COMMENTS REV. DATE DESCRIPTION DESIGNED CHECKED APPROVED NO.
CLIENT:
CEYLON ELECTRICITY BOARD
SRI LANKA
LOA NO.: PROJECT TITLE:
CEB / PM / KK / 220TR / TEC KERAWALAPITIYA – KOTUGODA TRANSMISSION – LOT B DATED 19.02.2007 PROJECT – LOT B, 220KV TRANSMISSION LINE OECF LOAN NO.: SL – P78 BETWEEN KERAWALAPITIYA AND KOTUGODA KEC WORK ORDER NO.: N41 ENGINEER: IN ASSOCIATION WITH: CONTRACTOR: KEC INTERNATIONAL LIMITED, GURGAON, HARYANA, INDIA APPROVED BY THE ENGINEER ON SCALE: STANDARD
DATE NAME TITLE OF DRAWING:
ESTABL. “S2” TYPE FOUNDATION
CHECKED FOR 1M RAISED CHIMNEY FOR APPROVED “TD3 –3M, +0M, +3M, +6M, +9M & +12M” TOWERS DATE DRAWING NO. PAGES REV D S – 1 3 0 1 11 A