers

Do not apply zone multipliers to the single-phase extension costs


published in the tariff. Those extension costs are already weighted for the zones
in which construction activity has been occurring.

However, if you use other average costs in Section 2 of the Distribution


Estimating Book, multiply by the appropriate zone multiplier below to
estimate the on-site cost.

These multipliers are averages for all normal construction including


Exceptional Costs.

Zone Multipliers for (Non-Tariffed) New OH and UG Construction

1A ….. 1.00 1C ….. 1.20 1E ….. 1.45


1B ….. 1.10 1D ….. 1.30 1F ….. 1.55

2-2 IDAHO 05/09


Overhead Primary Construction Costs
Average installed costs through 2/0 ACSR with dirt holes. See zone multipliers
on page 2-2.
Phases Fixed Cost Variable Cost
2 & Nt $5185 + $4.59 per foot
*3 & Nt $5706 + $5.27 per foot

Add Phases To Existing Pole Line


Average costs through 2/0 ACSR. Includes crossarms but no new poles and
no hot work (see Exceptional Costs). Fixed Cost is for circuit only.
Wire Added Fixed Cost Variable Cost
3rd $806 + $1.05 per foot
4th $209 + $0.69 per foot
3rd & 4th $1095 + $1.60 per foot

If a transformer bank will be modified in the section where wire will be added,
add $523 for mounting bracket, cutout and lightning arrester for each
transformer added.

Underground Primary Construction Costs


Average installed costs for #1 or 1/0 ALCN in dirt. Variable cost includes
cable, ditch and conduit (CDT). Cost of PLOWing is assumed to be $2.50
per foot. See zone multipliers on page 2-2.
Variable Cost
Phases Fixed Cost CDT DB Plow
2 $2187 + $13.45 $10.75 $7.35 per foot
*3 $2066 + $16.88 $13.15 $9.75 per foot

Cable Pulls: Use the following guideline for cable pulls in conduit. Count one
setup for every transformer and junction enclosure; and one pull for every cable
leaving the setup location.
SETUP: 1/2 man-hour
EACH PULL: 1 man-hour per cable

Note: The fixed costs are nearly the same because more materials are
provided by Avista Utilities at the load end of the 2-phase extension (i.e. 2 pads,
2 ground sleeves & 2 grounds vs. 1 ground sleeve & 1 ground). The 3-phase
concrete pad is normally provided by the customer.

*The costs as disclosed in the tariff are done as general guidelines for
3-phase costs to meet commission requirements. These do not represent
all of the 2-phase and 3-phase configuration options. If the actual line
extension configuration is different than those that are associated with the
3-phase costs that are in the tariff, use the appropriate costs with the actual
method of construction as shown above.

2-3 IDAHO 05/09


Overhead Service Construction Costs

Use zone multipliers on page 2-2.

Type Source Fixed Cost Variable Cost


Parallel TX OH $126 + $6.28 per foot
QX OH $273 + $6.76 per foot
Parallel QX OH $292 + $11.64 per foot

Underground Service Construction Costs

Use zone multipliers on page 2-2.

Variable Cost
Type Source Fixed Cost DB CDT
Parallel TXUG UG $298 + $8.24 $11.06 per foot
QXUG UG $255 + $7.48 $10.30 per foot
Parallel QXUG UG $397 + $10.77 $13.59 per foot

Street Lights

Use the following cost for the Exceptional Cost for developer-contributed
street light standards. They cover the difference between the installed cost
of a wood pole and the installed cost of a metal standard with base and
grounding.

DIRECT-BURIED STEEL $1074 per standard


PEDESTAL-BASE FBRGLS GREEN $1628 per standard
PEDESTAL-BASE LONG STEEL $1726 per standard
PEDESTAL-BASE SHORT STEEL $1604 per standard

Monthly rates cover the cost of installation and maintenance of the street
light. The rates do not include ditch or conduit. If the street lights are
requested after the ditch is closed, the customer is responsible for the
cost of trenching. If conduit is required, the customer is responsible for the
cost of conduit.

2-4 IDAHO 05/09


Cost Reductions (System Average)

All Cost Reductions allow for inspection by Avista Utilities. Cost Reductions are
based on costs used to develop the tariffed costs. Use local bids or zone multipliers
to adjust for distance from headquarters.

For Individual Customers and Backbones:

FOR: SUBTRACT:
Plowed installation of cable* $2.46 per foot
Service ditch by customer $3.64 per foot
Primary ditch by customer $4.31 per foot
Conduit by customer (2 in.) $1.08 per foot
Avista ditch; Joint with Gas $2.01 per foot

*NOTE: Enter the cost reduction for plowing (credit) under


Exceptional Costs on the Construction Contributions page of the
Electric Service Agreement form. (See pages 3-12 and 3-13 in the
Electric Line Extension Practices manual).

For Developments:

Maximum Cost Reduction shall not exceed $522 per lot or the values below,
whichever is less.

FOR: SUBTRACT:
Ditch by Developer $522 per lot

Avista Utilities Ditch:


Conduit by Developer -- Primary $92 per lot
-- Secondary $15 per lot
Avista Utilities Ditch; Joint with Gas $173 per lot

Allowances For Large Customers


Multiply the expected annual usage by the appropriate factor in the following table to
find the customer’s allowance. For Idaho customers, use this table for all
commercial and industrial customers, regardless of usage. Determine the usage
from similar buildings and industries or customer histories.
Allowance Factor
Schedule Load ID
11 or 12 General 0.10703 x kWh
21 or 22 Large General 0.06000 x kWh
31 or 32 Pumping 0.06000 x kWh
25 Extra Large General Contact Rates & Tariffs

2-5 IDAHO 05/09


*Exceptional/Customer-Requested Costs

Use zone multipliers on page 2-2 for items on this page.


Clearing: Light $0.35 per foot
Medium $0.70 per foot
Medium w/Cleanup $1.05 per foot
Heavy w/Cleanup $1.40 per foot
Pole Haul in Rock 30 to 55 ft. Poles $540 per pole
or Frozen Ground: 60 to 70 ft. Poles $695 per pole
Ditch Adders: Dirt Loose Rock
24 in. 0 $2.90 per foot
30 in. 0 $4.11 per foot
36 in. $0.94 $5.72 per foot
42 in. $1.90 $7.32 per foot
Cable Burial Costs: Fixed Variable
Cut & Replace Asphalt $425 + $10.64 per sq foot
Cut & Replace Concrete $662 minimum
(4 in. thick) $88 per sq yard
Boring with Conduit (1-3 phases) $20 per foot
Compaction: 90% $2.52 per foot
95% $6.05 per foot
Sandpadding $0.71 per foot
Temporary Transformer (Overhead) $559 each
Temporary Transformer (Underground) $612 each
Service Costs (N2): Fixed Variable
Reconnect OH Service $52 each
Reconnect UG Service $70 each
Temp Service 100 ft or shorter $90 each
Temp Service over 100 ft long $10.55 + $0.80 per foot
Long Ladder Jobs $401 each
UG Service in OH Area: Fixed DB in CDT
TXUG $210 $1.98 $3.17
Parallel TXUG $514 $1.96 $4.78
QXUG $422 0.95 $2.14
Parallel QXUG $653 --- $2.42
Extra Junction Enclosure: New Line Existing Line
JE1 $1211 $1682 each
JE2 $1916 $2809 each
JE3 $2664 $3978 each
Submersible Enclosures (Add to JE Cost):
SE1 $2422 extra each
SE2 $3177 extra each
SE3 $2933 extra each

2-6 IDAHO 05/09


*Exceptional/Customer-Requested Costs (continued)

Do not use zone multipliers for items on this page.

Rights of Way: (Contact Real Estate for more information).


On Private Property $Variable per structure/acre
On Public R/W $Variable Franchise Fee
Highway Crossing $150 to $500 per crossing
BNSF Crossing $2750 to $3750 per crossing
UPRR Crossing $1,500 per crossing
DNR Crossing/State Parks $1,500 administrative fee
DNR Crossing (variable) + 150% of land value easement fee
Overtime Rates: (N3)
1A $66.58 per manhour
1B $73.24 per manhour
1C $79.90 per manhour
1D $86.55 per manhour
1E $96.54 per manhour
1F $106.53 per manhour

Notes:
N1. In Idaho exceptional costs may be covered in whole or part by any
remaining allowance.

N2. Use local bids when possible.

N3. The rates for temporary service allow for labor and materials that cannot
be used for the permanent service.

N4. If the customer requests that work be performed before or after normal
company work hours, charge an Exceptional Cost based on the rate
for the work zone and the overtime manhours. The values in the table
are estimates.

N5. The “Ditch Adders” do not include conduit, sandpadding, compaction,


etc. Add the appropriate costs from the “Cable Burial Costs”.

* Exceptional Cost is the cost of labor and/or materials which are


necessary to construct the Line Extension, but which are not reflected in
the Basic Cost. In Idaho, Exceptional Costs may be covered in whole or
in part by any remaining allowance. Customer-Requested Cost is the
cost of unusual labor and/or materials which is requested by the
customer but which is not necessary to construct the Line Extension
based on the company’s minimum design, construction and operating
practices. All Customer-Requested Costs must be paid in full by the
customer, regardless of the allowance.

2-7 IDAHO 05/09


Overhead Primary Removal Costs

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost

Phase Fixed Variable


1 $555 + $0.39 per circuit foot
2 $887 + $0.44 per circuit foot
3 $963 + $0.47 per circuit foot

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value

Phase Fixed Variable


1 $290 + $0.136 per circuit foot
2 $748 + $0.312 per circuit foot
3 $1125 + $0.393 per circuit foot

Example
A customer requests removal of a 2001 three-span tap (600 feet) of single-
phase line on his property. His cost will be Removal less Salvage.
The zone is 1C.

Removal (555 +(0.39 x 600)) x 1.40 $1105


Salvage 290 + (0.136 x 600) -372

Termination Cost $733

Note: If the tap is greater than 10 years old, the salvage value is zero.

Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-8 IDAHO 05/09


Underground Primary Removal Costs

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost
Variable
Phase Fixed DB CDT
1 $59 + $0.014 $0.15 per circuit foot
2 $111 + $0.014 $0.29 per circuit foot
3 $106 + $0.014 $0.42 per circuit foot

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value

Phase Fixed Variable


1 $352 + $0.175 per circuit foot
2 $663 + $0.039 per circuit foot
3 $332 + $0.039 per circuit foot

Example
A customer requests removal of a 2001 750-foot three-phase conduited UG tap
on his property. His cost will be Removal less Salvage.
The zone is 1B.

Removal (106 + (0.42 x 750)) x 1.20 $505


Salvage 332 + (0.039 x 750) -361

Termination Cost $144

Note: If the tap is greater than 10 years old, the salvage value is zero.

Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-9 IDAHO 05/09


Overhead Service Removal Costs

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost

Type Average
TX $129 per service
Parallel TX $225 per service
QX $116 per service
Parallel QX $197 per service

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value

Type Average
TX $25 per service
Parallel TX $28 per service
QX $32 per service
Parallel QX $42 per service

Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-10 IDAHO 05/09


Underground Service in Underground Area
Removal Costs

For removal of an underground service in an overhead area, see page 2-12.

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost
Average
Type DB CDT
TXUG $3 $60 per service
Parallel TXUG $5 $120 per service
QXUG $3 $61 per service
Parallel QXUG $7 $122 per service

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value
Average
Type DB CDT
TXUG $0 $1 per service
Parallel TXUG $0 $2 per service
QXUG $0 $5 per service
Parallel QXUG $0 $9 per service

Note: There is no longer a remaining value charged in Idaho. Please see


Tariff, page 51L for revised conversion/relocation formula.

2-11 IDAHO 05/09


Underground Service in Overhead Area
Removal Costs

For removal of an underground service in an underground area, see page 2-11.

The cost of terminating a facility may be estimated since it is not specified in


Schedule 51.

Removal Cost
Average
Type DB CDT
TXUG $49 $106 per service
Parallel TXUG $98 $213 per service
QXUG $51 $108 per service
Parallel QXUG $101 $216 per service

Apply the following zone multipliers to removal costs:


1A ….. 1.00 1C ….. 1.40 1E ….. 1.80
1B ….. 1.20 1D ….. 1.60 1F ….. 2.10

Salvage Value
The DB salvage is for the riser.
Average
Type DB CDT
TXUG $52 $53 per service
Parallel TXUG $104 $106 per service
QXUG $52 $53 per service
Parallel QXUG $104 $106 per service

Note: There is no longer a remaining value charged in Idaho. Please see Tariff,
page 51L for revised conversion/relocation formula.

2-12 IDAHO 05/09


Overhead Extensions
Longer than 1500 Feet
Idaho

Charge an Exceptional Cost for the overhead primary length in excess of 1500 feet.

EXAMPLE
A customer requests a 2350-foot single-phase extension. The line will be overhead
with an overhead service. Do a layout and estimate the cost of construction of the
primary for the appropriate construction Zone.

Service Transf Primary TOTAL


2 BASIC COST 40 FT 15 Kva 2310 FT
b Variable 169 9332 9501
c Fixed 253 1173 3774 5200
3 GROSS BASIC COST 422 1173 13,106 14,701
4 ALLOWANCE (422) (578) 0 (1000)
5 NET BASIC COST 595 13,106 13,701
6 EXCEPTIONAL COST
f Long OH 316 316
7 TOTAL CONSTRUCTION 14,017

14 NOTES:

Estimated Cost = $14,000 ÷ 2310 ft = $6.06 per foot


(from layout)
Primary Tariffed Cost = $13,106 ÷ 2310 ft = $5.67 per foot
Cost Difference $0.39 per foot

Exceptional Cost = (2310 ft -1500 ft) x ($6.06/ft - $5.67/ft)

= 810 ft x $0.39/ft

= $316

For more information, see the Electric Line Extension Practices manual..

2-13 IDAHO 05/09


TASK NUMBER

(Used with Capital Blanket Project Numbers)

300100 Design and Engineering

107110 Add Overhead Primary Plant

107120 Add Underground Primary Plant

107199 Add Transformer - Materials Only

107200 Add Service Plant

107215 Add Development Joint Service

108000 Remove/Salvage/Retire Old Plant

3-1 05/09
CAPITAL BLANKET PROJECT NUMBERS

Residential Commercial Develop. Street Area


Revenue Revenue Revenue Lights Lights

Blanket ER1000 ER1000 ER1000 ER1004 ER1005

SPOKANE
NW County 95001100 95001101 95001102 95001300 95001370
NW City 95101100 95101101 95101102 95101300 95101370
Deer Park 95201100 95201101 95201102 95201300 95201370
NE County 95301100 95301101 95301102 95301300 95301370
NE City 95401100 95401101 95401102 95401300 95401370
Valley 95501100 95501101 95501102 95501300 95501370
Central 95601100 95601101 95601102 95601300 95601370
Network 95701100 95701101 95701102 95701300 95701370
West Plains 95801100 95801101 95801102 95801300 95801370
SW City 95901100 95901101 95901102 95901300 95901370

CDA 90101100 90101101 90101102 90101300 90101370


Post Falls 90101100 90101101 90101102 90101300 90101370

COLVILLE 96001100 96001101 96001102 96001300 96001370


Chewelah 96101100 96101101 96101102 96101300 96101370
Gifford/ 96301100 96301101 96301102 96301300 96301370
Inchelium 96301100 96301101 96301102 96301300 96301370
Northport 96201100 96201101 96201102 96201300 96201370

KELLOGG 90701100 90701101 90701102 90701300 90701370


St. Maries 90601100 90601101 90601102 90601300 90601370
Wallace 90801100 90801101 90801102 90801300 90801370

LEWIS-CLARK
Clarkston 92201100 92201101 92201102 92201300 92201370
Craigmont 91201100 91201101 91201102 91201300 91201370
Elk City 91501100 91501101 91501102 91501300 91501370
Grangeville 91001100 91001101 91001102 91001300 91001370
Lewiston 93201100 93201101 93201102 93201300 93201370
Moscow 93301100 93301101 93301102 93301300 93301370
Orofino 91301100 91301101 91301102 91301300 91301370
Pierce 91401100 91401101 91401102 91401300 91401370

3-2 05/09
CAPITAL BLANKET PROJECT NUMBERS

UG Dist. Plant Misc. Cust Failed


Cable Replace Requested/ Road Plant/
Replace OH/UG Caused Relocates Storms

Blanket ER2054 ER2055 ER2055 ER2056 ER2059

SPOKANE
NW County 95001330 95001340 95001341 95001350 95001520
NW City 95101330 95101340 95101341 95101350 95101520
Deer Park 95201330 95201340 95201341 95201350 95201520
NE County 95301330 95301340 95301341 95301350 95301520
NE City 95401330 95401340 95401341 95401350 95401520
Valley 95501330 95501340 95501341 95501350 95501520
Central 95601330 95601340 95601341 95601350 95601520
Network 95701330 95701340 95701341 95701350 95701520
West Plains 95801330 95801340 95801341 95801350 95801520
SW City 95901330 95901340 95901341 95901350 95901520

CDA 90101330 90101340 90101341 90101350 90101520


Post Falls 90101330 90101340 90101341 90101350 90101520

COLVILLE 96001330 96001340 96001341 96001350 96001520


Chewelah 96101330 96101340 96101341 96101350 96101520
Gifford/ 96301330 96301340 96301341 96301350 96301520
Inchelium 96301330 96301340 96301341 96301350 96301520
Northport 96201330 96201340 96201341 96201350 96201520

KELLOGG 90701330 90701340 90701341 90701350 90701520


St. Maries 90601330 90601340 90601341 90601350 90601520
Wallace 90801330 90801340 90801341 90801350 90801520

LEWIS-CLARK
Clarkston 92201330 92201340 92201341 92201350 92201520
Craigmont 91201330 91201340 91201341 91201350 91201520
Elk City 91501330 91501340 91501341 91501350 91501520
Grangeville 91001330 91001340 91001341 91001350 91001520
Lewiston 93201330 93201340 93201341 93201350 93201520
Moscow 93301330 93301340 93301341 93301350 93301520
Orofino 91301330 91301340 91301341 91301350 91301520
Pierce 91401330 91401340 91401341 91401350 91401520

3-3 05/09
CAPITAL BLANKET PROJECT NUMBERS

Residential Commercial Develop. Street Area


Revenue Revenue Revenue Lights Lights

Blanket ER1000 ER1000 ER1000 ER1004 ER1005

OTHELLO 97001100 97001101 97001102 97001300 97001370


Davenport 97401100 97401101 97401102 97401300 97401370
Long Lake 97501100 97501101 97501102 97501300 97501370
Odessa/ 97601100 97601101 97601102 97601300 97601370
Wilber 97601100 97601101 97601102 97601300 97601370
Ritzville 97101100 97101101 97101102 97101300 97101370

PALOUSE-WA 92801100 92801101 92801102 92801300 92801370


PALOUSE-ID 93801100 93801101 93801102 93801300 93801370
Colfax 94201100 94201101 94201102 94201300 94201370
Deary 91701100 91701101 91701102 91701300 91701370
Garfield/ 94101100 94101101 94101102 94101300 94101370
Rosalia 94101100 94101101 94101102 94101300 94101370
Genesee-WA 92601100 92601101 92601102 92601300 92601370
Genesee-ID 93601100 93601101 93601102 93601300 93601370
Kamiah 91101100 91101101 91101102 91101300 91101370
Pullman 92301100 92301101 92301102 92301300 92301370
Tekoa-WA 92701100 92701101 92701102 92701300 92701370
Tekoa-ID 93701100 93701101 93701102 93701300 93701370

SANDPOINT-ID 93001100 93001101 93001102 93001300 93001370


Priest River 90501100 90501101 90501102 90501300 90501370
Sandpoint-MT 94001100 94001101 94001102 94001300 94001370

3-4 05/09
CAPITAL BLANKET PROJECT NUMBERS

UG Dist. Plant Misc. Cust Failed


Cable Replace Requested/ Road Plant/
Replace OH/UG Caused Relocates Storms

Blanket ER2054 ER2055 ER2055 ER2056 ER2059

OTHELLO 97001330 97001340 97001341 97001350 97001520


Davenport 97401330 97401340 97401341 97401350 97401520
Long Lake 97501330 97501340 97501341 97501350 97501520
Odessa/ 97601330 97601340 97601341 97601350 97601520
Wilber 97601330 97601340 97601341 97601350 97601520
Ritzville 97101330 97101340 97101341 97101350 97101520

PALOUSE-WA 92801330 92801340 92801341 92801350 92801520


PALOUSE-ID 93801330 93801340 93801341 93801350 93801520
Colfax 94201330 94201340 94201341 94201350 94201520
Deary 91701330 91701340 91701341 91701350 91701520
Garfield/ 94101330 94101340 94101341 94101350 94101520
Rosalia 94101330 94101340 94101341 94101350 94101520
Genesee-WA 92601330 92601340 92601341 92601350 92601520
Genesee-ID 93601330 93601340 93601341 93601350 93601520
Kamiah 91101330 91101340 91101341 91101350 91101520
Pullman 92301330 92301340 92301341 92301350 92301520
Tekoa-WA 92701330 92701340 92701341 92701350 92701520
Tekoa-ID 93701330 93701340 93701341 93701350 93701520

SANDPOINT-ID 93001330 93001340 93001341 93001350 93001520


Priest River 90501330 90501340 90501341 90501350 90501520
Sandpoint-MT 94001330 94001340 94001341 94001350 94001520

3-5 05/09
LOCATION NUMBERS
FOR CAPITAL ACCOUNTS

Washington Counties Idaho Counties

Chewelah 961 Coeur d’Alene/Post Falls 901


Clarkston-Lewiston WA 922 Craigmont 912
Colfax 942 Deary 917
Colville 960 Elk City 915
Davenport 974 Genesee-ID 936
Deer Park 952 Grangeville 910
Garfield/Rosalia 941 Kamiah 911
Genesee-WA 926 Kellogg 907
Gifford/Inchelium 963 Clarkston-Lewiston ID 932
Long Lake 975 Pullman-Moscow ID 933
Northport 962 Orofino 913
Odessa/Wilbur 976 Palouse-ID 938
Othello 970 Pierce 914
Palouse-WA 928 Priest River 905
Pullman-Moscow WA 923 Sandpoint-ID 930
Ritzville 971 St. Maries 906
Spokane County NW 950 Tekoa-ID 937
Spokane City NW 951 Wallace 908
Spokane County NE 953
Spokane City NE 954
Spokane County Valley 955
Spokane County Central 956
Spokane Network 957
Spokane County West Plains 958 Montana Counties
Spokane City SW 959
Tekoa-WA 927 Sandpoint-MT 940

General Locations
Washington 028
Idaho 038
Montana 048
Common to Washington/Idaho 098

3-6 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


30P POLE - CEDAR - 30FT IN DIRT 248.45 6.20 886.53
35P POLE - CEDAR - 35FT IN DIRT 312.00 6.20 964.52
40P POLE - CEDAR - 40FT IN DIRT 427.67 6.20 1120.65
45P POLE - CEDAR - 45FT IN DIRT 619.69 6.60 1349.33
50P POLE - CEDAR - 50FT IN DIRT 679.76 6.60 1476.51
55P POLE - CEDAR - 55FT IN DIRT 757.82 7.00 1565.20
60P POLE - CEDAR - 60FT IN DIRT 1060.26 7.00 1965.61
65P POLE - CEDAR - 65FT IN DIRT 1206.59 7.00 2176.29
70P POLE - CEDAR - 70FT IN DIRT 1904.59 7.00 3056.81
75P POLE - CEDAR - 75FT IN DIRT 2201.36 10.10 3675.91
HANDDIG (Additional Manhours) 4.00
HANDSET (Additional Manhours) 10.00
CUT & REPLACE ASPHALT/CONCRETE (Addt'l Manhours) 2.00/5.00
30PR POLE - CEDAR - 30FT IN ROCK 248.45 12.20 1479.20
35PR POLE - CEDAR - 35FT IN ROCK 312.00 12.20 1557.18
40PR POLE - CEDAR - 40FT IN ROCK 427.67 12.20 1713.32
45PR POLE - CEDAR - 45FT IN ROCK 619.69 12.20 1947.27
50PR POLE - CEDAR - 50FT IN ROCK 679.76 12.60 2075.80
55PR POLE - CEDAR - 55FT IN ROCK 757.82 12.60 2167.13
60PR POLE - CEDAR - 60FT IN ROCK 1060.26 14.10 2674.54
65PR POLE - CEDAR - 65FT IN ROCK 1206.59 14.10 2887.86
70PR POLE - CEDAR - 70FT IN ROCK 1904.59 14.10 3770.99
75PR POLE - CEDAR - 75FT IN ROCK 2201.36 15.10 4194.75

14SF/BA POLE STUB - BANDED 14' 29.43 6.20 615.61


16SF/BA POLE STUB - BANDED 16' 29.43 6.20 615.61
SS10 POLE STUB - STEEL FOR 30-35 FOOT POLE 292.11 2.00 515.56
SS10HD POLE STUB - STEEL FOR 40-45 FOOT POLE 308.93 2.00 547.96
SS11HD POLE STUB - STEEL FOR 50-55 FOOT POLE 360.39 2.00 634.42

5FA2P CROSSARM SINGLE FIBERGLASS 5' 2 PHASE 108.52 0.30 163.00


9FHA CROSSARM SINGLE FIBERGLASS 9' HEAVY DUTY 108.12 0.85 210.37
11FHA CROSSARM SINGLE FIBERGLASS 11' HEAVY DUTY 130.78 0.85 283.57

9FDEA-LT CROSSARM DEADEND FIBERGLASS 9' LIGHT 200.44 0.85 327.62


9FDEA-HVY CROSSARM DEADEND FIBERGLASS 9' HEAVY 236.51 0.85 360.70
11FDEA-HVY CROSSARM DEADEND FIBERGLASS 11' HEAVY 313.35 0.85 469.05

5A CROSSARM SINGLE WOOD 5' 28.69 0.85 115.74


5DA CROSSARM DOUBLE WOOD 5' 48.61 1.42 194.00

4-1 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


22HA CROSSARM SINGLE 22' HEAVY DUTY 316.05 1.52 534.62
22HDA CROSSARM DOUBLE 22' HEAVY DUTY 639.12 2.28 1005.68
22STEEL STEEL CROSSARM 22" 62.72 1.64 230.99
16TIMBER TIMBER 16' X 4" X 6" 119.29 0.87 229.42

BB BACKBRACE FOR HD XARM W/EXTENSIONS 150.69 0.50 233.11


W WISHBONE BRACE FOR CROSSARM 23.61 0.85 108.85

PP POLE TOP PIN SINGLE - 13/25kV 8.71 0.32 41.82


PP35 POLE TOP PIN SINGLE - 35kV 10.40 0.32 42.67
DPP POLE TOP PIN DOUBLE - 13kV 16.38 0.32 53.37
DPP35 POLE TOP PIN DOUBLE - 25/35kV 19.80 0.32 55.12

SP STEEL PIN - 13KV FOR STANDARD XARM 3.93 0.13 17.11


SPH STEEL PIN - 13KV FOR HEAVY DUTY XARM 5.45 0.13 18.81
SP25 STEEL PIN - 25KV FOR STANDARD XARM 3.74 0.13 17.04
SP35 STEEL PIN - 25/35KV FOR STNDRD OR HD XARM 12.29 0.13 27.30
SPC STEEL PIN - CORNER 13KV 13.37 0.13 28.68
SPC25 STEEL PIN - CORNER 25KV 14.86 0.13 30.52

PDEHW HARDWARE D.E. PRIMARY-ONE WAY ON POLE 9.23 0.16 26.14


PDEDEHW HARDWARE D.E. PRIMARY-TWO WAY ON POLE 18.46 0.21 42.57
NPDEHW HARDWARE D.E. NEUTRAL-ONE WAY ON POLE 4.02 0.16 19.73
NPDEDEHW HARDWARE D.E. NEUTRAL-TWO WAY ON POLE 8.04 0.21 29.71
DADEHW HARDWARE D.E. ONE WAY ON DBL CROSSARM 2.71 0.16 17.90
DADEDEHW HARDWARE D.E. TWO WAY ON DBL CROSSARM 5.43 0.21 26.07

1RS SEC. RACK 1 SPOOL - SERVICE 4.80 0.50 52.01


1RH SEC. RACK 1 SPOOL WITH EXT, HEAVY DUTY 13.30 0.48 60.90
3R SEC. RACK 3 SPOOL 82.69 0.84 180.83
3RHDEDE SEC. RACK 3 SPOOL DOUBLE DEADEND 165.81 1.12 310.53
3RH SEC. RACK 3 SPOOL HEAVY DUTY 85.69 0.98 198.11
NS NEUTRAL SUPPORT 5.16 0.38 41.80

4-2 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


3/8DGKIT DOWN GUY PREASSEMBLED KIT 3/8" 15KV 89.35 1.85 283.70
3/8DGKIT(2) (2)DOWN GUY PREASSEMBLED KIT 3/8" 15KV 252.93 1.85 485.73
3/8FKIT DOWN GUY PREASSEMBLED KIT 3/8" 25/35KV 101.16 1.85 298.52
3/8FKIT(2) (2)DOWN GUY PREASSEMBLE KIT 3/8" 25/35KV 266.46 1.85 503.47

7/16DGKIT DOWN GUY PREASSEMBLED KIT 7/16" 15KV 177.76 1.85 393.34
7/16DGKIT(2) (2) DOWN GUY PREASSEMBLED KIT 7/16" 15KV 309.78 3.70 729.26
7/16DGKIT-LIGHTDOWN GUY 7/16" (LIGHT) 15KV 124.76 1.85 328.11
7/16FKIT DOWN GUY PREASSEMBLED KIT 7/16" 25/35KV 178.70 1.85 394.52
7/16FKIT(2) (2) DOWN GUY PREASSEMBL KIT 7/16" 25/35KV 301.55 3.70 719.69
7/16DGKITFG DOWN GUY ASMB KIT 7/16" FG DE XARM 15KV 116.18 1.85 316.79
7/16DGKITFG(2) (2)DOWN GUY ASMB KIT 7/16" FG DE ARM 15KV 248.20 3.70 652.71

3/8SG SPAN GUY 3/8'’ 15KV 60.31 2.45 304.16


3/8FSG SPAN GUY 3/8" 25/35KV 91.80 2.45 337.46
7/16SG SPAN GUY 7/16'’ 15KV 96.71 2.45 349.40
7/16FSG SPAN GUY 7/16" 25/35KV 121.43 2.45 380.10
#9IRONSG SPAN GUY #9 IRON 15KV 16.44 2.45 249.93
#6IRONSG SPAN GUY #6 IRON 15KV 55.67 2.45 298.03
6IRONFSG SPAN GUY #6 IRON 25/35KV 82.48 2.45 331.33

3/8SWGKIT SIDEWALK GUY PREASSEMBLED KIT 3/8" 15KV 164.32 3.65 545.74
3/8FSWGKIT SIDEWALK GUY PREASSEMBL KIT 3/8" 25/35KV 176.14 3.65 560.57
PUSHBRACE PUSH BRACE BRACKET 30.00 0.50 83.67

1MR2 ANCHOR MANTA RAY MR-2, 1" X 7' 40K LB 78.02 1.50 236.45
1MR1 ANCHOR MANTA RAY MR-1, 1" X 7' 40K LB 90.71 1.50 252.19
1MRSR ANCHOR MANTA RAY MRSR, 1" X 7' 40K LB 126.07 1.50 296.08

5/8X ANCHOR PLATE 5/8" X 6' X 16" 22.21 3.00 307.46


3/4X ANCHOR PLATE 3/4" X 8' X 20" 32.27 3.00 320.05
3/4E ANCHOR PLATE 3/4" X 8' EXPANDING 7.69 1.50 149.14
1X ANCHOR PLATE 1" X 10' X 24" 64.64 3.00 360.09

5/8R ANCHOR ROCK 5/8" X 6' 18.34 4.40 433.37


1RA ANCHOR ROCK 1" X 10' 38.53 5.86 587.40
1RA53 ANCHOR ROCK 1" X 53" 37.80 5.86 525.96
1RA72 ANCHOR ROCK 1" X 72" 46.11 5.86 536.28
1RA96 ANCHOR ROCK 1" X 96" 54.26 5.86 546.42

1S1 ANCHOR SCREW-1" ROD 1-10" HELIX 48.60 1.50 199.93


1S1-14 ANCHOR SCREW-1" ROD 1-14" HELIX 65.77 1.50 223.27
1SE ANCHOR SCREW EXTENSION ROD 1.5" X 3.5' 29.81 1.50 176.58
1S3 ANCHOR TRIPLE HELIX 129.61 1.50 300.50

4-3 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 364.00 - POLES, TOWERS & FIXTURES


TMHW TRANSF MOUNTING HARDWARE 3-25 kVA 2.66 0.25 26.60
TMHWMED TRANSF MOUNT HARDWARE-MEDIUM 37-50 kVA 3.62 0.25 27.99
TMHWHD TRANSF MOUNTING HARDWARE-HD 75-100 kVA 6.02 0.25 31.16
TMB2 2 TRANSF MOUNTING BRACKET, TO (2) 100 kVA 108.94 0.87 216.15
TMB3 3 TRANSF MOUNTING BRACKET, TO (3) 50 kVA 84.29 0.87 186.40
TMB3HD 3 TRANSF MOUNT BRACKET HD, TO (3) 167 kVA 153.66 0.87 275.08

ALPLTHD PLATFORM, ALUMAFORM 16' 2-POLE HD 2078.78 2.50 2815.95


RR1P REGULATOR RACK 1POLE MOUNT 1PH 15/25KV 1451.20 2.00 1990.15
RS2PHD REG STRUCT 2POLE PLTFRM MNT 3PH 15/25KV 5999.88 12.00 8573.98

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


6CU CONDUCTOR 6 COPPER BARE /1000 FT 319.20 3.40 718.09
4CU CONDUCTOR 4 COPPER BARE /1000 FT 589.68 3.40 1072.70
2CU CONDUCTOR 2 STR. COPPER BARE /1000 FT 878.37 3.40 1438.45

4ACSR CONDUCTOR 4 ACSR /1000 FT 110.00 4.10 527.59


2ACSR CONDUCTOR 2 ACSR /1000 FT 170.00 4.10 593.46
1/0ACSR CONDUCTOR 1/0 ACSR /1000 FT - FOR REPAIR USE 280.00 4.10 729.96
2/0ACSR CONDUCTOR 2/0 ACSR /1000 FT 310.00 4.10 765.60
4/0ACSR CONDUCTOR 4/0 ACSR /1000 FT 490.00 4.10 1010.66
336ACSR CONDUCTOR 336KCM ACSR /1000 FT 820.00 4.45 1434.02

336AAC CONDUCTOR 336KCM AAC /1000 FT 800.00 7.00 1658.42


556AAC CONDUCTOR 556KCM AAC /1000 FT 1070.00 7.00 1986.12
795AAC CONDUCTOR 795KCM AAC /1000 FT 1520.00 7.00 2549.71

13GRP4 GRIP, SLACK SPAN DEADEND (13/24KV) 4 ACSR 4.26 0.04 8.62
13GRP2 GRIP, SLACK SPAN DEADEND (13/24KV) 2 ACSR 3.59 0.04 7.77
35GRP4 GRIP, SLACK SPAN DEADEND (35KV) 4 ACSR 4.04 0.04 8.35
35GRP2 GRIP, SLACK SPAN DEADEND (35KV) 2 ACSR 4.10 0.04 8.42

13TW4 PREFORMED TIE WIRE (13KV) 4 ACSR 2.17 0.04 5.99


13TW2 PREFORMED TIE WIRE (13KV) 2 ACSR 2.29 0.04 6.21
13TW2/0 PREFORMED TIE WIRE (13KV) 2/0 ACSR 2.51 0.04 6.44
13TW4/0 PREFORMED TIE WIRE (13KV) 4/0 ACSR 2.96 0.04 7.01
13TW336A PREFORMED TIE WIRE (13KV) 336 ACSR 2.74 0.04 6.72
13TW336 PREFORMED TIE WIRE(13KV) 336 AAC 2.57 0.04 6.52
13TW556 PREFORMED TIE WIRE (13KV) 556 AAC 3.61 0.04 7.81
13TW795 PREFORMED TIE WIRE (13KV) 795 AAC 2.99 0.04 7.03

13STW4 PREFORMED SIDE TIE WIRE (13KV) 4ACSR 1.81 0.04 5.57
13STW2 PREFORMED SIDE TIE WIRE (13KV) 2ACSR 1.75 0.04 5.51
13STW2/0 PREFORMED SIDE TIE WIRE (13KV) 2/0ACSR 2.16 0.04 6.01
13STW556 PREFORMED SIDE TIE WIRE (13KV) 556AAC 5.58 0.04 10.24

4-4 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


24DT4 PRFMD DOUBLE TIE WIRE (13/24KV) 4ACSR 6.71 0.08 16.24
24DT2 PRFMD DOUBLE TIE WIRE (13/24KV) 2ACSR 7.07 0.08 16.70
24DT2/0 PRFMD DOUBLE TIE WIRE (13/24KV) 2/0ACSR 7.54 0.08 17.29
24DT336 PRFMD DOUBLE TIE WIRE (13/24KV) 336AAC 12.95 0.08 23.99
24DT556 PRFMD DOUBLE TIE WIRE (13/24KV) 556AAC 10.82 0.08 21.35
24DT795 PRFMD DOUBLE TIE WIRE (13/24KV) 795AAC 15.76 0.08 27.49

24DST4 PRFMD DBL SIDE TIE WIRE (13/24KV) 4ACSR 3.23 0.08 11.93
24DST2 PRFMD DBL SIDE TIE WIRE (13/24KV) 2ACSR 3.50 0.08 12.25
24DST2/0 PRFMD DBL SIDE TIE WIRE (13/24KV) 2/0ACSR 4.39 0.08 13.37
24DST4/0 PRFMD DBL SIDE TIE WIRE (13/24KV) 4/0ACSR 3.78 0.08 12.62
24DST336A PRFMD DBL SIDE TIE WIRE (13/24KV) 336ACSR 5.73 0.08 15.03
24DST336 PRFMD DBL SIDE TIE WIRE (13/24KV) 336AAC 6.68 0.08 16.21
24DST556 PRFMD DBL SIDE TIE WIRE (13/24KV) 556AAC 5.99 0.08 15.34

24TW4 PREFORMED TIE WIRE (24KV) 4 ACSR 1.83 0.04 5.59


24TW2 PREFORMED TIE WIRE (24KV) 2 ACSR 2.02 0.04 5.85
24TW2/0 PREFORMED TIE WIRE (24KV) 2/0 ACSR 2.56 0.04 6.50
24TW4/0 PREFORMED TIE WIRE (24KV) 4/0 ACSR 2.54 0.04 6.49
24TW556 PREFORMED TIE WIRE (24KV) 556 AAC 3.45 0.04 7.61

35TW4 PREFORMED TIE WIRE (35KV) 4 ACSR 1.39 0.04 5.05


35TW1/0 PREFORMED TIE WIRE (35KV) 1/0 ACSR 2.71 0.04 6.69
35TW2/0 PREFORMED TIE WIRE (35KV) 2/0 ACSR 3.46 0.04 7.68

35DT4 PREFORMED DOUBLE TIE WIRE (35KV) 4 ACSR 7.38 0.08 12.49
35DT2/0 PREFORMED DOUBLE TIE WIRE (35KV) 2/0 ACSR 9.95 0.08 20.27

35DST4 PRFMD DBL SIDE TIE WIRE (35KV) 4 ACSR 3.67 0.08 7.87
35DST2/0 PRFMD DBL SIDE TIE WIRE (35KV) 2/0 ACSR 6.03 0.08 15.40

ST4 PREFORMED TIE WIRE - SPOOL 4ACSR 1.56 0.04 5.26


ST2 PREFORMED TIE WIRE - SPOOL 2ACSR 1.61 0.04 5.32
ST1/0 PREFORMED TIE WIRE - SPOOL 1/0 ACSR 1.55 0.04 5.24
ST2/0 PREFORMED TIE WIRE - SPOOL 2/0 ACSR 1.86 0.04 5.64
ST4/0 PREFORMED TIE WIRE - SPOOL 4/0 ACSR 2.30 0.04 6.19

SLVA6CP SLEEVE AUTOMATIC FOR 6A COMP 3.75 0.20 24.11


SLVA6C SLEEVE AUTOMATIC FOR 6 CU 3.09 0.20 23.20
SLVA4C SLEEVE AUTOMATIC FOR 4 CU 3.36 0.20 23.37
SLVA2C SLEEVE AUTOMATIC FOR 2 CU 5.80 0.20 26.38
SLVA20C SLEEVE AUTOMATIC FOR 2/0 CU 8.89 0.20 30.23

4-5 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


SLVA4AC SLEEVE AUTOMATIC FOR 4 ACSR 4.53 0.20 25.25
SLVA2AC SLEEVE AUTOMATIC FOR 2 ACSR 4.53 0.20 25.25
SLVA10AC SLEEVE AUTOMATIC FOR 1/0 ACSR 10.76 0.20 33.44
SLVA20AC SLEEVE AUTOMATIC FOR 2/0 ACSR 10.76 0.20 33.44
SLVA40AC SLEEVE AUTOMATIC FOR 4/0 ACSR 11.57 0.20 33.56

SLVAMRLN SLEEVE AUTOMATIC FOR 336 ACSR & AAC 14.59 0.20 37.30
SLVADHLA SLEEVE AUTOMATIC FOR 556 AAC 18.85 0.20 42.61

PI8W INSULATOR, PIN - 8KV (WHITE) 4.27 0.02 24.04


PI13 INSULATOR, PIN - 13KV 2.57 0.02 22.40
PI13-795 INSULATOR, PIN - 13KV - FOR 795 AAC 3.92 0.02 24.08
PI25 INSULATOR, PIN - 25KV 5.23 0.02 26.46
PI35 INSULATOR, PIN - 35 KV 8.91 0.02 30.25

PIPL15 INSULATOR, PIN - PLASTIC 15KV 8.29 0.02 28.29


PIPL25 INSULATOR, PIN - PLASTIC 25KV 9.15 0.02 30.57

NDE INSULATOR, DEADEND NEUTRAL 7.10 0.01 9.62


DEINPL15 INSULATOR, DEADEND PLASTIC 15KV 9.13 0.01 12.14
DEINPL25 INSULATOR, DEADEND PLASTIC 25KV 16.28 0.01 21.03
DEINPL35 INSULATOR, DEADEND PLASTIC 35KV 18.89 0.01 24.04

CDES4-20 CLAMP D.E. STRAIGHTLINE FOR 4-2/0 ACSR 6.37 0.20 27.11
CDES CLAMP D.E. STRAIGHTLINE 4/0ACSR-556AAC 12.59 0.25 39.04
CDES336 CLAMP D.E. STRAIGHTLINE 336ACSR-1113ACSR 21.96 0.25 48.83
CDES795 CLAMP D.E. STRAIGHTLINE FOR 795AAC 21.96 0.25 48.83
CDEPINC CLAMP D.E. PINCO FOR 8-1/0 CU 4.07 0.25 28.46

CDEA6CP CLAMP D.E. AUTOMATIC FOR 6A COMP 6.92 0.20 28.17


CDEA6CW CLAMP D.E. AUTOMATIC FOR 6 CPRWLD 5.23 0.20 25.91
CDEA6C CLAMP D.E. AUTOMATIC FOR 6 CU 5.23 0.20 25.91
CDEA4C CLAMP D.E. AUTOMATIC FOR 4 CU 5.41 0.20 25.91
CDEA2C CLAMP D.E. AUTOMATIC FOR 2 CU 10.12 0.20 31.74
CDEA10C CLAMP D.E. AUTOMATIC FOR 1/0 CU 11.64 0.20 33.65
CDEA20C CLAMP D.E. AUTOMATIC FOR 2/0 CU 12.16 0.20 34.32
CDEA40C CLAMP D.E. AUTOMATIC FOR 4/0 CU 18.06 0.20 41.63

CDEA4AW CLAMP D.E. AUTOMATIC FOR 4 AWAC 18.06 0.20 41.63


CDEA4AC CLAMP D.E. AUTOMATIC FOR 4 ACSR 6.41 0.20 27.15
CDEA2AC CLAMP D.E. AUTOMATIC FOR 2 ACSR 8.19 0.20 29.36
CDEA10AC CLAMP D.E. AUTOMATIC FOR 1/0 ACSR 14.78 0.20 37.53
CDEA20AC CLAMP D.E. AUTOMATIC FOR 2/0 ACSR 14.78 0.20 37.53
CDEA40AC CLAMP D.E. AUTOMATIC FOR 4/0 ACSR 15.29 0.20 38.19

4-6 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 365.00 - OH CONDUCTORS & DEVICES


HOTTAP-S HOT TAP - SMALL 8-1/0 to 6-1/0 7.99 0.25 33.13
HOTTAP-M HOT TAP - MEDIUM 6-336 to 6-3/0 8.37 0.25 33.80
HOTTAP-L HOT TAP - LARGE 4/0-795 to 6-336 15.75 0.25 42.96

SDEA4AC SPOOL-NEUT & SEC DE AUTO - 4ACSR 6.85 0.07 14.96


SDEA2AC SPOOL-NEUT & SEC DE AUTO - 2ACSR 6.85 0.07 14.96
SDEA20AC SPOOL-NEUT & SEC DE AUTO - 2/0 & 1/0 ACSR 15.24 0.07 25.33

LA10 LIGHTNING ARRESTER - 10KV FOR 13KVYG 72.88 0.75 161.53


LA15 LIGHTNING ARRESTER - 15KV FOR 20KVYG 56.85 0.75 141.66
LA18 LIGHTNING ARRESTER - 18KV FOR 25KVYG 62.65 0.75 148.83
LA27 LIGHTNING ARRESTER - 27KV FOR 35KVYG 81.61 0.75 172.40
LABK ARRESTER BRACKET FOR HD/STD XARMS 15.16 0.10 28.48

GND GROUND ROD - NO.4 COPPER 39.21 1.70 201.66


GNDSP GROUND, COPPER - AT STEEL POLE 19.55 1.70 71.18
GNDSP-GLV GROUND, GALVANIZED - AT STEEL POLE 17.63 0.50 68.86
GNDT GROUND - OH TRANSFORMER 16.42 0.08 28.73

DISC15-25 DISCONNECT SWITCH 900A 1-PHASE 15/25KV 258.85 3.00 604.17


DISCIL336/15-25 DISCON SWITCH 900A 336AAC 1PH INLINE 15/25kV 513.38 3.00 920.18
DISCIL556/15-25 DISCON SWITCH 900A 556AAC 1PH INLINE 15/25kV 522.66 3.00 931.70
DISCIL795/15-25 DISCON SWITCH 900A 795AAC 1PH INLINE 15/25kV 532.69 3.00 944.14

AS900/15-25 AIR SWITCH 900A 15/25kV 3-PHASE 3674.63 20.00 6448.72


AS900HOG15-25 AIR SWITCH 900A HOTSTICK GANG OP 3PH 15/25kV 2426.00 10.00 3953.03

UGDIPDSC600-15 UG DIP KIT - 15KV, 600 AMP, w/DISCONNECTS 1142.49 12.00 2429.07
UGDIPDSC600-20 UG DIP KIT - 20KV, 600 AMP, w/DISCONNECTS 1169.91 12.00 2463.13
UGDIPDSC600-25 UG DIP KIT - 25KV, 600 AMP, w/DISCONNECTS 1187.30 12.00 2484.66

UGDIPSW600-15 UG DIP KIT - 15KV, 600 AMP, FOR HOG SWITCH 266.48 1.50 470.48
UGDIPSW600-20 UG DIP KIT - 20KV, 600 AMP, FOR HOG SWITCH 293.90 1.50 504.55
UGDIPSW600-25 UG DIP KIT - 25KV, 600 AMP, FOR HOG SWITCH 311.29 1.50 526.07

OCR1 RECLOSER, OCR, KYLE V4H, 1-PHASE, 15KV 1932.73 6.00 2965.12
OCR3 RECLOSER, OCR, KYLE V6H, 3-PHASE, 15KV 6948.22 6.00 9192.37

FI-STROBE FAULT IND OH LOAD TRACKER STROBE 150.00 0.10 280.69

4-7 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 368.00 - LINE TRANSFORMERS


13CO1/10 * CUTOUT 13 KV 100A 10,000 INT 83.96 0.75 175.03
13CO2/10 * CUTOUT 13 KV 200A 10,000 INT 140.31 0.75 244.47
20-35CO1/8 * CUTOUT 20-35 KV 100A 8,000 INT 104.02 0.75 199.93
20-35CO2/8 * CUTOUT 20-35 KV 200A 8,000 INT 150.48 0.75 257.60

BLADE13 BLADE, SOLID 13 KV, 300A 40.30 0.05 54.18


BLADE20-35 BLADE, SOLID 20-35 KV, 300A 34.35 0.05 46.67
DOOR200A13 FUSE HOLDER, 13KV, 200A 56.34 0.05 73.62

BRKT-SO BRACKET, SO FG POLE-MNT FOR TRM, LA, CO 34.14 0.20 61.57


COB CUTOUT BRACKET FOR HD/STD XARMS 15.16 0.20 38.11
LABK ARRESTER BRACKET FOR HD/STD XARMS 15.16 0.10 28.48

LA10T TRANSFORMER LIGHTNING ARRESTER - 10KV 41.97 0.75 123.08


LA15T TRANSFORMER LIGHTNING ARRESTER - 15KV 51.11 0.75 134.43
LA18T TRANSFORMER LIGHTNING ARRESTER - 18KV 56.91 0.75 141.60
LA27T TRANSFORMER LIGHTNING ARRESTER - 27KV 75.87 0.75 165.17

GUARD TRANSFORMER WILDLIFE GUARD 5.00 0.25 30.18


GUARD-HOT TRANSFORM WILDLIFE GUARD-Hot Stick Installable 7.43 0.25 32.74

900CAP13-3P CAPACITOR BANK, 3 PHASE, 13KV, 600 KVAR 5444.69 16.00 8268.53
600CAP13-3P CAPACITOR BANK, 3 PHASE, 13KV, 600 KVAR 2091.83 16.00 4105.90
300CAP13-3P CAPACITOR, 3 PHASE, 13KV, 300 KVAR 1883.69 16.00 3847.48
400CAP13 CAPACITOR, 1 PHASE, 13KV, 400 KVAR 470.00 3.55 918.12
300CAP13 CAPACITOR, 1 PHASE, 13KV, 300 KVAR 380.00 3.55 806.37
200CAP13 CAPACITOR, 1 PHASE, 13KV, 200 KVAR 416.32 3.55 851.46
100CAP13 CAPACITOR, 1 PHASE, 13KV, 100 KVAR 347.57 3.55 766.11

1200CAP20-3P CAPACITOR BANK, 3 PHASE, 20 KV,1200 KVAR 2823.85 16.00 5015.81


600CAP20-3P CAPACITOR BANK, 3 PHASE, 20 KV, 600 KVAR 2392.68 16.00 4480.51
400CAP20 CAPACITOR, 1 PHASE, 20 KV, 400 KVAR 800.00 3.55 1327.82
200CAP20 CAPACITOR, 1 PHASE, 20 KV, 200 KVAR 700.00 3.55 1203.67

600CAP25-3P CAPACITOR BANK, 3 PHASE, 25 KV, 600 KVAR 2149.31 16.00 4172.69
400CAP25 CAPACITOR, 1 PHASE, 25KV, 400 KVAR 705.60 3.55 1210.61
300CAP25 CAPACITOR, 1 PHASE, 25KV, 300 KVAR 400.00 3.55 831.21
200CAP25 CAPACITOR, 1 PHASE, 25KV, 200 KVAR 467.11 3.55 914.53
100CAP25 CAPACITOR, 1 PHASE, 25KV, 100 KVAR 452.55 3.55 896.45

* CUTOUTS ARE 368.00 IF USED TO FUSE A TRANSFORMER,


365.00 IF USED TO FUSE A PRIMARY OVERHEAD CIRCUIT,
AND 367.00 IF USED TO FUSE AN UNDERGROUND DIP.

4-8 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0369.10 - SERVICES


4TX SERVICE 4 ALUMINUM TRIPLEX /100 FT 45.00 1.70 229.07
2TX SERVICE 2 ALUMINUM TRIPLEX /100 FT 52.00 1.70 237.71
2/0TX SERVICE 2/0 ALUMINUM TRIPLEX /100 FT 104.00 1.70 304.46
4/0TX SERVICE 4/0 ALUMINUM TRIPLEX /100 FT 142.00 2.05 387.87

2QX SERVICE 2 ALUMINUM QUADRUPLEX /100 FT 78.00 1.90 292.30


2/0QX SERVICE 2/0 ALUMINUM QUADRUPLEX /100 FT 149.00 1.90 381.19
4/0QX SERVICE 4/0 ALUMINUM QUADRUPLEX /100 FT 235.00 2.29 527.20

FERC ACCOUNT 0373.20 - STREET LIGHTING - CIRCUIT


6DX CONDUCTOR #6 ALUMINUM DUPLEX /1000 FT 230.00 2.50 525.77

GNDUGSL GROUND, COPPER AT STEEL ST LIGHT STNDRD 12.84 0.50 64.50


GNDSP-GLV GROUND, GALVANIZED - AT STEEL POLE 17.63 0.50 70.49

FERC ACCOUNT 0373.30 - STREET LIGHTING - STEEL POLES


16FG STANDARD 16' DECORATIVE FBRGLS BLACK 189.49 1.40 369.90
16FGGRN STANDARD 16' DECORATIVE FBRGLS GREEN 520.55 1.40 780.98
20FGBK STANDARD 20' DECORATIVE FBRGLS BLACK 198.63 1.40 381.30
20FGBR STANDARD 20' DECORATIVE FBRGLS BRONZE 189.06 1.40 369.42
25FGBK STANDARD 25' DECORATIVE FBRGLS BLACK 222.42 1.40 411.41

25GRNPB STANDARD 25' PED BASE GREEN w/Decor Shroud 2060.28 3.60 2904.51
30STLPB STEEL STANDARD 30' PEDESTAL BASE 1,393.66 3.60 2124.98
30STLDA STEEL STANDARD 30' DOUBLE ARM PED BASE 1,819.13 3.60 2605.11
35STLDB STEEL STANDARD 35' DIRECT BURY 1,407.45 6.20 2344.78

BASELONG BASE, CONCRETE, STREET LIGHT - LONG 11" 415.00 3.60 861.88
BASESHORT BASE, CONCRETE, STREET LIGHT - SHORT 11" 317.00 3.60 740.21

FERC ACCOUNT 0373.40 - STREET LIGHTING - FIXTURES


2.5MA STREET LIGHT MAST ARM - 2.5 FT 37.80 1.64 204.99
8MA STREET LIGHT MAST ARM - 8 FT 89.94 1.64 270.52
12MA STREET LIGHT MAST ARM - 12 FT 111.14 1.64 301.27
16MA STREET LIGHT MAST ARM - 16 FT 152.21 1.64 352.77
FLMA ARM, FLOOD LIGHT ANGLE BRACKET 22.11 1.64 185.75

DECACORN LUMINAIRE HPS DECORATIVE 100W ACORN 469.75 0.80 660.22


DECACORNGRN LUMINAIRE HPS DECOR 100W ACORN GREEN 569.69 0.80 784.29
DECCOLBK LUMINAIRE HPS DECOR 100W COLONIAL BLACK 142.42 0.80 253.86
DECCOLBR LUMINAIRE HPS DECOR 100W COLONIAL BROWN 148.91 0.80 261.88
DECCNTBK LUMINAIRE HPS DECOR 100W CONTEMP BLACK 160.37 0.80 276.10
DECCNTBR LUMINAIRE HPS
DECOR 100W CONTEMP BROWN 174.88 0.80 297.99
DECSALEM LUMINAIRE HPS DECOR 100W SALEM BLACK 162.07 0.80 278.22
DECTRAD LUMINAIRE HPS DECOR 100W TRADITIONAL 434.77 0.80 616.78

4-9 05/09
OVERHEAD ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0373.40 - STREET LIGHTING - FIXTURES


100HPS2 LUMINAIRE COBRA-HEAD HPS W/SS 100W 2-WAY 101.39 0.80 202.88
100HPS4 LUMINAIRE COBRA-HEAD HPS W/SS 100W 4-WAY 107.32 0.80 210.93
200HPS2 LUMINAIRE COBRA-HEAD HPS W/SS 200W 2-WAY 115.22 0.80 221.99
400HPS2 LUMINAIRE COBRA-HEAD HPS W/SS 400W 2-WAY 158.01 0.80 273.18

250HPSFL LUMINAIRE HPS 250W FLOOD 168.33 0.80 286.00


400HPSFL LUMINAIRE HPS 400W FLOOD 168.35 0.80 286.02

VNDL SHLD VANDAL SHIELD FOR 200W HPS LUMINAIRE 358.45 1.00 540.89

FERC ACCOUNT 596 - MAINTENANCE OF STREET LIGHTING


SSW SUNSWITCH D-2 WITH M-2 BRACKET 4.70 1.40 125.65
REFRACT REFRACTOR, 175W, 4-WAY 33.24 0.40 72.26

4-10 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0366.00 - UG CONDUIT


2RSR-6 RISER, CONDUIT 2 IN w/6.5" STANDOFF BRKTS 31.56 1.50 160.26
2RSR-10 RISER, CONDUIT 2 IN w/10" STANDOFF BRKTS 56.94 1.50 202.15
2RSR-15 RISER, CONDUIT 2 IN w/15" STANDOFF BRKTS 63.98 1.50 200.52
(2)2RSR-15 RISER, CONDUIT (2) 2 IN w/15" STANDOFF BRKTS 88.04 2.00 271.26
(3)2RSR-15 RISER, CONDUIT (3) 2 IN w/15" STNDOFF BRKTS 112.11 2.25 321.88
3RSR-10 RISER, CONDUIT 3 IN w/10" STANDOFF BRKTS 76.81 1.50 226.16
3RSR-15 RISER, CONDUIT 3 IN w/15" STANDOFF BRKTS 83.85 1.50 224.52
4RSR-10 RISER, CONDUIT 4 IN w/10" STANDOFF BRKTS 90.84 1.50 243.63
4RSR-15 RISER, CONDUIT 4 IN w/15" STANDOFF BRKTS 97.88 1.50 242.00
(3)4RSR600 RISER, 600AMP CONDUIT (3) 4" w/15" SO BRKTS 256.39 2.50 519.79
(6)4RSR600 RISER, 600AMP CONDUIT (6) 4" w/15" SO BRKTS 427.48 5.00 934.09
2CDTCAP CONDUIT CAP FOR 2 IN. PVC RISER 8.78 0.03 10.87

PVCPE2CPL COUPLING, 2 IN. PVC TO POLY 7.51 0.36 29.35


P2CPL COUPLING 2 IN. POLY 1.44 0.05 5.26
2CPL COUPLING 2 IN. PVC 0.98 0.20 17.10
3CPL COUPLING 3 IN. PVC 2.15 0.20 18.59
4CPL COUPLING 4 IN. PVC 3.38 0.20 20.08

2CDTPL CONDUIT - 2 IN. PVC /FT 0.53 0.01 1.09


3CDTPL CONDUIT - 3 IN. PVC /FT 1.08 0.01 2.14
4CDTPL CONDUIT - 4 IN. PVC /FT 1.47 0.01 2.62

2CDTFLX FLEX CONDUIT 2 IN. PVC /FT 1.17 0.01 2.25


2POLYRIB-G CONDUIT CONT POLY 2" COIL WAVERIB GRAY /FT 0.59 0.01 1.13

2SCDTPL SPLIT CONDUIT 2 IN. PVC /FT 3.42 0.05 8.48


3SCDTPL SPLIT CONDUIT 3 IN. PVC /FT 5.54 0.05 26.74
4SCDTPL SPLIT CONDUIT 4 IN. PVC /FT 8.17 0.05 14.48

2CDTSTL CONDUIT - 2 IN. STEEL /FT 4.61 0.02 7.34


3CDTSTL CONDUIT - 3 IN. STEEL /FT 7.93 0.02 11.44
4CDTSTL CONDUIT - 4 IN. STEEL /FT 9.99 0.02 14.01

DUCT4WAY 4-WAY DUCT BANK - FORMS & CONCRETE /FT 9.12 0.35 37.82
DUCT6WAY 6-WAY DUCT BANK - FORMS & CONCRETE /FT 11.47 0.50 52.87
DUCT9WAY 9-WAY DUCT BANK - FORMS & CONCRETE /FT 13.99 0.50 55.66

DUCTSPBASE4 SPACER, CONDUIT BASE, 4" PVC 0.75 0.02 2.27


DUCTSPINTR4 SPACER, CONDUIT, INTERMEDIATE, 4" PVC 0.71 0.02 2.23
DUCTREBARHOLD DUCT SPACER REBAR HOLDER 0.94 0.02 2.52
CONCRETE-FTB FLUIDIZED THERMAL BACKFILL /cu yd 70.00 0.25 97.64
CONCRETE-4000 CONCRETE, THERMAL BACKFILL 4000 PSI /cu yd 90.00 0.25 119.81

5-1 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0366.00 - UG CONDUIT


2SWEEP SWEEP, BEND, 2 IN. 90 DEGREE PVC 3.82 0.12 14.38
2SWEEP-22DEG SWEEP, BEND, 2 IN. 22.5 DEGREE PVC 3.88 0.12 14.47
2SWEEP-45DEG SWEEP, BEND, 2 IN. 45 DEGREE PVC 4.27 0.12 14.94
3SWEEP SWEEP, BEND, 3 IN. 90 DEGREE PVC 10.39 0.12 22.54
3SWEEP-22DEG SWEEP, BEND, 3 IN. 22.5 DEGREE PVC 7.35 0.12 18.78
3SWEEP-45DEG SWEEP, BEND, 3 IN. 45 DEGREE PVC 9.14 0.12 20.98
4SWEEP SWEEP, BEND, 4 IN. 90 DEGREE PVC 14.84 0.12 28.08
4SWEEP-22DEG SWEEP, BEND, 4 IN. 22.5 DEGREE PVC 9.75 0.12 21.76
4SWEEP-45DEG SWEEP, BEND, 4 IN. 45 DEGREE PVC 13.95 0.12 24.89

S444 SUBM ENCL CONC 4’8"X4’8"X4’ w/CVR & STL LID 1710.53 6.50 2646.02
S575 SUBM ENCL CONC 7'X4'8"X5' w/CVR, DBL STL LIDS 2800.00 7.00 4038.19
S644 SUBM ENCL CONC 6'X4'X4' w/CVR, DBL STL LID 2124.58 6.50 3160.07
S676 SUBM ENCL CONC 6'3"X7'9"X7'2"w/CVR,DBLSTL LIDS 4500.00 7.00 6148.77
S4484 SUBM ENCL CONC 9' 0" X 5' '0"' X 7' 2" W/LID 4979.00 8.00 6161.56
S5106 SUBM ENCL CONC 6’X11’X7’ w/CVR & 3 STL LIDS 5364.00 8.00 6588.33

S575ST SUBM ENCL CONC 4'8"X7'X5' SUB TFMR 25-50 kVA 2656.00 8.00 3586.51
S577ST SUBM ENCL CONC 4'8"X7'X6'8"SUB TFMR 75-167kVA 2923.00 8.00 3882.47

S333 SUBM ENCL CONC (SECONDARY HH) 36"X42"X35" 879.00 6.50 1376.21
SECPED SECONDARY PEDESTAL - SINGLE PHASE 97.88 1.00 201.86
SECENCLPAD3PH SECONDARY ENCLOSURE, PADMOUNT 3PH 2957.16 0.50 3781.16
SECENCL-BOXPAD SECONDARY ENCL BOX PAD 46"X46"X24"H 492.50 0.80 651.57
HH SEC. HANDHOLE 13"X24" 49.28 1.00 141.58
HH-POLYCRETE SEC. HANDHOLE, POLY CONCRETE 13"X24" 187.95 1.00 313.69
HHL SEC. HANDHOLE, LARGE 17"X30" 70.88 1.00 168.18
HHL-POLYCRETE SEC. HANDHOLE, POLY CONC LG 17"X30" 247.32 1.00 387.37

BOXPAD TRANSFORMER BOX PAD 190.99 0.80 301.49


BOXPADLID COVER FOR TRANSFORMER BOX PAD 106.88 0.80 197.07
P44PL PLASTIC PAD FOR 1-PHASE TRANSFORMER 63.03 0.20 94.14

JE1-GNDSLV GROUND SLEEVE 1PH JE1, JE1-25KV 15/25KV 202.59 0.80 320.28
JE2-GNDSLV GROUND SLEEVE 2PH JE2, JE2-25KV 15/25KV 251.23 0.80 381.30
JE3-GNDSLV GROUND SLEEVE 3PH JE3, JE3-25KV 15/25KV 340.57 0.80 491.95
JE3-5POS-GNDSLV GROUND SLEEVE 3PH JE3-5POSITION 15/25KV 641.75 0.80 864.19
JE3-600-GNDSLV GROUND SLEEVE 3PH JE3-600 15/25KV 331.61 1.00 498.91

GNDSLV600L GROUND SLEEVE 1PH TRANSFORMER 15/25kV 610.60 1.00 838.41


GNDSLV1 GRND SLV w/LID 1PH TFMR, JE1, JE1-25KV 15/25kV 198.99 0.80 315.87
GNDSLV1L GROUND SLEEVE 2PH TRANSFORMER 15/25kV 261.41 0.80 388.91
GNDSLV2 GROUND SLEEVE 3PH TFMR 45-500 kVA 15/25kV 251.23 0.80 376.27
GNDSLV3 GROUND SLEEVE 3PH TFMR 750-1500 kVA 15/25kV 113.90 0.80 205.83
GNDSLV3LRG GROUND SLEEVE w/LOCKING LID 600A JE3 332.11 0.80 475.98

5-2 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0366.00 - UG CONDUIT


CBLRACK CABLE RACK SUPPORT 14 HOLE 27-1/2" MOUNT 29.28 0.33 62.91
HOOK-6 CABLE RACK HOOK 6" 12.04 0.01 15.61
HOOK-10 CABLE RACK HOOK 10" 15.07 0.01 19.36
HOOK-15 CABLE RACK HOOK 15" 19.91 0.01 25.38

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


1CN15 CBL UG 1 AL w/CN 15KV /100 FT 140.00 0.66 227.67
4/0CN15 CBL UG 4/0 AL w/CN 15KV /100 FT 233.00 0.66 343.05
350CN15 CBL UG 350 AL w/CN 15KV /100 FT 350.00 0.92 508.95
750CN15 CBL UG 750 AL w/CN 15KV /100 FT 427.00 1.67 665.36
1000CN15 CBL UG 1000 AL w/CN 15KV /100 FT 558.00 1.67 827.50
1CN25 CBL UG 1 AL w/CN 25KV /100 FT 167.00 0.70 262.41
350CN25 CBL UG 350 AL w/CN 25KV /100 FT 256.00 0.92 392.06
1000CN25 CBL UG 1000 AL w/CN 25KV /100 FT 750.00 1.67 966.60
1/0CN35 CBL UG 1/0 AL w/CN 35KV /100 FT 184.00 0.70 242.10
CBLPULL LABOR FOR SET UP & PULLING CABLE /HR 0.00 1.00 81.12
SETUP = .50 M/H EACH PULL = 1.00 M/H
GNDCA GROUNDING KIT FOR UG CABLE 68.67 2.70 306.67
GNDUG GROUND - AT PAD OR VAULT 12.84 0.50 56.19
GNDUGALT GROUND ROD ALTERNATIVE - 2/0 COPPER 195.24 0.33 270.16
GNDUG600 NEUTRAL FOR 600 AMP INSTALLATIONS 1.88 0.25 3.01
GNDVLTBUS SUBSURFACE VAULT INTERNAL GROUND BUS 143.89 0.50 219.86

FIUG FAULT IND UG LOAD TRACKER TEST POINT 12.06 0.10 23.11
FIUGREMOTE FAULT INDICATOR FIBER OPTIC REMOTE 29.37 0.10 44.71

BI15 BUSHING INSERT 15KV 23.67 0.05 32.88


BI25 BUSHING INSERT 25KV 35.55 0.05 51.51
FTBI15 FEED THRU BUSHING INSERT 15KV 107.32 0.50 173.55
FTBI25 FEED THRU BUSHING INSERT 25KV 139.46 0.50 231.36

BC15 BUSHING CAP 15KV 20.69 0.05 29.15


BC25 BUSHING CAP 25KV 36.78 0.05 49.14
BC600MALE BUSHING CAP, MALE 15/25KV 600A 61.10 0.05 79.31
BC600FEMALE BUSHING CAP, FEMALE 15/25KV 600A 94.67 0.05 120.99

BE15600/200 BUSHING EXTENSION 15KV 600A/200A 198.96 0.17 260.82


BE25600/200 BUSHING EXTENSION 25KV 600A/200A 253.24 0.17 328.21

FTB15 FEED THRU STANDOFF BUSHING 15KV 88.44 0.50 148.69


FTB25 FEED THRU STANDOFF BUSHING 25KV 139.28 0.50 213.14
SOB15 STANDOFF BUSHING 15KV 37.66 0.10 54.98
SOB25 STANDOFF BUSHING 25KV 62.78 0.10 85.85
SOBPI600 PLUG INSULATING STANDOFF 15/25KV 600 AMP 63.94 0.10 87.63
SOBPG600 PLUG GROUNDED STANDOFF 15/25KV 600 AMP 101.86 0.10 134.70

5-3 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


S15 SPLICE 15KV FOR #1 ALCN 48.45 1.50 180.87
S15L SPLICE, LONG 15KV FOR #1 ALCN - FOR REPAIR 106.80 1.50 253.28
S15/2 SPLICE 15KV FOR #2 ALCN - FOR REPAIR 48.45 1.50 180.87
S151/0 SPLICE 15KV FOR 1/0 ALCN 46.91 1.50 178.95
S151/0L SPLICE, LONG 15KV FOR 1/0 ALCN - FOR REPAIR 100.94 1.50 246.00
S154/0 SPLICE 15KV FOR 4/0 ALCN 54.51 1.50 188.35
S15/350 SPLICE 15KV FOR 350 AL 186.53 2.25 413.32
S15/750 SPLICE 15KV FOR 750 ALCN 204.96 2.25 436.35
S15/1000 SPLICE 15KV FOR 1000 ALCN 256.57 2.25 500.27
S25 SPLICE 25KV FOR #1 ALCN 75.55 1.5 214.51
S25/2 SPLICE 25KV FOR #2 ALCN 73.67 1.5 212.16
S25/350 SPLICE 25KV FOR 350 ALCN 263.69 2.25 479.16
S25/1000 SPLICE 25KV FOR 1000 ALCN 287.08 2.25 505.09
S351/0 SPLICE 35KV FOR 1/0 ALCN 119.40 1.5 266.43

CASK-S CABLE ACCESSORY SEALING KIT #1 & 1/0 ALCN 7.64 0.10 17.72
CASK-L CABLE ACCESSORY SEALING KIT 350 - 750 ALCN 12.27 0.10 23.47

EB15 ELBOW 15KV FOR #1 ALCN 33.24 0.65 93.99


EB151/0 ELBOW 15KV FOR 1/0 ALCN 33.59 0.65 94.34
EB154/0 ELBOW 15KV FOR 4/0 ALCN 33.47 0.65 94.17
EB25 ELBOW 25KV FOR #1 ALCN 49.08 0.65 113.56
EB25/2 ELBOW 25KV FOR #2 ALCN 55.87 0.65 122.02
LRTP#1 EB w/LD RED TAP PLUG 600-200A 15kV #1 ALCN 237.62 2.00 456.64
LRTP1/0 EB w/LD RED TAP PLUG 600-200A 15kV 1/0 ALCN 237.64 2.00 456.67
LRTP4/0 EB w/LD RED TAP PLUG 600-200A 15kV 4/0 ALCN 237.08 2.00 455.97
LRTP350 EB w/LD RED TAP PLUG 600-200A 15kV 350 ALCN 245.85 2.00 466.87
LRTP750 EB w/LD RED TAP PLUG 600-200A 15kV 750 ALCN 242.82 2.00 463.10
LRTP1000 EB w/LD RED TAP PLUG 600-200A 15kV 1000 ALCN 245.64 2.00 466.60
LRTP350-25 EB w/LD RED TAP PLUG 600-200A 25kV 350 ALCN 300.13 2.00 534.25
LRTP1000-25 EB w/LD RED TAP PLUG 600-200A 25kV 1000 ALCN 300.43 2.00 534.63

LAUG10 LIGHTNING ARRESTER UG EB 10KV FOR 13KVYG 70.25 0.75 148.68


LAUG18 LIGHTNING ARRESTER UG EB 18KV FOR 20/24KVYG 108.65 0.75 195.76
RLA10 ARRESTER RISER POLE - 10KV FOR 13 KVYG 76.60 0.53 138.09
RLA15 ARRESTER RISER POLE - 15KV FOR 20 KVYG 65.75 0.53 124.59
RLA18 ARRESTER RISER POLE - 18KV FOR 25 KVYG 71.55 0.53 131.77
RLA27 ARRESTER RISER POLE - 27KV FOR 35 KVYG 90.51 0.53 155.34

TRM15 TERMINATOR POLE 15KV FOR #1 ALCN 26.72 0.63 84.44


TRM151/0 TERMINATOR POLE 15KV FOR 1/0 ALCN 23.36 0.63 80.27
TRM154/0 TERMINATOR POLE 15KV FOR 4/0 ALCN 38.10 0.63 98.58
TRM15350 TERMINATOR POLE 15KV FOR 350 ALCN 98.34 0.63 173.38
TRM15750 TERMINATOR POLE 15KV FOR 750 ALCN 131.20 0.63 214.18
TRM151000 TERMINATOR POLE 15KV FOR 1000 ALCN 148.08 0.63 235.14

5-4 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL INSTALLED
CODE FILE DESCRIPTION COST MANHRS COST

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


TRM25 TERMINATOR POLE 25KV FOR #1 ALCN 38.90 0.63 99.61
TRM25350 TERMINATOR POLE 25KV FOR 350 ALCN 114.80 0.63 193.81
TRM251000 TERMINATOR POLE 25KV FOR 1000 ALCN 157.95 0.63 247.40
TRM351/0 TERMINATOR POLE 35KV FOR 1/0 ALCN 74.62 0.63 143.96
TRMBKT TERMINATOR MOUNTING BRACKET 17.63 0.10 30.14
COBRLA15 CUTOUT BRACKET, MOUNT RLA BELOW CO 35.14 0.20 60.31

13CO1/10 CUTOUT 13 KV 100A 10,000 INT 83.96 0.75 165.01


13CO2/10 CUTOUT 13 KV 200A 20,000 INT 140.31 0.75 234.46
20-35CO1/8 CUTOUT 20-35 KV 100A 8,000 INT 104.02 0.75 189.92
20-35CO2/8 CUTOUT 20-35 KV 200A 8,000 INT 150.48 0.75 247.60
BLADE13 BLADE, SOLID 13 KV, 300A 40.30 0.05 53.51
BLADE20-35 BLADE, SOLID 20-35 KV, 300A 34.35 0.05 45.99
DOOR200A13 FUSE HOLDER, 13KV, 200A 56.34 0.05 72.99

UGDIP15-1 UG DIP KIT 15KV 100 AMP, #1 ALCN 183.56 2.86 459.42
UGDIP1/0 UG DIP KIT 15KV 200 AMP, 1/0 ALCN 236.55 2.86 524.71

JE1 JUNCTION ENCL 15 KV 1 PHASE, 4-POSITION 481.25 2.50 1050.52


JE1-25KV JUNCTION ENCL 25 KV 1 PHASE, 4-POSITION 557.52 2.50 1147.33
JE2 JUNCTION ENCL 15/25 KV 2 PHASE, 4-POSITION 728.75 3.50 1499.71
JE2-25KV JUNCTION ENCL 15/25 KV 2 PHASE, 4-POSITION 1111.30 3.50 1974.65
JE3 JUNCTION ENCL 15 KV 3 PHASE, 4-POSITION 1003.60 4.50 2041.92
JE3-5POSITION JUNCTION ENCL 15 KV, 3PH, 5-POSITION + INSERTS 2346.84 4.50 4073.98
JE3-25KV JUNCTION ENCL 25 KV 3 PHASE, 4-POSITION 1254.37 4.50 2343.71
JE3-600 JUNCTION ENCL 600A 15/25 KV 3 PHASE, 4-POSITION 907.89 6.50 2064.06
JE5POSBACKPLATE JUNCTION ENCL BACK PLATE 5-POS JUNCTNS 15KV 777.39 0.25 985.19

J415 JUNCTION BUS PRI 4-POSITION w/BRKT 15KV 154.03 0.50 232.00
J425 JUNCTION BUS PRI 4-POSITION w/BRKT 25KV 305.85 0.50 420.30
J515VLT JUNCTION BUS PRI 5-POSITION w/BRKT 15KV 791.47 1.00 1084.18
J515JE JUNCTION BUS PRI 5-POSITION without BRKT 15KV 713.46 1.00 986.97
J3600 JUNCTION BUS PRI 3-POSITION 15/25KV 600A 168.68 1.00 289.73
J3600VLT JUNCTION BUS PRI 3-POS w/BRKT 15/25KV 600A 254.95 1.00 397.63
J4600 JUNCTION BUS PRI 4-POSITION 15/25KV 600A 275.96 1.00 423.71
J4600VLT JUNCTION BUS PRI 4-POS w/BRKT 15/25KV 600A 327.15 1.00 487.27
J4600/200 JUNCTION BUS PRI 4-POS 15/25KV (2)600A (2)200A 449.46 1.00 639.12
J12Y600 JUNCTION BUS PRI 12-POS Y TYPE 15/25KV 600A 2241.30 1.00 2863.72

CLDPTCH COLD PATCH ONLY - BY AVISTA CREW /FT 10.00 0.01 12.07
CLDPTH-C COLD PATCH ONLY - BY CONTRACTOR /FT 10.00 0.00 11.08
CONC-M/C CONCRETE-CUT & REPLACE (MIN CHG) 0.00 0.00 665.10

5-5 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL MAN INSTALLED
CODE FILE DESCRIPTION COST HRS COST
ADD M/H
FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES SETUP
ASPH-C&R2 ASPHALT CUT & REPLACE 2 FT /100FT 0.50 0.00 4.50 2677.50
ASPH-C&R3 ASPHALT CUT & REPLACE 3 FT /100FT 0.50 0.00 5.00 3275.72
ASPH-C&R4 ASPHALT CUT & REPLACE 4 FT /100FT 0.50 0.00 5.50 3874.59
ASPHJACK ASPHALT CUT&REPL JACKHAMMER /100FT 0.50 0.00 4.50 2677.50
ASPHG&R2 ASPHALT GRIND & REPLACE 2 FT /100FT 0.00 0.00 3206.88
ASPHG&R3 ASPHALT GRIND & REPLACE 3 FT /100FT 0.00 0.00 4242.22
ASPHG&R4 ASPHALT GRIND & REPLACE 4 FT /100FT 0.00 0.00 5277.56

BJ2 BORING OR JACKING 2 IN CONDUIT /FT 0.00 0.30 45.97


BJ3 BORING OR JACKING 3 IN CONDUIT /FT 0.00 0.30 45.97
BJ4 BORING OR JACKING 4 IN CONDUIT /FT 0.00 0.30 45.97
BROCK BORE THROUGH ROCK /FT 0.00 0.30 86.25
BORE BORE w/ROD BORING MACHINE /100FT 2.00 0.00 12.00 1124.30
GBORE$ GUIDED BORING /FT 2.00 0.00 0.01 2.41
GBORE1 GUIDEBORE, FOR 1 ITEM /100FT 2.00 0.00 1.00 241.03
GBORE2 GUIDEBORE, FOR 2 ITEMS /100FT 2.25 0.00 2.00 341.47
GBORE3 GUIDEBORE, FOR 3 ITEMS /100FT 2.50 0.00 2.00 360.90
GBORE4 GUIDEBORE, FOR 4 ITEMS /100FT 2.75 0.00 3.00 461.35
MISSILE MISSILE DIRT DITCH /100FT 0.50 0.00 7.00 602.00
HOERAM HOERAM FOR ROCK DITCH /50FT 0.20 0.00 2.50 238.94
BLAST BLAST /FT 1.00 0.00 0.50 85.22

DD24 BACKHOE DIRT DITCH 24 IN /100FT 0.00 3.06 192.11


DD30 BACKHOE DIRT DITCH 30 IN /100FT 0.00 3.62 227.26
DD36 BACKHOE DIRT DITCH 36 IN /100FT 0.00 4.31 270.58
DD42 BACKHOE DIRT DITCH 42 IN /100FT 0.00 5.01 314.53

DLR24 LOOSE ROCK DITCH 24 IN /100FT 0.00 6.12 384.21


DLR30 LOOSE ROCK DITCH 30 IN /100FT 0.00 7.79 489.06
DLR36 LOOSE ROCK DITCH 36 IN /100FT 0.00 9.19 576.95
DLR42 LOOSE ROCK DITCH 42 IN /100FT 0.00 10.58 664.21

DD24PLOW PLOW DIRT DITCH 24 IN /100FT 0.00 1.49 93.54


DD30PLOW PLOW DIRT DITCH 30 IN /100FT 0.00 1.49 93.54
DD36PLOW PLOW DIRT DITCH-USE CAT 36 IN /100FT 0.00 3.95 247.98
DD42PLOW PLOW DIRT DITCH-USE CAT 42 IN /100FT 0.00 3.95 247.98

DR24 ROCK DITCH 24 IN /100FT 0.00 24.49 1537.48


DR30 ROCK DITCH 30 IN /100FT 0.00 30.06 1887.17
DR36 ROCK DITCH 36 IN /100FT 0.00 35.90 2253.80
DR42 ROCK DITCH 42 IN /100FT 0.00 41.75 2621.07

TRCH30 TRENCHER 30 IN DEPTH /70FT 0.33 0.00 1.40 130.90


TRCH36 TRENCHER 36 IN DEPTH /65FT 0.33 0.00 1.40 138.54

5-6 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL MAN INSTALLED
CODE FILE DESCRIPTION COST HRS COST

FERC ACCOUNT 0367.00 - UG CONDUCTORS & DEVICES


CUSTDTCHE CUSTOMER DITCH INSPECTION /100 FT 0.00 0.00 8.22
BCKFILL BACKFILL DITCH ONLY /100FT 0.00 0.00 52.55
SAND SAND MATERIAL /1 CU YD 21.26 18.90 23.56
SANDPAD LABOR - SAND PADDING, 6" ROCK DITCH /100 FT 0.00 0.00 56.06
SANDCOV LABOR - SAND PADDING, COVER ONLY /100 FT 0.00 0.00 39.50

LS LOCATION SIGN FOR UNDERGROUND CABLE 22.25 0.05 31.12


WT6 WARNING TAPE 6 IN. FOR UG CBL /1000' ROLL 19.09 0.01 23.69
WT3 WARNING TAPE 3 IN. FOR UG CBL /1000' ROLL 10.33 0.01 12.80
CMT CABLE END MARKER 2.06 0.05 6.03

FERC ACCOUNT 0369.30 - SERVICES


2/0ALUG CABLE UG 2/0 ALUMINUM 600V /100 FT 54.00 0.66 121.90
4/0ALUG CABLE UG 4/0 ALUMINUM 600V /100 FT 75.00 0.66 148.55
350ALUG CABLE UG 350 ALUMINUM 600V /100FT 111.00 1.00 221.13
750ALUG CABLE UG 750 KCM ALUMINUM 600V /100FT 203.00 1.00 336.28

2TXUG CABLE UG 2 ALUM. TRIPLEX 600V /100 FT 67.00 0.66 138.47


2/0TXUG CABLE UG 2/0 ALUM. TRIPLEX 600V /100 FT 101.00 0.66 178.32
4/0TXUG CABLE UG 4/0 ALUM. TRIPLEX 600V /100 FT 135.00 0.66 222.47
350TXUG CABLE UG 350 ALUM. TRIPLEX 600V /100FT 243.00 0.66 357.26

2/0QXUG CABLE UG 2/0 ALUM. QUADRUPLEX /100FT 142.00 1.00 260.31


4/0QXUG CABLE UG 4/0 ALUM. QUADRUPLEX /100FT 203.00 1.00 335.98
350QXUG CABLE UG 350 QUADRUPLEX /100FT 329.00 1.00 492.65

SLSV6-2/0 SECONDARY SPLICE 6 - 2/0 UG 2.68 0.20 20.05


SLSV4-4/0 SECONDARY SPLICE 4 - 4/0 UG 2.84 0.20 20.23
SLSV4/0-500 SECONDARY SPLICE 4/0 - 500 UG 5.38 0.20 23.39

BUS30 SEC. BUS - 3 POS. SINGLE-SCREW CONNECTOR 9.16 0.25 32.27


BUS40 SEC. BUS - 4 POS. SINGLE-SCREW CONNECTOR 11.20 0.25 33.56
BUS66 SEC. BUS - 6 POS. SINGLE-SCREW CONNECTOR 14.78 0.25 39.32
BUS88 SEC. BUS - 8 POS. SINGLE-SCREW CONNECTOR 23.07 0.25 49.55

BUS40LRG SEC. BUS - 4 POS. TWO-SCREW CONNECTOR 54.37 0.25 89.83


BUS60LRG SEC. BUS - 6 POS. TWO-SCREW CONNECTOR 60.52 0.25 94.35
BUS80LRG SEC. BUS - 8 POS. TWO-SCREW CONNECTOR 74.47 0.25 113.35

BUS40DUAL SEC. BUS - 4 POS. DUAL ENTRY 2-SCREW CONN 76.37 0.25 115.71
BUS60DUAL SEC. BUS - 6 POS. DUAL ENTRY 2-SCREW CONN 60.82 0.25 96.42
BUS80DUAL SEC. BUS - 8 POS. DUAL ENTRY 2-SCREW CONN 91.20 0.25 134.14

5-7 05/09
UNDERGROUND ASSEMBLIES
ZONE 1A
U/A MATERIAL MAN INSTALLED
CODE FILE DESCRIPTION COST HRS COST

FERC ACCOUNT 0369.30 - SERVICES


BUS8TS58 SEC. BUS - 8 POS. THREADED STUD 5/8 IN 14.64 0.10 26.49
BUS8TS10 SEC. BUS - 8 POS. THREADED STUD 1 IN 19.85 0.10 32.96
BUSCVR8 SEC. BUS COVER 8 POS. THREADED STUD 11.92 0.04 17.62

BUS3P6-500 SEC BUS - 6 POS THRD STUD, 3PH PAD #6-500 13.15 0.10 24.64
BUSCVR3P6-500 SEC BUS COVER 6 POS THRD STUD 3PH PAD #6-500 9.40 0.04 14.49

BUS3P1/0-750 SEC BUS - 6 POS THRD STUD, 3PH PAD 1/0-750 41.51 0.10 65.05
BUSCVR3P1/0-750 SEC BUS COVER 6 POS THRD STUD 3PH PAD 1/0-750 7.95 0.04 12.69

BUSADAPT4 SEC. BUS ADAPTER, SET SCREW 4 POS. 1/0-1000 107.03 0.25 155.98
BUSADAPT6 SEC. BUS ADAPTER, SET SCREW 6 POS. 1/0-1000 145.10 0.25 205.20
BUSADAPT8 SEC. BUS ADAPTER, SET SCREW 8 POS. 1/0-1000 180.44 0.25 245.16

LUG #1 LUG FOR #1 AL/CU 1.13 0.10 9.72


LUG2/0 LUG FOR 2/0 AL/CU 1.46 0.10 10.13
LUG25 LUG FOR 250 AL/CU 2.79 0.17 18.03
LUG35 LUG FOR 350 AL/CU 3.08 0.17 18.38
LUG2-4/0B LUG STACKING BOTTOM FOR 2 TO 4/0 AL/CU 9.79 0.17 26.39
LUG2-4/0T LUG STACKING TOP FOR 2 TO 4/0 AL/CU 3.82 0.17 19.34
LUG350B LUG STACKING BOTTOM FOR 350 KCM AL/CU 10.34 0.17 27.39
LUG350T LUG STACKING TOP FOR 350 KCM AL/CU 4.96 0.17 20.73
LUG500B LUG STACKING BOTTOM FOR 500 KCM AL/CU 12.51 0.17 30.10
LUG500T LUG STACKING TOP FOR 500 KCM AL/CU 7.46 0.17 23.83
LUG600B LUG STACKING BOTTOM FOR 600 KCM AL/CU 14.62 0.17 32.44
LUG600T LUG STACKING TOP FOR 600 KCM AL/CU 7.86 0.17 24.33
LUG750B LUG STACKING BOTTOM FOR 750 KCM AL/CU 15.99 0.17 34.42
LUG750T LUG STACKING TOP FOR 750 KCM AL/CU 12.87 0.17 30.56

SERVCONN SERVICE CONNECTION LABOR (PER l00 KVA) 0.00 1.00 83.88

FERC ACCOUNT 0373.20 - STREET LIGHTING - UG CIRCUITS & DITCH


6DXUG CBL UG - 6 ALUMINUM DUPLEX /100 FT 33.00 0.40 82.07
SLSV6 SEALING SLEEVES FOR #6DX 2.68 0.12 24.37
1RSR RISER, CONDUIT 1 IN 7.70 1.50 166.24
1CDTPL CONDUIT 1 IN PVC /FT 0.24 0.01 1.34
BUS2SL SEC BUS - 2-POSITION STREET LIGHT 15.76 0.01 21.56
BUS3SL SEC BUS - 3-POSITION STREET LIGHT 19.11 0.01 49.90
GNDUGSL GROUND, COPPER AT STEEL STREET LIGHT STAND 12.84 0.50 68.34
GNDSP-GLV GROUND, GALVANIZED - AT STEEL POLE 17.63 0.50 74.33
HH10 SEC. HANDHOLD - ROUND w/LID (10"X10") 10.23 1.00 117.55
HH10LID LID FOR SEC. HANDHOLD - ROUND (10" DIA) 7.74 0.16 26.31

NOTE: CABLE AND HANDHOLES ARE 373.20 IF USED FOR


STREET LIGHTS OR 369.30 IF USED FOR SERVICES.

5-8 05/09
FERC ACCOUNT
108.00 REMOVAL

FERC FERC
Acct. ManHrs Acct. ManHrs

364 Pole 1.98 367 Lightning Arrester 0.10


Pole - Stubbed 2.31 Cutout 0.10
Crossarm -Single 0.41 Sec. Bus 0.25
Crossarm - Double 0.65 Feed Thru Bushing 0.10
Down Guy 0.59 Feed Thru Bushing Insert 0.05
Span Guy 0.42 Standoff Insulator 0.10
Sidewalk Guy 0.86 Splice 0.10
Rack - 1 Spool 0.12 Y-Splice 0.15
Rack - 3 Spool 0.20 Bushing Cap 0.05
Neutral Support 0.12 Bushing Insert 0.05
Pole Top Pin 0.17 Elbow 0.05
Steel Pin 0.10 Terminator 0.10
Transf. Mtg. Bracket 0.50 Junction 0.25
Transf. Rack 1.98 368 Cutout 0.10
365 Conductor .007/lb. Lightning Arrester 0.10
Insulator- Pin 0.00 369.1 Service 0.85
Insulator- Deadend 0.17 373.1 Street Light 0.70
Clamp 0.07 Luminaries Only 0.33
Ground 0.33 Mast Arm Only 0.37
Air Switch 5.00 Ballast Only 0.17
366 Riser, Conduit 0.50 Relay 0.10
Handhole - Sec 0.25 Sunswitch 0.10
373.2 Riser, Conduit 0.50

See man-hour rates on page 1-1

6-1 05/09
SALVAGE—OVERHEAD

POLES & CROSSARMS - For poles and crossarms 0-10 years of age, use the
following salvage table: (Older than 10 years - NO SALVAGE)

Pole & Crossarm Current Mat'l. Cost


Reduction per Year. 10 x 1.120

Salvage Value = (Reduction/Year) (10-Age)

POLES
30' $22.18 55' $67.66
35' $27.86 60' $94.67
40' $38.18 65' $107.73
45' $55.33 70' $170.05
50' $60.69 75' $196.55

Note: Obtain a Bill of Sale for our records when selling poles to customers.

CROSSARMS
Size Single Double
5 Ft. $2.56 $4.34
9 Ft. $5.90 $9.93
9HA $7.72 $13.56
11HA $9.67 $17.46

Salvage Value = (Total Material Cost/Material Multiplier)

9' Crossarm - Single (Hdwr only) ................................................................ $27.86


9' Crossarm - Double (Hdwr only) ............................................................... $37.11
9' Crossarm - Single HD (Hdwr only) .......................................................... $27.63
9' Crossarm - Double HD (Hdwr only) ......................................................... $36.49
Steel Stub ....................................................................................................$275.83
Rack Secondary - 1 Spool w/ext ................................................................. $11.88
Rack Secondary - 3 Spool w/ext ................................................................. $76.51
Neutral Support ........................................................................................... $4.61

Pole Top Pin - 13kV (Double) ..................................................................... $7.78


Pole Top Pin - 13kV (Double) ..................................................................... $14.63
Steel Pin - 13kV (No Adpt) .......................................................................... $3.51
Steel Pin - 25kV (No Adpt) .......................................................................... $10.97

2 Transf Mount Bracket ............................................................................... $97.27


3 Transf Mount Bracket (to 50KVA) ............................................................ $75.26
3 Transf Mount Bracket (75 to 167KVA) ..................................................... $137.20

6-2 05/09
SALVAGE—OVERHEAD

Insulator Pin Type - 8kV (Br) .................................................................... $3.81


Insulator Pin Type - 8kV (Wh) .................................................................. $3.81
Insulator Pin Type - 13kV ......................................................................... $2.29
Insulator Pin Type - 25kV .......................................................................... $4.67

Insulator Deadend 8kV .............................................................................. $6.34


Insulator Deadend 13kV ............................................................................ $8.15

Clamp Pinco .............................................................................................. $3.63


Clamp 4-2/0 ACSR .................................................................................... $5.69
Clamp 556 AAC .........................................................................................$11.24

Ground - Rod .............................................................................................$35.01

Cutout - Open 13kV 100 Amp ................................................................... $74.96


Lightning Arrester - 10kV ...........................................................................$65.07

SCRAP CONDUCTOR

Copper Bare $1.86 /lb Alum.Bare $1.14 /lb


ACSR $0.22 /lb Alum.WP $0.28 /lb

6-3 05/09
SALVAGE UNDERGROUND
(Current Material Cost/Material Multiplier)

Conduit Riser - 2" ........................................................................................ $57.13


Conduit Riser - 3" ........................................................................................ $74.87
Conduit Riser - 4" ........................................................................................ $87.39

Riser Pole Arrester 10kV ............................................................................. $68.39

Plastic Pad - Single Phase .......................................................................... $56.28


Groundsleeve - Single Phase ...................................................................... $177.67
Cutout - Open 13kV 100 Amp ......................................................................$74.96
Cutout - Bracket for Heavy Arms ................................................................. $13.54

Ground Rod - Pad or Vault .......................................................................... $11.46

Bus - Bar 30 ................................................................................................. $8.18


Bus - Bar 40 ................................................................................................. $10.00
Bus - Bar 66 ................................................................................................. $13.20

Feed Thru Bushing - 15kV ........................................................................... $78.96


Feed Thru Bushing - 25kV ........................................................................... $124.36
Feed Thru Bushing Insert- 15kV .................................................................. $95.82
Feed Thru Bushing Insert - 25kV ................................................................. $124.52

Standoff Bushing - 15kV .............................................................................. $33.63


Standoff Bushing - 25kV .............................................................................. $56.05

Bushing Cap- 15kV ...................................................................................... $18.47


Bushing Cap - 25kV ..................................................................................... $32.84
Bushing Insert - 15kV .................................................................................. $21.13
Bushing Insert - 25kV .................................................................................. $31.74

Elbow - 15kV ................................................................................................$29.68


Elbow - 25kV ................................................................................................$43.82

Junction Bus - Pri 4 Position - 15kV ............................................................ $137.53


Junction Bus - Pri 5 Position - 15kV ............................................................ $637.02
Junction Bus - Pri 4 Position - 25kV ............................................................ $273.08

6-4 05/09
MAINTENANCE

Use the following as a guideline for estimating maintenance cost of new


MAN-HRS MAINT
TASK# TASK PER UNIT COSTS
583000 (OH) Install or Remove Transformer 1-25 KVA 2.15 174
and (System Average) 37-167 KVA 2.35 191
584010 (UG) 200-750 KVA 3.55 288
1000-2000 KVA* 4 M 599
2500 KVA* 7.5 U 883
Transfer 1.5 x Install L
593010 Trench Pole 8.60 T 605
Up or Down Guy 1.85 I 130
Single Arm 0.85 P 60
Double Arm 1.42 L 100
Spool Rack 0.48 Y 34
Transformer Bracket 0.87 61
593020 Retie Conductor to pole 0.08 T 6
Reclamp Conductor 0.20 H 14
Relocate Conductor (per Insulator) 0.2 E 14
Up or Down Line Cutout 0.75 S 53
Line OCR 0.75 E 53
Service (OH) 0.96 68
593031 Tree Trim (Avista Utilities Crew) X
Tree Trim (Contract Crew)
Clear Line-Light 0.01 1.50.35/ft
Medium 0.01 0.70/ft
Heavy 0.02 F 1.05/ft
594010 Up or Down Terminator 0.63 O 44
Arrester 0.75 R 53
Cutout 0.75 53
Riser 3.00 T 211
595000 Up or Down Cutout for Transf or Cap 0.75 R 53
Arrester for Transf or Cap 0.75 A 53
Cap Bank 300-75 KVAR 3.55 N 250
900-1200 KVAR 4.00 S 281
596010 Up or Down Street Light & Bracket 2.86 F 166
Luminaire 0.80 E 56
Relay 1.40 R 98
Sunswitch 1.40 98
Notes:
1. Use ZONE, HOT WORK, CONTRACT & OMISSION corrections as required, except for transformers.
2. * Includes Cost of Crane ($275)
3. The Maintenance Cost column equals the Man-Hours Per Unit column times the appropriate 4-man
crew rate, times the material multiplier. (See man-hour rates on page 1-1).
4. Transfer refers to removal and installation of an item on the same day without leaving the job site.
Multiply the man-hours or maintenance cost by 1.5 for transfer.

6-5 05/09
95kV BIL 125kV BIL 125kV BIL 150kV BIL

7620/13200Y 12000/20800Y 14400/24900Y 19920/34500Y

KVA 120/240 277/480Y 120/240 277/480Y 120/240 277/480Y 120/240 277/480Y


3 $425 * * * * * * *

15 $734 $751 $758 $803 $808 $1,038 $1,176 $976

25 $918 $934 $1,047 $1,081 $967 $1,633 $1,472 $1,011

7-1
37.5 $809 $1,193 $1,337 * $1,235 * * *

50 $1,437 $1,431 $1,469 $1,427 $1,550 $1,597 * $2,291

75 $1,898 $1,970 $2,016 $1,998 $1,967 $1,836 * *


(WITH TAPS & NO TAPS)

100 $2,550 $2,362 $2,466 $2,462 * * * *


DISTRIBUTION ESTIMATING
NEW TRANSFORMER COST FOR

SINGLE-PHASE OVERHEAD TYPE

Prices do not include sales tax, material overheads or installation.


167 $3,783 $3,652 $4,237 $3,351 * * * *

250 $5,048 $4,413 * * * * * *

05/09
*Not stocked by Avista Utilities. Must special order. Prices include shipping.
333 $6,672 $6,227 * * * * * *

500 * $7,797 * * * * * *
NEW TRANSFORMER COST FOR
DISTRIBUTION ESTIMATING
SINGLE-PHASE PADMOUNT TYPE

95kV BIL 125kV BIL 125kV BIL


13200Y/7620 20800Y/12000 24900Y/14400
240/120 240/120 240/120
KVA WITH & NO TAPS NO TAPS NO TAPS
15 $1,170 $1,231 $1,338
25 $1,453 $1,449 $1,529
37.5 $1,613 * *
50 $1,893 $1,882 *
75 $2,265 $2,320 *
100 $2,814 $2,898 *
167 $3,699 $3,833 *

2 - 2-1/2 taps above and below 7620 volts are required for 12.5 kV system.

*Not stocked by Avista Utilities. Must special order.

Prices include shipping. Prices do not include sales tax, material overheads
or installation.

7-2 05/09
NEW TRANSFORMER COST FOR
DISTRIBUTION ESTIMATING
THREE-PHASE PADMOUNT TYPE
(WITH TAPS & FUSES)

95kV BIL 125kV BIL 125kV BIL


13200Y/7620 20800Y/12000 24900Y/14400
KVA 208Y/120 480Y/277 208Y/120 480Y/277 208Y/120 480Y/277
45 $4,845 $4,904 * * * *
75 $5,138 $5,480 $5,604 $5,997 * *
112 $5,993 $6,186 $6,330 $6,375 * *
150 $6,659 $6,456 $6,579 $6,623 * *
225 $7,473 $7,189 $7,473 $7,323 * *
300 $9,112 $8,443 $9,175 $8,746 * *
500 $14,346 $11,941 $12,411 * * *
750 $16,227 $14,723 * $14,907 * *
1000 $19,598 $22,779 * $20,610 * *
1500 * $23,782 * * * *
2500 * * * $40,123 * *

*Not stocked by Avista Utilities. Must special order. Prices include shipping.
Prices do not include sales tax, material overheads or installation.

7-3 05/09
SERVICE VOLTAGE DROP
IN PERCENT AT 100% POWER FACTOR

120/240 VOLT SERVICE

4TX OVERHEAD
WINTER LOADS:
KVA:
5 10 15 20 25
FEET
AMPS at 240 volts:
21 42 63 83 104
50 0.46 0.93 1.39 1.85 2.32
100 0.93 1.85 2.78 3.71 4.64
150 1.39 2.78 4.17 5.56 6.95
200 1.85 3.71 5.56 7.42 9.27
250 2.32 4.64 6.95 9.27 11.59
300 2.78 5.56 8.34 11.13 13.91
350 3.24 6.49 9.73 12.96 16.22
400 3.71 7.42 11.13 14.83 18.54

120/240 VOLT SERVICE

2TX OVERHEAD
WINTER LOADS:
KVA:
10 15 20 25 30 35
FEET
AMPS at 240 volts:
42 63 83 104 125 146
50 0.59 0.88 1.17 1.46 1.76 2.05
100 1.17 1.76 2.34 2.93 3.51 4.10
150 1.76 2.63 3.51 4.39 5.27 6.14
200 2.34 3.51 4.68 5.85 7.02 8.19
250 2.93 4.39 5.85 7.31 8.78 10.24
300 3.51 5.27 7.02 8.78 10.53 12.29
350 4.10 6.14 8.19 10.24 12.29 14.33
400 4.68 7.02 9.36 11.70 14.04 16.38

SHADED VALUES ARE FOR REFERENCE ONLY.

8-1 05/09
SERVICE VOLTAGE DROP
IN PERCENT AT 100% POWER FACTOR

120/240 VOLT SERVICE

2/OTXUG WINTER
LOADS:
KVA:
10 15 20 25 30 35 40 45 50
FEET
AMPS at 240 volts:
42 63 83 104 125 146 167 188 208
50 0.30 0.44 0.59 0.74 0.89 1.03 1.18 1.33 1.48
100 0.59 0.89 1.18 1.48 1.77 2.07 2.36 2.66 2.95
150 0.89 1.33 1.77 2.21 2.66 3.10 3.54 3.98 4.43
200 1.18 1.77 2.36 2.95 3.54 4.13 4.72 5.31 5.90
250 1.48 2.21 2.95 3.69 4.43 5.16 5.90 6.64 7.38
300 1.77 2.66 3.54 4.43 5.31 6.20 7.08 7.97 8.85
350 2.07 3.10 4.13 5.16 6.20 7.23 8.26 9.30 10.33
400 2.36 3.54 4.72 5.90 7.08 8.26 9.44 10.63 11.81
450 2.66 3.98 5.31 6.64 7.97 9.30 10.63 11.95 13.28
500 2.95 4.43 5.90 7.38 8.85 10.33 11.81 13.28 14.76
550 3.25 4.87 6.49 8.12 9.74 11.36 12.99 14.61 16.23
600 3.54 5.31 7.08 8.85 10.63 12.40 14.17 15.94 17.71

120/240 VOLT SERVICE

4/OTXUG WINTER
LOADS:
KVA:
30 35 40 45 50 55 60 65 70
FEET
AMPS at 240 volts:
125 146 167 188 208 229 250 271 292
50 0.57 0.67 0.76 0.86 0.95 1.05 1.15 1.24 1.34
100 1.15 1.34 1.53 1.72 1.91 2.10 2.29 2.48 2.67
150 1.72 2.01 2.29 2.58 2.86 3.15 3.44 3.72 4.01
200 2.29 2.67 3.06 3.44 3.82 4.20 4.58 4.97 5.35
250 2.86 3.34 3.82 4.30 4.77 5.25 5.73 6.21 6.68
300 3.44 4.01 4.58 5.16 5.73 6.30 6.88 7.45 8.02
350 4.01 4.68 5.35 6.02 6.68 7.35 8.02 8.69 9.36
400 4.58 5.35 6.11 6.88 7.64 8.40 9.17 9.93 10.69

SHADED VALUES ARE FOR REFERENCE ONLY.

8-2 05/09
SERVICE VOLTAGE DROP
IN PERCENT AT 100% POWER FACTOR

120 VOLT SERVICE (STREET LIGHTS)

6DX
MULTIPLE LIGHTS:
FEET WATTS:
50 100 200 250 400 500 600 700 800
50 0.03 0.06 0.12 0.15 0.24 0.29 0.35 0.41 0.47
100 0.06 0.12 0.24 0.29 0.47 0.59 0.71 0.82 0.94
150 0.09 0.18 0.35 0.44 0.71 0.88 1.06 1.24 1.41
200 0.12 0.24 0.47 0.59 0.94 1.18 1.41 1.65 1.88
250 0.15 0.29 0.59 0.74 1.18 1.47 1.76 2.06 2.35
300 0.18 0.35 0.71 0.88 1.41 1.76 2.12 2.47 2.82
350 0.21 0.41 0.82 1.03 1.65 2.06 2.47 2.88 3.29
400 0.24 0.47 0.94 1.18 1.88 2.35 2.82 3.29 3.76

SHADED VALUES ARE FOR REFERENCE ONLY.

8-3 05/09
TRANSFORMER 160% - LOAD CURRENT

SINGLE-PHASE CURRENT = KVA x 1000 x 1.6


IN AMPS Phase to Ground Voltage

TRANSF PHASE-TO-GROUND VOLTAGE:


KVA 120 240 277 480 2400 7200 7620 14400 19900
3 40 20 17 10 2 1 1 0 0
5 67 33 29 17 3 1 1 1 0
7.5 100 50 43 25 5 2 2 1 1
10 133 67 58 33 7 2 2 1 1
15 200 100 87 50 10 3 3 2 1
25 333 167 144 83 17 6 5 3 2
37.5 500 250 217 125 25 8 8 4 3
50 667 333 289 167 33 11 10 6 4
75 1,000 500 433 250 50 17 16 8 6
100 1,333 667 578 333 67 22 21 11 8
167 2,227 1,113 965 557 111 37 35 19 13
250 3,333 1,667 1,444 833 167 56 52 28 20
333 4,440 2,220 1,923 1,110 222 74 70 37 27
500 6,667 3,333 2,888 1,667 333 111 105 56 40

THREE-PHASE CURRENT = Bank KVA x 1000 x 1.6


IN AMPS 1.732 x Phase to Ground Voltage

BANK PHASE-TO-PHASE VOLTAGE:


KVA 208 240 480 4160 12470 13200 24900 34500
30 133 116 58 7 2 2 1 1
45 200 173 87 10 3 3 2 1
75 333 289 145 17 6 5 3 2
112.5 500 434 217 25 8 8 4 3
150 667 578 289 33 11 11 6 4
225 1,000 867 434 50 17 16 8 6
300 1,334 1,156 578 67 22 21 11 8
500 2,223 1,927 963 111 37 35 19 13
750 3,335 2,890 1,445 167 56 53 28 20
1000 4,446 3,854 1,927 222 74 70 37 27
1500 6,670 5,780 2,890 333 111 105 56 40

8-4 05/09
TRANSFORMER FULL - LOAD CURRENT

SINGLE-PHASE CURRENT = KVA x 1000


IN AMPS Voltage

TRANSF PHASE-TO-GROUND VOLTAGE:


KVA 120 240 277 480 2400 7200 7620 14400 19900
3 25 13 11 6 1 0 0 0 0
5 42 21 18 10 2 1 1 0 0
7.5 63 31 27 16 3 1 1 1 0
10 83 42 36 21 4 1 1 1 1
15 125 63 54 31 6 2 2 1 1
25 208 104 90 52 10 3 3 2 1
37.5 313 156 135 78 16 5 5 3 2
50 417 208 181 104 21 7 7 3 3
75 625 313 271 156 31 10 10 5 4
100 833 417 361 208 42 14 13 7 5
167 1,392 696 603 348 70 23 22 12 8
250 2,082 1,042 903 521 104 35 33 17 13
333 2,775 1,388 1,202 694 139 46 44 23 17
500 4,167 2,083 1,805 1042 208 69 66 35 25

THREE-PHASE CURRENT = KVA x 1000


IN AMPS 1.732 Voltage

BANK PHASE-TO-PHASE VOLTAGE:


KVA 208 240 480 4160 12470 13200 24900 34500
30 83 72 36 4 1 1 1 1
45 125 108 54 6 2 2 1 1
75 208 180 90 10 3 3 2 1
112.5 312 271 135 16 5 5 3 2
150 416 361 180 21 7 7 3 3
225 625 541 271 31 10 10 5 4
300 833 722 361 42 14 13 7 5
500 1,388 1,203 601 69 23 22 12 8
750 2,082 1,804 902 104 35 33 17 13
1000 2,776 2,406 1,203 139 46 44 23 17
1500 4,164 3,608 1,804 208 69 66 35 25

8-5 05/09
OVERHEAD MAXIMUM AMPACITY TABLES

ACSR

Conductor Weight Maximum Ampacity (Amps)


Size Code (Lb./Ft.) Summer Winter

#4 Swanate 0.0670 121 176


#2 Sparrow 0.0913 161 241
1/O Raven (N1) 0.1450 210 309
2/O Quail 0.1831 241 355
4/O Penguin 0.2911 314 465
266.8 kCM Partridge (N2) 0.3673 397 590
336.4 kCM Merlin (N2) 0.3653 451 671
397.5 kCM Ibis (N2) 0.5469 510 761
556.5 kCM Parakeet (N2) 0.7168 625 937

ALL ALUMINUM

Conductor Weight Maximum Ampacity (Amps)


Size Code (Lb./Ft.) Summer Winter

#4 Tie Wire 0.3900 100 150


336.4 kCM Tulip 0.3158 452 676
556.5 kCM Dahlia 0.5220 610 913
795 kCM Arbutus 0.7460 762 1146
1272 kCM Nacrissus 1.1940 1014 1535

COPPER

Conductor Weight Maximum Ampacity (Amps)


Size Code (Lb./Ft.) Summer Winter

#6 --- 0.0800 110 156

For additional information, refer to Overhead Construction Standards


DO-3.110 through DO-3.140.

N1. Not for new Distribution Construction.


N2. For neutrals with secondary mid-span taps only.

8-6 05/09
OVERHEAD MAXIMUM AMPACITY TABLES

SERVICES

Conductor Neutral Cond Weight Maximum Ampacity (Amps)


Size ACSR (6/1) (Lb./Ft.) Summer Winter

#6 DX #6 0.0770 59 86
#4 TX #4 0.1720 78 114
#2 TX #4 0.2360 106 155
2/0 TX #1 0.4680 165 241
4/0 TX #2/0 0.7290 224 328
#2 QX #2 0.3600 95 139
2/0 QX #2/0 0.7000 149 216
4/0 QX #4/0 1.0700 202 295
2/0 SNGL None 0.1900 232 311
4/0 SNGL None 0.2800 312 418
350 ALWP None 0.4390 431 578
750 ALWP None 0.9050 707 949
250 CUWP None 0.8100 445 556
500 CUWP None 1.6000 695 933

For additional information, refer to Overhead Construction Standard DO-6.101.

Ampacity is for each phase conductor.

8-7 05/09
UNDERGROUND MAXIMUM AMPACITY TABLES

ALUMINUM CROSS-LINKED POLYETHYLENE


90 Degrees C

Conductor Neutral Weight Maximum Ampacity (Amps)


Voltage Size Size (Lb./Ft.) Summer Winter
15 kV 1 Full 0.60 145 160
15 kV 1/0 Full 0.70 180 205
15 kV 4/0 1/2 0.81 270 310
15 kV 350 1/3 1.12 340 380
15 kV 750 1/3 2.00 585 665
15 kV 1000 1/8 2.70 675 770
25 kV 1 Full 0.68 160 180
25 kV 350 1/3 1.38 380 430
25 kV 1000 1/8 2.87 670 760
35 kV 1/0 Full 0.92 185 210

For additional information, refer to Underground Construction Standard


DU-4.105.

Ampacity values are for 3-phase construction with one cable per conduit.

8-8 05/09
UNDERGROUND MAXIMUM AMPACITY TABLES

ALUMINUM CROSS-LINKED POLYETHYLENE MULTIPLEX


90 deg. 600 VOLT INSULATION

Conductor Neutral Cond Weight Maximum Ampacity (Amps)


Size Size (Lb./Ft.) Summer Winter
6DXUG #6 100 58 76
2TXUG #4 275 102 133
2/0TXUG #1 525 159 208
4/0TXUG #2/0 765 217 283
2/0QXUG #1 705 159 208
4/0QXUG #2/0 1038 217 283
3 x 350AL #4/0 AL 1630 303 395
3 x 750AL 350 AL 3180 488 637

Multiply ampacity values by 1.6 for two parallel sets of conductors.

Ampacity is for each phase conductor in conduit.

For additional information, refer to Underground Construction Standard


DU-7.101.

8-9 05/09
URD TRANSFORMERS AND
JUNCTION ENCLOSURES

JUNCTION ENCLOSURES

Type Equipped With Items to Order


JE1 (1) J4__, (4) BI EBs, BCs, (1) GNDSLV1, GNDUG
JE2 (2) J4__, (8) BI EBs, BCs, (1) GNDSLV2, GNDUG
JE3 (3) J4__, (12) BI EBs, BCs, (1) GNDSLV3, GNDUG

Note: Order BCs to cover unused positions on the J4 primary bus.

SINGLE PHASE PADMOUNT TRANSFORMERS

To install a single phase padmount transformer you will need to order


the following items:

P44PL
KVA FTBI PAD SCOOP GNDUG
15 To exit twice 1 1GNDSLV1 1
25 To exit twice 1 1GNDSLV1 1
37.5 To exit twice 1 1GNDSLV1 1
50 To exit twice 1 1GNDSLV1 1
75 To exit twice 1 1GNDSLV1 1
100 To exit twice 1 1GNDSLV1 1
167 To exit twice 1 1GNDSLV1 1

Notes:

1) New single phase padmount transformers are shipped from the factory
with the following primary components:

· Two primary bushings and two bushing inserts (BI) for feed through
· 2-200 amp elbows (EB) in a prepackaged kit

Additional primary components needed:

· If you are going into the transformer with a primary conductor and out
of the transformer with a primary conductor, no additional primary
components need to be ordered.
· If you are not going out of the transformer with a primary conductor,
order a bushing cap (BC).
· If you intend to take two primary conductors out of the transformer,
order a feed through bushing insert (FTBI) and an additional 200 am elbow (EB).

8-10 05/09
URD TRANSFORMERS AND
JUNCTION ENCLOSURES

SINGLE PHASE PADMOUNT TRANSFORMERS

Notes: (continued)

2) All new single phase padmount transformers are shipped from the
factory with the following secondary connectors:

· 15-75 kVA transformers are shipped with eight position secondary


connectors on 5/8" studs (BUS8TS58). Boot covers are included on X1
and X3.
· 100-167 kVA transformers are shipped with eight position secondary
connectors on 1" studs (BUS8TS10). Boot covers are included on X1
and X3.

3) It is typically not necessary to order SOBs for transformers.

4) Whenever it is practical to do so, replace subsurface transformers with


padmount units when the subsurface unit fails. Poly concrete pad
(54"x48") stock number 571-2010 should be ordered.

8-11 05/09
URD TRANSFORMERS AND
JUNCTION ENCLOSURES

THREE PHASE PADMOUNT TRANSFORMERS

Three phase padmount transformers come in 45, 75, 112.5, 150, 225, 300,
500, 750, 1000, and 1500 kVA ratings. All three phase padmount transformers
are wired for wye secondary voltages of either 208Y/120 or 480Y/277.

Notes:
1) All three phase padmount transformers are shipped from the factory
with the following primary components:
· Three primary bushings and three bushing inserts (BI)
· 3-200 amp elbows (EB) in a prepackaged kit

Additional primary components needed:


· If the service feeds a single transformer, no additional primary
components need to be ordered.
· If the transformer is being used in a feed through application, three
feed through bushing inserts (FTBI) and three 200 amp elbows (EB)
must be ordered.

2) Secondary connectors are either set screw style with boot covers pre
installed, or spade connectors as follows:

KVA 208Y/120 480Y/277


45-75 six pos set screw #6-500KCM six pos set screw #6-500KCM
112.5-225 six pos set screw 1/0-750KCM six pos set screw 1/0-750KCM
300 16 hole supported six pos set screw 1/0-750KCM
500-1000 16 hole supported 16 hole supported
1500 N/A 16 hole supported

The holes required are in addition to any holes used to support and/or connect
to the terminal.

Three phase padmount transformers do not come with their own plastic base
pad. They require a poured concrete pad for installation. For most applications,
the customer is required to supply a concrete pad that meets Avista Utilities'
standards. Remember to order a three phase scoop (GNDSLV3 or
GNDSLV3LRG) to be installed in the concrete pad. See DU-5.122.

If the customer proposes more than 3 wires per phase, they may be required
to provide a secondary enclosure. See DU-5.124 for guidelines; and DU-5.122
and DU-5.123 for fiberglass box pad or concrete pad.

8-12 05/09
Copyright 2004 Avista Utilities.

All rights reserved under U.S. and foreign law, treaties and
conventions. No part of this work may be copied or reproduced,
stored in retrieval system, or transmitted in any form, graphic,
electronic or mechanical, without permission of the copyright
owner.

You might also like