Professional Documents
Culture Documents
Build120 25 BuildRight RetainingWalls PDF
Build120 25 BuildRight RetainingWalls PDF
RETAINING WALLS
Even low retaining walls can be exposed to large forces from
water, the earth behind them and nearby cars or buildings.
They need to be well designed and built to prevent failure.
By Alide Elkink, Freelance Technical Writer, Wellington
A
retaining wall is built to hold back a a combination, or using a proprietary, pre- with the tensile and compressive strengths of
bank of earth where there is a change cast concrete block system (see Figures 2 the construction material used (see Figures 4
of grade. There are different types of and 3). Proprietary systems either consist of and 5).
retaining walls, and not all require interlocking blocks or require the hollow section Wide-footing cantilever retaining walls may
a building consent. A retaining wall must be of the blocks to be filled with soil for stability. be built using in situ, reinforced concrete or
designed to: Another type of gravity wall is the crib retaining precast masonry blocks.
❚❚ support the lateral load or pressure of the wall, which comprises a system of interlocking Embedded footing cantilever walls may be
earth or fill behind it and any applied loads, header and stretcher blocks to retain the granular built from round or square H5-treated timber
such as cars or structures, so the wall does fill that provides the mass to the wall. or precast concrete poles or I-beams. Poles are
not tip over Both proprietary block and crib retaining walls typically spaced between 900 and 1,800 mm
❚❚ prevent water build-up behind or below the must be built on an in situ concrete foundation and set in concrete (see Figure 5). Horizontal
wall, which will increase the lateral pressure or on a compacted base course. The walls are rails of either H5-treated half-round logs or
as well as reduce the wall’s bearing capacity angled back towards the top: timber or precast concrete planks are installed
and resistance to sliding. ❚❚ Proprietary block systems have each row of behind the poles (see Figure 4).
blocks stepped back from the previous row.
When is a building consent needed? ❚❚ Crib walls are laid with a 1:4 batter. Drainage essential
Under Schedule 1 of the Building Act 2004, the CANTILEVER WALLS A build-up of water behind the wall is the
construction of a retaining wall does not require Cantilever walls rely for stabilisation either on a principal cause of retaining wall failure. Good
a building consent when it is less than 1.5 m wide ‘T’ or ‘L’-shaped footing or vertical poles piped drainage that disposes of water away
high and ‘does not support any surcharge or deeply embedded into the ground, combined from behind the wall to limit this build-up of
any load additional to the load of that ground
(for example, the load of the vehicles on a road)’.
Retaining walls that are over 1.5 m high and
those supporting a surcharge require a building
mass concrete, may have
consent (see Figure 1). stone rubble or brick facing
surcharge
Regardless of whether a building consent
300 mm 1.5 m, no surcharge
is required, retaining walls must comply with
the requirements of the New Zealand Building
Code clause B1 Structure: B1.2, which states
1.5 m granular fill
‘Buildings, building elements and siteworks maximum
shall withstand the combination of loads that 1.5 m
maximum geotextile filter
they are likely to experience during construction
45°
or alteration and throughout their lives.’ weepholes at
600–800 mm
zone of
Types of retaining walls 200 mm
influence
slotted drain
The two principal types of retaining walls are: 450 mm with fall
draining to
❚❚ gravity 100 mm 100 mm soak pit,
❚❚ cantilever. watercourse
compacted base or stormwater
course system
GRAVITY WALLS
Gravity walls rely on their mass to withstand
the pressure of the soil behind. They may
be constructed from concrete or stone or Figure 1: Surcharge and zone of influence. Figure 2: Mass concrete or rubble gravity retaining wall.
200 mm concrete
blockwork with fully
precast concrete or grouted cells to
timber crib wall laid to 150 pole at 1:10 batter
topsoil NZS 4229
a batter of 1:4 rails or half at 900 mm centres
rounds
topsoil
height in accordance vertical reinforcing
with manufacturer’s 60 mm cover to filled
requirements side
filter cloth granular fill maximum ground
horizontal retained to
stretcher
reinforcing manufacturer’s
granular fill granular fill geotextile filter requirements
header drainage
excavated metal ground
face weepholes drain with fall
granular fill draining to soak
geotextile filter geotextile filter pit, watercourse or
stormwater system
17 MPa
concrete
Figure 3: Proprietary concrete or timber crib walling. Figure 4: Example of cantilever concrete block retaining wall Figure 5: Cantilevered timber pole retaining wall.
with ‘L’-shaped footing.
WAT1