Professional Documents
Culture Documents
SLAB TRACK
SYSTEM ÖBB–PORR ELASTICALLY SUPPORTED TRACK BASE PLATE
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 2
The slab track (ST), system ÖBB–PORR elastically supported Production is made in a prefabrication plant and/or a field
track base plate, has been jointly developed by the Austrian plant and is therefore independent of weather conditions. Due
Railway Corporation (ÖBB) and Allgemeine Baugesellschaft – to a complete quality assurance system a constant high qual-
A. Porr AG. Since 1995 it has been the obligatory system in ity is guaranteed and documented. The used steel formworks
Austria and since 2001 it has also been used in the construc- are adjustable and so they completely cover all radii ranges.
tion of bridges and tunnels in Germany. No problems have Reductions, block outs, coverings, dowels etc. can be fore-
occurred on the tracks already in operation, covering a dis- seen with millimetre accuracy using adequate layers. Due to
tance of approximately 100 km. The oldest section has been the “just-in-time-principle” storage place is as a rule provided
in operation for 17 years without maintenance and service in the company plant only. From there the track base plates
costs. are normally transported to their destination by wagon. The
5 t heavy plates are fastened using a special traverse grab-
TRACK BASE PLATE (TP) bing into the grouting opening. Each of the track base plate
types is unmistakably marked with a corresponding bar code
CONSTRUCTION
set in concrete and can therefore be easily identified at any
The principal element of this system is the elastically supported time if intermediate storage is necessary. The unloading is
track base plate. The track-base-plate-system ÖBB–PORR is handled with the necessary unloading equipment (portal
based on a 5,16 m long pre-fabricated reinforced concrete crane or lorry with crane) or with any other lifting device if
plate with untensioned reinforcement. Thus eight pairs of intermediate storage is essential.
supporting points type Vossloh 300-1 are integrated at inter-
vals of 65 cm. The sole of the plate as well as the tapered
grouting openings are provided with an elastic layer for
decoupling. This results in a reduction in the vibrations emit-
ted into the foundation (damping of structure-borne noise).
The system weighs 1 t per linear meter and is therefore a light
mass-spring-system.
2
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 3
2 2
track base plate chequer plate 7/9 zinc-dipped
8 16 23
The slab track system ÖBB–PORR elastically supported track
base plate, is built on a solid or low-subsidence base struc- concrete subbase
18 18
-0.47
ture such as, for example, a tunnel invert, bridge construction 1.836
structure height up to the upper edge of the track is 60 E1 tubbing segment -1.55
(E2) > 47,3 cm. Through the tapered grouting openings a
drainage piping
positive locking compound of the track base plate and the incline concrete
2.400
Vertical loads
60E1(E2)
elastic
640 upper edge of
the track 0.00 Freight train UIC 71
concrete joint
track bed
sealing compound
Heavy load train SW 0 acc. UIC 776-1E
Speed v = 250 km/h (A) respectively v = 330 km/h
393
160 80
≥473
240
3
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 4
MODE OF OPERATION
The bedding necessary for the load distribution on the track is
guaranteed by the elasticity of the track mounting. In addition
the elastic rubber granulate layer, amounting to approximate-
ly 10 % of the total elasticity, has the effect that high forces are
well distributed and causes a reduction of the stress in the
multi-layered system.
Portal crane
Bedding of the supporting points and track base plates under traffic load
bedding measured in 6 MP /
calculated according to stress application
0,00
-0,50
-1,00
-1,50
bedding in mm
-2,00
-2,50
-3,00
-3,50
Laying of track base plates with lorry
-4,00
MP1 MP2 MP3 MP4 MP5 MP6 MP7 MP8 MP9 MP10 MP11 MP12
free bearing
stressed track
In any case, the track base plates are being laid at the desti-
under consideration for plate bedding
nation with an accuracy of + 1 cm in order to minimize the
work needed to adjust them.
Laying of under traffic load
PRODUCTION
Adjustment of tracks
Laying
After the partial spreading of the tracks positioned at the side,
The laying of the track base plates, which have a width of just the work of adjusting the final track begins by using a M36-
2,40 m (2,10 m), is normally done with portal cranes. This spindle. This method guarantees precise track set accuracy in
enables the plates to be lifted forwards in the smallest possi- setting the track requiring no further correction.
ble space. In addition, no reloading or intermediate storage is
necessary, because the plates can be taken directly from the Adjustment work is further reduced by an adequate track
transport wagon. In the case of islands or missing track con- geometry of the track base plates. Therefore the time involved
nection, the take over and the laying of the track base plates for the adjustment is reduced by up to 50 % in comparison to
by lorry with loader arm is the usual practice. other slab track systems.
4
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 5
DAMAGE CONCEPT
A further advantage of the elastic layer is its separation from
the concrete. Therefore the two tapered grouting openings,
which prevent a lift off of the track base plate, can be cut free
or chiselled out and the track base plates can be replaced
separately within three to four hours.
Measurement of track positioning with track measurement wagon
Concrete
According to the space available, the concrete joint sealing
compound is applied either directly or through a hose pump
up to a maximum of 500 m. The use of a self-compacting con-
crete joint sealing compound enables a holohedral embedding
of the track base plate. As a result of the vibration-free concret-
ing process (without vibrator), the fine-tuning of the track unit
is not affected. Furthermore, it is possible for these slab tracks
to be installed in a short railway block (example: East-West-
Connection Berlin 2002) due to the fast setting process of the
scc-concrete. The concrete joint sealing compound is ade-
quately reinforced in order to limit wide cracks.
Concreting of track base plate with scc (self compacting concrete) Lifting – top view – longitudinal section
5
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 6
Balast
2%
Ballast
Concrete blocks
1.600 1.700
Ballsting
Track base plate
+0,18
SOK ±0.00
45.5 32.5
78.0
-0.60
Shield section – Sectional view Berlin – Main station – Lehrter railway bridges with slab track
6
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 7
Essential differences occur due to the rather high deforma- EARTH STRUCTURE
tion, by disfigurement or shrinkage, caused by temperature
differences, subsidence, or traffic loads as well as creep and The laying of earth structures is done on a load distribution
shrinkage. Especially at the bridge joints deformations can plate or a hydraulically bond supporting layer. Based on the
cause unacceptably high track tension and lifting of track sup- high degree of prefabrication of the track base plates and the
porting points. In such cases special track-crossing construc- relatively small grouting openings, quality influences due to
tions are necessary in order to reduce deformations to an weather conditions are kept fairly low. This also applies to
acceptable extent. For example, on the 25 bridge girder sys- mounting on bridge constructions.
tems of the east-west-connections, a total of 50 special track-
crossing constructions were built, and twelve joining areas
were directly built over with slab tracks (on extensive sliding
bearings).
Track axle
Concrete joint
Partial sealing
comound Upper edge
drainage pipe Absorbing plates
Rail axle
of track Bitumen cating
made of concrete ± 0,00
DN 200 drainage material Balast,
Longitudinal member ballast granulate 1
Track 60E1(E2) washed
Track base plate
Track base plate A Cross member
2:3
49 Steel concrete distribution
plate d = 30 cm -0.80
6%
20 2.40 20
Soil exchange
Bitumen cating
Elastically supported
WU concrete (C25/30) track base plate
210 210
A
Open section – cross section
Track crossing construction (track support structure) Slab track – Open section
7
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 8
Track axle
In case of increased demands on protection against structure-
Concentric noise absorber
borne noise, the system can be layered on a mass spring Track base plate
trough (example: cross section mass spring system in tunnel) Concrete joint sealing compound
Elastomer mat
or in case of lower construction heights, directly on the exten- Supporting Noise absorber at the
sive elastomer support (example: cross section mass spring structure edges
Due to the low height of the system (> 47,3 cm), mass spring
systems without troughs can be produced for low construc-
tion heights, for example 25 Hz on approximately 50 cm. On
the bridges of the main station Lehrter Bahnhof, a softer elas-
tomer was applied in the centre of the concrete blocks area,
unlike in the side areas, in order to avoid punching.
8
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 9
Noise absorber
Section A-A
Guard rail
Track magnet Thread rod Adapter plate
Compensating plate
Anchorage device
Elastomer base plate
Base plate
Elastomer
base plate
Section B-B
Blockage
Conductor rail support REHAU
height adjustable Adapter plate
Adapter plate
Elastomer base plate
Compensation plate
B
A
Additional equipment of the track slab system ÖBB-PORR – sectional view + top view
9
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 10
Transition from ballast to slab track system, “track base plate with the ÖBB regulation RZ no. 17220. The ballast area is
ÖBB–PORR”, is carried out according to the standard cata- solidified by the use of a well-tried procedure with synthetic
logue for building slab tracks (4th edition) or in accordance resin.
Österreich RZ 17220
6.5
Track base plate
Upper edge
Upper edge Elastic bond ballast
of foundation
of foundation
Slabtrack Ballast
60 60 60
2.400
2.800
A A B B
65 65 60 60
Elastically bonded ballast 30.00 m - 35.00 m
Surface bonding includes strip along sleeper ends, 0.2-0.3 m wide and 0.2-0.3 m deep
30.00 m - 35.00 m
Transition area slab track / ballast (Germany) – longitudinal section, top view + sectional view
10
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 11
REFERENCES REFERENCES
Finally, the ÖBB–PORR slab track system, is impressive parts and because its application has now been maintenance-
because of the visible concrete quality of the prefabricated free for over 17 years.
Galgenbergtunnel 1996/1997 New tunnel construction, light mass spring system, bridge 11.040 m
Römerbergtunnel 1997 New tunnel construction, light and medium mass spring system 638 m
Zammertunnel 1998/1999 New tunnel construction, light and medium mass spring system 4.477 m
Kaponigtunnel 1999 New tunnel construction and bridge, light mass spring system 11.170 m
Wolfsgrubentunnel/Arlbergtunnel 1999/2000 New tunnel construction, medium mass spring system 3.730 m
S7-Rennweg Airport 2001/2002 New tunnel construction, medium mass spring system 3.250 m
Lehrter Bahnhof 2001/2002 Bridges/light mass spring system track base plate on 4.690 m
(east-west-connection) slide bearings 50 joint crossing constructions
Lehrter Bahnhof 2002/2006 New tunnel construction / light, medium and heavy 8.944 m
(north-south connection) and heavy mass spring system / big block outs
Birgl- and Kennlachtunnel 2004 New tunnel construction and light mass spring system 2.650 m
Pistentunnel S7 2005 New tunnel construction, medium and heavy mass spring system 1.412 m
TOTAL 124.038 m
11
70270 Feste Fahrbahn Englisch 16.02.2007 12:26 Uhr Seite 12
Fotos: PORR-Archiv
ABAP Ref. 317B / 02.07 / 0,25 M
The reference brochures of the PORR Group (from ABAP Nr. 217 on) can be downloaded from www.porr.at