9.

9 MW BIOMASS POWER PLANT PROJECT

OSCAR SAVE THE WORLD #1 PROJECT

OWNER : OSCAR SAVE THE WORLD COMPANY LIMITED


Amphoe Saira, Chawang, Nakhonsritammarat Province

OE : JERA POWER ENGINEERING (Thailand) Co.,Ltd.


33/4 The 9th Towers Grand Rama 9, Tower B, 16th floor,
Rama 9 Road, Kwang Huay Kwang, Khet Huay Kwang,
Bangkok 10310, Thailand
EPC : ENSYS COMPANY LIMITED
636/4-5 Soi Ramkhamhaeng 39 (Thepleela 1)
Pracha Uthit Rd., Wangthonglang, Wangthonglang, Bangkok
10310, Thailand

DOCUMENT NAME: Weekly Report Date 26 February – 2 Mar 2018

Boiler This Week Last Week Achieve Remark


Indicator Block 90% 90% 0%
Loop Control 80% 70% 5%
Logic & Function 65% 45% 35% Get update from Getabec on 13 Feb 18.
Total of Boiler 78.33% 68.33% 10%

BOP This Week Last Week Achieve Remark


Indicator Block 90% 90% 5%
Loop Control 85% 55% 10%
Logic & Function 80% 65% 15%
Total of BOP 85.00% 70.00% 15%

Graphic This Week Last Week Achieve Remark


Graphic Static 90% 90% 0% Revise follow JERA Comment.
Graphic Dynamic 75% 65% 15% Revise follow JERA Comment.
Graphic Pop-Up 25% 15% 10%
Total of Graphic 63.33% 56.67% 7%

Progress
This Week Last Week Achieve
Total Progress 75.56% 65.00% 11% Boiler, BOP and Graphic

Rev. Date Description Issue Check Approver


- 2 Mar 18 Weekly Report Software Apichart R. Surachai S. Chaiyut T.

Weekly Report
1 of 1 Software