You are on page 1of 18

PERHITUNGAN VOLUME KOLOM ZONE A

1. LANTAI BASEMENT

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.8 0.8 4.2 21.50 104.32 19 2.2257 6.25 28 3113.4872
K1B 2 0.8 0.8 4.2 5.38 26.08 19 2.2257 6.25 28 778.3718
K1C 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 6.25 28 1945.9295
K1D 7 0.8 0.8 4.2 18.82 91.28 19 2.2257 6.25 28 2724.3013
K1E 9 0.8 0.8 4.2 24.19 117.36 19 2.2257 6.25 28 3502.6731
K1F 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 6.25 28 1945.9295
K2 6 0.8 0.8 4.2 16.13 78.24 32 6.3134 6.96 24 6327.5420
K2A 1 0.8 0.8 4.2 2.69 13.04 32 6.3134 6.96 24 1054.5903
K3 11 0.8 0.8 4.2 29.57 143.44 32 6.3134 6.96 32 15467.3249
K3A 5 0.8 0.8 4.2 13.44 65.20 32 6.3134 6.96 32 7030.6022
K4 1 0.8 0.8 4.2 2.69 13.04 32 6.3134 6.96 24 1054.5903
K8 5 1 1 4.2 21.00 81.50 25 3.8534 6.58 56 7094.1094
K9 14 1 1 4.2 58.80 228.20 32 6.3134 6.96 56 34449.9510
K10 4 1 1 4.2 16.80 65.20 32 6.3134 6.96 60 10545.9034
TOTAL 257.88 1157.30 97035.3061

2. LANTAI LOWER GROUND

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.8 0.8 4.2 21.50 104.32 19 2.2257 4.96 24 2119.5786
K1B 2 0.8 0.8 4.2 5.38 26.08 19 2.2257 4.96 24 529.8947
K1C 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 24 1324.7366
K1D 7 0.8 0.8 4.2 18.82 91.28 19 2.2257 4.96 24 1854.6313
K1E 9 0.8 0.8 4.2 24.19 117.36 19 2.2257 4.96 24 2384.5260
K2 6 0.8 0.8 4.2 16.13 78.24 32 6.3134 5.48 24 4982.0302
K2A 1 0.8 0.8 4.2 2.69 13.04 32 6.3134 5.48 24 830.3384
K3 11 0.8 0.8 4.2 29.57 143.44 32 6.3134 5.48 32 12178.2961
K3A 5 0.8 0.8 4.2 13.44 65.20 32 6.3134 5.48 32 5535.5891
K4 1 0.8 0.8 4.2 2.69 13.04 32 6.3134 5.48 24 830.3384
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 56 5610.5504
K9 14 1 1 4.2 58.80 228.20 32 6.3134 5.48 56 27124.3867
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 60 8303.3837
TOTAL 244.44 1092.10 73608.2801

3. LANTAI GROUND

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.8 0.8 4.2 21.50 104.32 19 2.2257 4.96 24 2119.5786
K1B 2 0.8 0.8 4.2 5.38 26.08 19 2.2257 4.96 24 529.8947
K1C 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 24 1324.7366
K1D 7 0.8 0.8 4.2 18.82 91.28 19 2.2257 4.96 24 1854.6313
K1E 9 0.8 0.8 4.2 24.19 117.36 19 2.2257 4.96 24 2384.5260
K2 6 0.8 0.8 4.2 16.13 78.24 25 3.8534 5.20 20 2404.5216
K2A 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536
K3 11 0.8 0.8 4.2 29.57 143.44 25 3.8534 5.20 28 6171.6054
K3A 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 28 2805.2752
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 32 6.3134 5.48 40 19374.5619
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 60 8303.3837
TOTAL 244.44 1092.10 52161.9089

4. LANTAI UPPER GROUND

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.8 0.8 4.2 21.50 104.32 19 2.2257 4.96 24 2119.5786
K1C 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 24 1324.7366
K1D 7 0.8 0.8 4.2 18.82 91.28 19 2.2257 4.96 24 1854.6313
K1E 9 0.8 0.8 4.2 24.19 117.36 19 2.2257 4.96 24 2384.5260
K2 6 0.8 0.8 4.2 16.13 78.24 25 3.8534 5.20 20 2404.5216
K2A 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536
K3 11 0.8 0.8 4.2 29.57 143.44 25 3.8534 5.20 28 6171.6054
K3A 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 28 2805.2752
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 32 6.3134 5.48 40 19374.5619
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 239.06 1066.02 48864.2197

5. LANTAI 1st

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.8 0.8 4.2 21.50 104.32 19 2.2257 4.96 24 2119.5786
K1C 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 24 1324.7366
K1D 7 0.8 0.8 4.2 18.82 91.28 19 2.2257 4.96 24 1854.6313
K1E 9 0.8 0.8 4.2 24.19 117.36 19 2.2257 4.96 24 2384.5260
K2 6 0.8 0.8 4.2 16.13 78.24 25 3.8534 5.20 20 2404.5216
K2A 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536
K3 11 0.8 0.8 4.2 29.57 143.44 25 3.8534 5.20 28 6171.6054
K3A 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 28 2805.2752
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 32 6.3134 5.48 40 19374.5619
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 239.06 1066.02 48864.2197
6. LANTAI 2nd

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.6 0.6 4.2 12.10 78.24 19 2.2257 4.96 20 1766.3155
K1C 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K1D 7 0.6 0.6 4.2 10.58 68.46 25 3.8534 5.20 16 2244.2202
K1E 9 0.6 0.6 4.2 13.61 88.02 25 3.8534 5.20 16 2885.4259
K2 6 0.6 0.6 4.2 9.07 58.68 25 3.8534 5.20 20 2404.5216
K2A 1 0.6 0.6 4.2 1.51 9.78 25 3.8534 5.20 20 400.7536
K3 11 0.6 0.6 4.2 16.63 107.58 25 3.8534 5.20 28 6171.6054
K3A 5 0.6 0.6 4.2 7.56 48.90 25 3.8534 5.20 28 2805.2752
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 25 3.8534 5.20 40 11221.1008
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 177.91 896.50 41027.1949

7. LANTAI 3rd

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.6 0.6 4.2 12.10 78.24 19 2.2257 4.96 20 1766.3155
K1C 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K1D 7 0.6 0.6 4.2 10.58 68.46 25 3.8534 5.20 16 2244.2202
K1E 9 0.6 0.6 4.2 13.61 88.02 25 3.8534 5.20 16 2885.4259
K2 6 0.6 0.6 4.2 9.07 58.68 25 3.8534 5.20 20 2404.5216
K2A 1 0.6 0.6 4.2 1.51 9.78 25 3.8534 5.20 20 400.7536
K3 11 0.6 0.6 4.2 16.63 107.58 25 3.8534 5.20 28 6171.6054
K3A 5 0.6 0.6 4.2 7.56 48.90 25 3.8534 5.20 28 2805.2752
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 25 3.8534 5.20 40 11221.1008
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 177.91 896.50 41027.1949

8. LANTAI P1

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.6 0.6 4.2 12.10 78.24 19 2.2257 4.96 20 1766.3155
K1C 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K1D 7 0.6 0.6 4.2 10.58 68.46 25 3.8534 5.20 16 2244.2202
K1E 9 0.6 0.6 4.2 13.61 88.02 25 3.8534 5.20 16 2885.4259
K2 6 0.6 0.6 4.2 9.07 58.68 19 2.2257 4.96 20 1324.7366
K2A 1 0.6 0.6 4.2 1.51 9.78 19 2.2257 4.96 20 220.7894
K3 11 0.6 0.6 4.2 16.63 107.58 19 2.2257 4.96 20 2428.6838
K3A 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 25 3.8534 5.20 40 11221.1008
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 177.91 896.50 34323.1962

9. LANTAI P2

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.6 0.6 4.2 12.10 78.24 19 2.2257 4.96 20 1766.3155
K1C 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K1D 7 0.6 0.6 4.2 10.58 68.46 25 3.8534 5.20 16 2244.2202
K1E 9 0.6 0.6 4.2 13.61 88.02 25 3.8534 5.20 16 2885.4259
K2 6 0.6 0.6 4.2 9.07 58.68 19 2.2257 4.96 20 1324.7366
K2A 1 0.6 0.6 4.2 1.51 9.78 19 2.2257 4.96 20 220.7894
K3 11 0.6 0.6 4.2 16.63 107.58 19 2.2257 4.96 20 2428.6838
K3A 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 1 1 4.2 21.00 81.50 25 3.8534 5.20 40 4007.5360
K9 14 1 1 4.2 58.80 228.20 25 3.8534 5.20 40 11221.1008
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 177.91 896.50 34323.1962

10. LANTAI P3

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.6 0.6 4.2 12.10 78.24 19 2.2257 4.96 20 1766.3155
K1C 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K1D 7 0.6 0.6 4.2 10.58 68.46 25 3.8534 5.20 16 2244.2202
K1E 9 0.6 0.6 4.2 13.61 88.02 25 3.8534 5.20 16 2885.4259
K2 6 0.6 0.6 4.2 9.07 58.68 19 2.2257 4.96 20 1324.7366
K2A 1 0.6 0.6 4.2 1.51 9.78 19 2.2257 4.96 20 220.7894
K3 11 0.6 0.6 4.2 16.63 107.58 19 2.2257 4.96 20 2428.6838
K3A 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 20 1103.9472
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 40 4007.5360
K9 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 40 11221.1008
K10 4 1 1 4.2 16.80 65.20 32 6.3134 5.48 40 5535.5891
TOTAL 149.18 834.56 34323.1962

11. LANTAI TOP


TYPE DIMENSI TULANGAN UTAMA
JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K1 8 0.6 0.6 4.2 12.10 78.24 19 2.2257 4.96 20 1766.3155
K1D 7 0.6 0.6 4.2 10.58 68.46 25 3.8534 5.20 16 2244.2202
K2 6 0.6 0.6 4.2 9.07 58.68 19 2.2257 4.96 20 1324.7366
K3 11 0.6 0.6 4.2 16.63 107.58 19 2.2257 4.96 20 2428.6838
K4 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043
K8 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 40 4007.5360
K9 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 40 11221.1008
TOTAL 102.14 573.76 23473.4973

12. LANTAI OFFICE 1

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K8 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 28 1545.5261
K9 14 0.8 0.8 4.2 37.63 182.56 19 2.2257 4.96 28 4327.4730
TOTAL 51.07 247.76 5872.9991

13. LANTAI OFFICE 2

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K8 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 28 1545.5261
K9 14 0.8 0.8 4.2 37.63 182.56 19 2.2257 4.96 28 4327.4730
TOTAL 51.07 247.76 5872.9991

14. LANTAI OFFICE 3

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K8 5 0.8 0.8 4.2 13.44 65.20 19 2.2257 4.96 28 1545.5261
K9 14 0.8 0.8 4.2 37.63 182.56 19 2.2257 4.96 28 4327.4730
TOTAL 51.07 247.76 5872.9991

15. LANTAI OFFICE 4

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K8 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 24 1324.7366
K9 14 0.6 0.6 4.2 21.17 136.92 19 2.2257 4.96 24 3709.2626
TOTAL 28.73 185.82 5033.9992

16. LANTAI OFFICE 5

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K8 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 24 1324.7366
K9 14 0.6 0.6 4.2 21.17 136.92 19 2.2257 4.96 24 3709.2626
TOTAL 28.73 185.82 5033.9992

17. LANTAI OFFICE 6

TYPE DIMENSI TULANGAN UTAMA


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l
K8 5 0.6 0.6 4.2 7.56 48.90 19 2.2257 4.96 24 1324.7366
K9 14 0.6 0.6 4.2 21.17 136.92 19 2.2257 4.96 24 3709.2626
TOTAL 28.73 185.82 5033.9992

FORMULA

LANTAI BASEMENT

VOLUME ( f ) = bxcxdxe
BEKISTING ( g ) = b x ( 2c + 2d ) x ( e - 0.125 )
PANJANG ( j ) = e + 1 + 15 ( h / 1000 ) + 40 ( h / 1000 )
TOTAL ( l ) = bxlxjxk
PANJANG ( o ) = ( ( c - 0.08) + ( d - 0.08 ) ) x 2 + ( 2 x 4 ( m / 1000 ) )
TOTAL ( q ) = bxnxoxp

LANTAI LOWER GROUND S/D LANTAI TOP

VOLUME ( f ) = bxcxdxe
BEKISTING ( g ) = b x ( 2c + 2d ) x ( e - 0.125 )
PANJANG ( j ) = e + 40 ( h / 1000 )
TOTAL ( l ) = bxlxjxk
PANJANG ( o ) = ( ( c - 0.08) + ( d - 0.08 ) ) x 2 + ( 2 x 4 ( m / 1000 ) )
TOTAL ( q ) = bxnxoxp
SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.984 53 1318.3551
13 1.0420 2.984 53 329.5888
13 1.0420 2.984 53 823.9719
13 1.0420 2.984 53 1153.5607
13 1.0420 2.984 53 1483.1495
13 1.0420 2.984 53 823.9719
13 1.0420 2.984 53 988.7663
13 1.0420 2.984 53 164.7944
13 1.0420 2.984 53 1812.7382
13 1.0420 2.984 53 823.9719
13 1.0420 2.984 53 164.7944
13 1.0420 3.784 53 1044.8759
13 1.0420 3.784 53 2925.6526
13 1.0420 3.784 53 835.9007
14694.0923

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.960 42 613.1462
10 0.6165 2.960 42 153.2866
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 536.5030
10 0.6165 2.960 42 689.7895
10 0.6165 2.960 42 459.8597
10 0.6165 2.960 42 76.6433
10 0.6165 2.960 42 843.0761
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
6795.8335

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.960 42 613.1462
10 0.6165 2.960 42 153.2866
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 536.5030
10 0.6165 2.960 42 689.7895
10 0.6165 2.960 42 459.8597
10 0.6165 2.960 42 76.6433
10 0.6165 2.960 42 843.0761
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
6795.8335

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.960 42 613.1462
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 536.5030
10 0.6165 2.960 42 689.7895
10 0.6165 2.960 42 459.8597
10 0.6165 2.960 42 76.6433
10 0.6165 2.960 42 843.0761
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
6642.5470

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.960 42 613.1462
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 536.5030
10 0.6165 2.960 42 689.7895
10 0.6165 2.960 42 459.8597
10 0.6165 2.960 42 76.6433
10 0.6165 2.960 42 843.0761
10 0.6165 2.960 42 383.2164
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
6642.5470
SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.160 42 447.4310
10 0.6165 2.160 42 279.6444
10 0.6165 2.160 42 391.5022
10 0.6165 2.160 42 503.3599
10 0.6165 2.160 42 335.5733
10 0.6165 2.160 42 55.9289
10 0.6165 2.160 42 615.2177
10 0.6165 2.160 42 279.6444
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
5565.3982

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.160 42 447.4310
10 0.6165 2.160 42 279.6444
10 0.6165 2.160 42 391.5022
10 0.6165 2.160 42 503.3599
10 0.6165 2.160 42 335.5733
10 0.6165 2.160 42 55.9289
10 0.6165 2.160 42 615.2177
10 0.6165 2.160 42 279.6444
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
5565.3982

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.160 42 447.4310
10 0.6165 2.160 42 279.6444
10 0.6165 2.160 42 391.5022
10 0.6165 2.160 42 503.3599
10 0.6165 2.160 42 335.5733
10 0.6165 2.160 42 55.9289
10 0.6165 2.160 42 615.2177
10 0.6165 2.160 42 279.6444
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
5565.3982

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.160 42 447.4310
10 0.6165 2.160 42 279.6444
10 0.6165 2.160 42 391.5022
10 0.6165 2.160 42 503.3599
10 0.6165 2.160 42 335.5733
10 0.6165 2.160 42 55.9289
10 0.6165 2.160 42 615.2177
10 0.6165 2.160 42 279.6444
10 0.6165 2.960 42 76.6433
13 1.0420 3.784 42 828.0149
10 0.6165 3.760 42 1363.0075
10 0.6165 3.760 42 389.4307
5565.3982

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.160 42 447.4310
10 0.6165 2.160 42 279.6444
10 0.6165 2.160 42 391.5022
10 0.6165 2.160 42 503.3599
10 0.6165 2.160 42 335.5733
10 0.6165 2.160 42 55.9289
10 0.6165 2.160 42 615.2177
10 0.6165 2.160 42 279.6444
10 0.6165 2.960 42 76.6433
13 1.0420 2.984 42 652.9589
10 0.6165 2.960 42 1073.0059
10 0.6165 3.760 42 389.4307
5100.3406
SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
10 0.6165 2.160 42 447.4310
10 0.6165 2.160 42 391.5022
10 0.6165 2.160 42 335.5733
10 0.6165 2.160 42 615.2177
10 0.6165 2.960 42 76.6433
13 1.0420 2.984 42 652.9589
10 0.6165 2.960 42 1073.0059
3592.3322

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.984 42 652.9589
10 0.6165 2.960 42 1073.0059
1725.9648

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.984 42 652.9589
10 0.6165 2.960 42 1073.0059
1725.9648

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.984 42 652.9589
10 0.6165 2.960 42 1073.0059
1725.9648

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.184 42 477.9029
10 0.6165 2.160 42 783.0043
1260.9072

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.184 42 477.9029
10 0.6165 2.160 42 783.0043
1260.9072

SENGKANG
DIA BERAT PANJANG JUMLAH TOTAL
( mm ) ( kg/m ) (m) ( kg )
m n o p q
13 1.0420 2.184 42 477.9029
10 0.6165 2.160 42 783.0043
1260.9072
PERHITUNGAN VOLUME KOLOM ZONE B

1. LANTAI BASEMENT

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.8 0.8 4.2 45.70 221.68 19 2.2257 6.25 28 6616.1603 13 1.0420 2.984 53 2801.5045
K1A 3 0.8 0.8 4.2 8.06 39.12 19 2.2257 6.25 28 1167.5577 13 1.0420 2.984 53 494.3832
K1B 1 0.8 0.8 4.2 2.69 13.04 19 2.2257 6.25 28 389.1859 13 1.0420 2.984 53 164.7944
K2 18 0.8 0.8 4.2 48.38 234.72 32 6.3134 6.96 24 18982.6260 13 1.0420 2.984 53 2966.2989
K3 3 0.8 0.8 4.2 8.06 39.12 32 6.3134 6.96 32 4218.3613 13 1.0420 2.984 53 494.3832
K3A 17 0.8 0.8 4.2 45.70 221.68 32 6.3134 6.96 32 23904.0476 13 1.0420 2.984 53 2801.5045
K4 5 0.8 0.8 4.2 13.44 65.20 32 6.3134 6.96 24 5272.9517 13 1.0420 2.984 53 823.9719
K5 4 0.9 0.9 4.2 13.61 58.68 32 6.3134 6.96 44 7733.6625 13 1.0420 3.384 53 747.5391
K6 14 0.8 0.8 4.2 37.63 182.56 32 6.3134 6.96 36 22146.3971 13 1.0420 2.984 53 2307.1214
K7 1 0.8 0.8 4.2 2.69 13.04 32 6.3134 6.96 36 1581.8855 13 1.0420 2.984 53 164.7944
TOTAL 225.96 1088.84 92012.8357 13766.2955

2. LANTAI LOWER GROUND

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.8 0.8 4.2 45.70 221.68 19 2.2257 4.96 24 4504.1046 10 0.6165 2.960 42 1302.9358
K1A 3 0.8 0.8 4.2 8.06 39.12 19 2.2257 4.96 24 794.8420 10 0.6165 2.960 42 229.9298
K1B 1 0.8 0.8 4.2 2.69 13.04 19 2.2257 4.96 24 264.9473 10 0.6165 2.960 42 76.6433
K2 18 0.8 0.8 4.2 48.38 234.72 32 6.3134 5.48 24 14946.0906 10 0.6165 2.960 42 1379.5790
K3 3 0.8 0.8 4.2 8.06 39.12 32 6.3134 5.48 28 2906.1843 10 0.6165 2.960 42 229.9298
K3A 17 0.8 0.8 4.2 45.70 221.68 32 6.3134 5.48 28 16468.3776 10 0.6165 2.960 42 1302.9358
K4 5 0.8 0.8 4.2 13.44 65.20 32 6.3134 5.48 24 4151.6918 10 0.6165 2.960 42 383.2164
K5 4 0.9 0.9 4.2 13.61 58.68 32 6.3134 5.48 44 6089.1480 13 1.0420 3.384 42 592.3895
K6 14 0.8 0.8 4.2 37.63 182.56 32 6.3134 5.48 36 17437.1057 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 32 6.3134 5.48 36 1245.5076 10 0.6165 2.960 42 76.6433
TOTAL 225.96 1088.84 68807.9996 6647.2086
3. LANTAI GROUND

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.8 0.8 4.2 45.70 221.68 19 2.2257 4.96 24 4504.1046 10 0.6165 2.960 42 1302.9358
K1A 3 0.8 0.8 4.2 8.06 39.12 19 2.2257 4.96 24 794.8420 10 0.6165 2.960 42 229.9298
K1B 1 0.8 0.8 4.2 2.69 13.04 19 2.2257 4.96 24 264.9473 10 0.6165 2.960 42 76.6433
K2 18 0.8 0.8 4.2 48.38 234.72 25 3.8534 5.20 20 7213.5648 10 0.6165 2.960 42 1379.5790
K3 3 0.8 0.8 4.2 8.06 39.12 25 3.8534 5.20 24 1442.7130 10 0.6165 2.960 42 229.9298
K3A 17 0.8 0.8 4.2 45.70 221.68 25 3.8534 5.20 24 8175.3734 10 0.6165 2.960 42 1302.9358
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.9 0.9 4.2 13.61 58.68 32 6.3134 5.48 44 6089.1480 13 1.0420 3.384 42 592.3895
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 24 6732.6605 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043 10 0.6165 2.960 42 76.6433
TOTAL 225.96 1088.84 38102.7795 6647.2086

4. LANTAI UPPER GROUND

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.8 0.8 4.2 45.70 221.68 19 2.2257 4.96 24 4504.1046 10 0.6165 2.960 42 1302.9358
K1A 3 0.8 0.8 4.2 8.06 39.12 19 2.2257 4.96 24 794.8420 10 0.6165 2.960 42 229.9298
K2 18 0.8 0.8 4.2 48.38 234.72 25 3.8534 5.20 20 7213.5648 10 0.6165 2.960 42 1379.5790
K3 3 0.8 0.8 4.2 8.06 39.12 25 3.8534 5.20 24 1442.7130 10 0.6165 2.960 42 229.9298
K3A 17 0.8 0.8 4.2 45.70 221.68 25 3.8534 5.20 24 8175.3734 10 0.6165 2.960 42 1302.9358
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.9 0.9 4.2 13.61 58.68 32 6.3134 5.48 44 6089.1480 13 1.0420 3.384 42 592.3895
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 24 6732.6605 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043 10 0.6165 2.960 42 76.6433
TOTAL 223.27 1075.80 37837.8322 6570.5653
5. LANTAI 1st

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.8 0.8 4.2 45.70 221.68 19 2.2257 4.96 24 4504.1046 10 0.6165 2.960 42 1302.9358
K1A 3 0.8 0.8 4.2 8.06 39.12 19 2.2257 4.96 24 794.8420 10 0.6165 2.960 42 229.9298
K2 18 0.8 0.8 4.2 48.38 234.72 25 3.8534 5.20 20 7213.5648 10 0.6165 2.960 42 1379.5790
K3 3 0.8 0.8 4.2 8.06 39.12 25 3.8534 5.20 24 1442.7130 10 0.6165 2.960 42 229.9298
K3A 17 0.8 0.8 4.2 45.70 221.68 25 3.8534 5.20 24 8175.3734 10 0.6165 2.960 42 1302.9358
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.9 0.9 4.2 13.61 58.68 32 6.3134 5.48 44 6089.1480 13 1.0420 3.384 42 592.3895
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 24 6732.6605 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 24 480.9043 10 0.6165 2.960 42 76.6433
TOTAL 223.27 1075.80 37837.8322 6570.5653

6. LANTAI 2nd

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K1A 3 0.6 0.6 4.2 4.54 29.34 19 2.2257 4.96 20 662.3683 10 0.6165 2.160 42 167.7866
K2 18 0.6 0.6 4.2 27.22 176.04 25 3.8534 5.20 20 7213.5648 10 0.6165 2.160 42 1006.7198
K3 3 0.6 0.6 4.2 4.54 29.34 25 3.8534 5.20 24 1442.7130 10 0.6165 2.160 42 167.7866
K3A 17 0.6 0.6 4.2 25.70 166.26 25 3.8534 5.20 24 8175.3734 10 0.6165 2.160 42 950.7910
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.8 0.8 4.2 10.75 52.16 25 3.8534 5.20 32 2564.8230 10 0.6165 2.960 42 306.5731
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 20 5610.5504 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536 10 0.6165 2.960 42 76.6433
TOTAL 152.21 880.20 32228.0886 5083.3138
7. LANTAI 3rd

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K2 18 0.6 0.6 4.2 27.22 176.04 25 3.8534 5.20 20 7213.5648 10 0.6165 2.160 42 1006.7198
K3 3 0.6 0.6 4.2 4.54 29.34 25 3.8534 5.20 24 1442.7130 10 0.6165 2.160 42 167.7866
K3A 17 0.6 0.6 4.2 25.70 166.26 25 3.8534 5.20 24 8175.3734 10 0.6165 2.160 42 950.7910
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.8 0.8 4.2 10.75 52.16 25 3.8534 5.20 32 2564.8230 10 0.6165 2.960 42 306.5731
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 20 5610.5504 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536 10 0.6165 2.960 42 76.6433
TOTAL 147.67 850.86 31565.7203 4915.5271

8. LANTAI P1

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K2 18 0.6 0.6 4.2 27.22 176.04 19 2.2257 4.96 20 3974.2099 10 0.6165 2.160 42 1006.7198
K3 3 0.6 0.6 4.2 4.54 29.34 19 2.2257 4.96 20 662.3683 10 0.6165 2.160 42 167.7866
K3A 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.8 0.8 4.2 10.75 52.16 25 3.8534 5.20 24 1923.6173 10 0.6165 2.960 42 306.5731
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 20 5610.5504 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536 10 0.6165 2.960 42 76.6433
TOTAL 147.67 850.86 22482.8621 4915.5271
9. LANTAI P2

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K2 18 0.6 0.6 4.2 27.22 176.04 19 2.2257 4.96 20 3974.2099 10 0.6165 2.160 42 1006.7198
K3 3 0.6 0.6 4.2 4.54 29.34 19 2.2257 4.96 20 662.3683 10 0.6165 2.160 42 167.7866
K3A 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.8 0.8 4.2 10.75 52.16 25 3.8534 5.20 24 1923.6173 10 0.6165 2.960 42 306.5731
K6 14 0.8 0.8 4.2 37.63 182.56 25 3.8534 5.20 20 5610.5504 10 0.6165 2.960 42 1073.0059
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536 10 0.6165 2.960 42 76.6433
TOTAL 147.67 850.86 22482.8621 4915.5271

10. LANTAI P3

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K2 18 0.6 0.6 4.2 27.22 176.04 19 2.2257 4.96 20 3974.2099 10 0.6165 2.160 42 1006.7198
K3 3 0.6 0.6 4.2 4.54 29.34 19 2.2257 4.96 20 662.3683 10 0.6165 2.160 42 167.7866
K3A 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.8 0.8 4.2 10.75 52.16 25 3.8534 5.20 24 1923.6173 10 0.6165 2.960 42 306.5731
K6 14 0.6 0.6 4.2 21.17 136.92 19 2.2257 4.96 20 3091.0522 10 0.6165 2.160 42 783.0043
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536 10 0.6165 2.960 42 76.6433
TOTAL 131.21 805.22 19963.3638 4625.5255
11. LANTAI TOP

TYPE DIMENSI TULANGAN UTAMA SENGKANG


JUMLAH VOLUME BEKISTING
KOLOM p l t DIA BERAT PANJANG JUMLAH TOTAL DIA BERAT PANJANG JUMLAH TOTAL
(m) (m) (m) ( m3 ) ( m2 ) ( mm ) ( kg/m ) (m) ( kg ) ( mm ) ( kg/m ) (m) ( kg )
a b c d e f g h I j k l m n o p q
K1 17 0.6 0.6 4.2 25.70 166.26 19 2.2257 4.96 20 3753.4205 10 0.6165 2.160 42 950.7910
K2 18 0.6 0.6 4.2 27.22 176.04 19 2.2257 4.96 20 3974.2099 10 0.6165 2.160 42 1006.7198
K3 3 0.6 0.6 4.2 4.54 29.34 19 2.2257 4.96 20 662.3683 10 0.6165 2.160 42 167.7866
K4 5 0.8 0.8 4.2 13.44 65.20 25 3.8534 5.20 24 2404.5216 10 0.6165 2.960 42 383.2164
K5 4 0.8 0.8 4.2 10.75 52.16 25 3.8534 5.20 24 1923.6173 10 0.6165 2.960 42 306.5731
K7 1 0.8 0.8 4.2 2.69 13.04 25 3.8534 5.20 20 400.7536 10 0.6165 2.960 42 76.6433
TOTAL 84.34 502.04 13118.8912 2891.7302

FORMULA

LANTAI BASEMENT

VOLUME ( f ) = bxcxdxe
BEKISTING ( g ) = b x ( 2c + 2d ) x ( e - 0.125 )
PANJANG ( j ) = e + 1 + 15 ( h / 1000 ) + 40 ( h / 1000 )
TOTAL ( l ) = bxlxjxk
PANJANG ( o ) = ( ( c - 0.08) + ( d - 0.08 ) ) x 2 + ( 2 x 4 ( m / 1000 ) )
TOTAL ( q ) = bxnxoxp

LANTAI LOWER GROUND S/D LANTAI TOP

VOLUME ( f ) = bxcxdxe
BEKISTING ( g ) = b x ( 2c + 2d ) x ( e - 0.125 )
PANJANG ( j ) = e + 40 ( h / 1000 )
TOTAL ( l ) = bxlxjxk
PANJANG ( o ) = ( ( c - 0.08) + ( d - 0.08 ) ) x 2 + ( 2 x 4 ( m / 1000 ) )
TOTAL ( q ) = bxnxoxp

You might also like