Construction Permits in Cambodia

Introduction a construction permit. This raises the issue


of whether these works are considered as
Due to strong economic growth, several sectors
Table of contents “construction”. Without a legal instrument
in Cambodia have seen rapid development, with
defining “construction”, there is no distinction
notably the construction industry now booming,
• Construction Permits between construction, reconstruction, expansion,
on the back of high demand. Referring to the
in Cambodia or floor additions. Consequently, details in article
annual report on work Implementation, and the
2 of the sub- decree state that a building owner is
Ministry of Land Management’s, (MLMUPC)
required to obtain a construction permit for any of
authors 2016 Working Plan, the construction industry has
these activities, and that any construction must be
created between 200,000 and 250,000 jobs, at all
carried out, in compliance with relevant laws and
• San Vattanak Visal skill levels.
regulations, and in the interest of public safety and
Legal Associate
During this period, the MLMUPC also noted well-being. Although, some types of modification
• Tok Thavsothaly an increase in the number of building license to a building may require a construction permit,
Legal Associate requests, as shown below: this does not apply to all construction activities.

• Delivery of construction permits: Some construction projects do not require a


permit. For example, dwellings located in rural
Construction permits, worth US$3,338 million
areas, or places far from highways, railroads,
granted for 2,305 projects, covering a total area of
tourism resorts, national heritage sites or protected
7,686,112 square meters
areas. Sub -decree # 86 provides details concerning
• Delivery of renovation, opening, and closing constructions that are not subject to a permit.
building permits:
As building activities affect public safety and well-
- 111 opening permits being, construction permit requests involve the
following documents and procedures:
- 55 closing permits
How long does it take to apply for a construction
- 10 renovation permits
permit?
With this increase in numbers, the government
Deciding what procedures, and which competent
has been working to adopt appropriate legal
authorities, to address when applying for a
instruments governing the construction sector,
construction permit, will depend on the size
with particular emphasis on safety measure.
of the construction project, (refer to decision
Until now, sub-decree 86 has been the principal
No. 5, relating to ‘Procedures of construction
legal instrument deployed in the granting of
permit application review and approval’, dated 06
construction permits. In the following paragraphs,
February 2006).
details of this decree are examined, together with
several other legal instruments, and construction The Provincial and Municipal Administration is the
permit information for building owners. competent authority for the issue of construction
permits for the area under its authorization. These
What kind of construction requires a permit?
are then duly signed either by a government
A question often posed is whether renovation, delegate, the provincial or municipal governor, or
No 65B, St 111 re-construction, or modifications to an an appointed vice governor.
existing building requires the owner to obtain
PO Box 172 The standard MLMUPC application form,
Phnom Penh along with the supporting documents, must be
completed in Khmer, and submitted at Sangkat
Cambodia Level, Khan Level, and to the Phnom Penh
+855 23 217 510 Municipal Department of Land Management. This
may take 30 days, although according to current
+855 23 967 450
practice, around 4 to 6 months is more likely.
+855 23 212 840
In accordance with article 5 of sub Decree No.
cambodia@bnglegal.com 86, some constructions have come under the
www.bnglegal.com jurisdiction of the government authority. These
applications take an additional 15 days for

© BNG Legal 2016 September 2016 Newsletter Page 1


MLMUPC’s review and approval. apply to the Department of Urbanization and
About us
Construction and the provincial/municipal land
For example, industrial and commercial buildings
office.5
BNG Legal is a leading regional law over 3,000 square meters, hotels that are considered
firm providing comprehensive legal as commercial buildings, or building used for The MLUC has the competence to issue business
services to foreign and local clients agricultural exploitations over 500 hectares. licenses, close and suspend a business, and
in Cambodia and Myanmar. to check and follow up all business activities.
How long is the construction permit valid for?
Whereas the Department of Land Management,
Registered with the Bar Association
Although a construction permit shall cease to be Urbanization and Construction is in charge of
of the Kingdom of Cambodia,
valid, if works have not been undertaken within a coordinating to make request to the Ministry for
our legal professionals combine
period of one year from the date of signing on the decision on the issuing of letter of authorization
international standards with local
construction permit, it can be renewed once.1 to open, close or suspend the business activities of
expertise.
Architectural design and construction enterprises
This means that either construction starts within
We differentiate ourselves by and companies. These offices also follow up and
one year from the permit signing date, or the
coupling a deep understanding of check construction activities on site, and may
building owner renews the permit validity, if the
the local business environment with submit reports to the Ministry for examination or
work has not been undertaken within that period.
international professionalism and settlement.
Otherwise, the owner is required to re-apply for a
integrity.
new permit. Letter of authorization to operate as an
We facilitate business, investment architectural design business
Construction is considered to have begun once
and trade between Cambodia,
the foundation bases are completed. For floor This authorization letter is valid for 3 years from
Myanmar, and the rest of the
additions, the construction shall be deemed begun the day of issue. Should a renewal be required, the
world through innovative and cost-
when the first pole is completed. In cases where enterprises or company shall apply 30 days before
effective legal services.
construction has been suspended for more than the expiration date.
Superior knowledge of local one year, the permit holder can be required to
ii. Location Site
protocol, local procedure, and local either, complete the construction, or demolish the
people is necessary for any business constructions at a determined date, and bear any The location, type, and size of the construction
to succeed. expenses incurred. need to be taken into consideration to ensure
the well-being, and safety of the public, and to
Conducting daily business in What other requirements are necessary to comply
avoid any environmental nuisance or potential
Cambodia and Myanmar, BNG with construction regulations?
disaster. Dangerous places such as landslide, wet
Legal is up to date with the newest
To fully comply with construction regulations region, which are not firm enough for building
procedures and requirements,
requires not only prior to construction, but also and any construction, are prohibited, as well as
helping clients efficiently and
during the construction as well as construction construction sites causing noise pollution.6
successfully complete any project.
completion.
Besides the construction site itself, other factors
a. Prior to construction such as suitable access and parking need to be taken
Cambodian Law Blog into account. It must also be noted that resorts
i. Legitimacy of Architect and Engineer
and historical heritage sites are preserved from
cambodianlaw.wordpress.com All enterprises and companies of architectural any construction. In fact, construction activities
design and construction, having activities are required have appropriate land access, both
BNG Legal believes expanding
throughout the Kingdom of Cambodia, shall be public and private roads, paths or cross roads, in
access to legal information is crucial
placed under the competence of the Ministry proportion to the size, or use, of the building.
to rule of law. To that end, several of
of Land Management, Urbanization and
our legal professionals write a blog However, construction will be not permitted,
Construction.2
discussing recent developments in despite respecting the conditions above, if the
the legal landscape. Architectural design enterprises and companies activity is likely to affect the preservation, or
are divided into four categories, and classified as beauty, of a natural, historic heritage site, or
enterprises, companies or natural persons.3 antique vestiges.
legal database
Construction enterprises and companies are iii. Construction Conditions
The laws and regulations in our divided into four categories, with a classification
database are based upon the Official as enterprise, company or group of constructors. 4 Any construction must respect the border between
Gazettes, law compendiums and plots; meaning that construction will be made ei-
All enterprises and companies planning to carry ther next to the border , with a common wall, or
other collections from the ministries
out architectural or construction activities shall a minimum of two meters away from the border.
and institutions of the Royal
submit a business license application to the MLUC, Moreover, this two meters space shall be left va-
Government of Cambodia. These cant without any construction.7
whilst natural persons and groups of constructors
are available to the public through Furthermore, any construction requiring a con-
our partner site, www.bnglaw.net. 1. Article 16 of the Sub Decree No. 86 on Construction Permits, dated 19 struction permit is required to make available a
December 1997
supply of clean water and a sewage drainage sys-
2. Article 1 of Prakas No. 75 on Management of Blueprint Design and tem.
Construction Companies and Entreprises, dated 02 September 1999
5. Article 1 of Prakas No. 75 on Management of Blueprint Design and
3. Article 2 of Prakas No. 75 on Management of Blueprint Design and Construction Companies and Entreprises, dated 02 September 1999
Construction Companies and Entreprises, dated 02 September 1999 6. Article 27 of the Sub-Decree No. 86 on Construction Permits, dated 19
December 1997
4. Article 2 of Prakas No. 75 on Management of Blueprint Design and 7. Article 34 of the Sub Decree No. 86 on Construction Permits, dated 19
Construction Companies and Entreprises, dated 02 September 1999 December 1997

© BNG Legal 2016 September 2016 Newsletter Page 2


About us A supply of clean water shall be ensured to all ii. Construction Closing Permit
construction plots, and if there is not a mains
As per circular No. 01, after certifying the
BNG Legal is a leading regional law connection to the anticipated construction area,
construction, the construction owner must apply
firm providing comprehensive legal the applicant shall show evidence that it is able
for a construction-closing permit, at the MLMUPC
services to foreign and local clients supply sufficient cleaning water to its buildings.
or the Municipal/Provincial Department of Land
in Cambodia and Myanmar. In cases where there is no connection to a main Management, Urban Planning, Construction and
Registered with the Bar Association sewage system, the construction owner has Cadastre. It may take 6 days for reviewing and
of the Kingdom of Cambodia, the obligation to make provisions to treat and approval on the application of the construction-
our legal professionals combine evacuate sewage water through a septic tank and a closing permit.
international standards with local subterranean filtering system.
Conclusion
expertise. A construction permits shall be denied if it
Due to rapid construction growth, we note that
We differentiate ourselves by does not present sufficient assurance of hygiene
in practice, once construction is completed,
coupling a deep understanding of and health of the projected construction and
some construction owners do not apply for a
the local business environment with surrounding existing constructions.
construction-closing permit, as officials do not
international professionalism and iv. Construction Start up Permit fully control these issues. We note that, although
integrity. according to law, construction sites shall be
In order to be legally compliant, along with the
We facilitate business, investment inspected and controlled for compliance to the
construction permit, the building owner needs to
and trade between Cambodia, permit, the effectiveness of this inspection by
take obtain all the other relevant permits. Within
Myanmar, and the rest of the officials is still a concern.
one month, after receiving the construction
world through innovative and cost- permit (article 3 of Prakas No. 32 construction We refer to the letter dated April 19, 2016 written by
effective legal services. management), the construction owner must apply the Secretary of State of the MLMUPC, addressing
Superior knowledge of local for a construction site start up permit, prior to the current challenging issues in the construction
protocol, local procedure, and local opening the construction site. sectors, namely the lack of the management,
people is necessary for any business technical inspection on the implementation
Applications need to be submitted at the MLMUPC,
to succeed. at the site, the lack of the management on the
or the Municipal/Provincial Department of Land
construction professionals, and the lack of the
Conducting daily business in Management, Urban Planning, Construction and
technical officials. These issues shall be considered
Cambodia and Myanmar, BNG Cadastral.
and settled in the ministerial strategic plans.
Legal is up to date with the newest b. During the Construction
procedures and requirements,
helping clients efficiently and Control and inspection by relevant authorities
successfully complete any project. During the construction period, the municipal
and provincial administration can at all time
to visit and control worksites and inspect the
Cambodian Law Blog approved plans. In case that they observe any
irregularities, they shall notify them in writing
cambodianlaw.wordpress.com to the contractor and requested that they are
BNG Legal believes expanding remedied within a determined period. In the event
access to legal information is crucial of non-compliance or incomplete compliance
to rule of law. To that end, several of with the orders received, an immediate work
our legal professionals write a blog suspension shall be ordered by the Municipal or
discussing recent developments in provincial administration.
the legal landscape. c. Construction Completion
i. Certificate of Compliance
legal database The construction permit recipient must notify
The laws and regulations in our completion of works to the chief of “Khan, or Srok”,
database are based upon the Official so that the competent authorities can ascertain the
Gazettes, law compendiums and conformity between the finished construction and
other collections from the ministries the construction as specified in the authorized
and institutions of the Royal construction permits. After that, the construction
Government of Cambodia. These owner must apply for the certificate of compliance.
are available to the public through Such certificate shall be mandatory as per provision
our partner site, www.bnglaw.net. of the article 21 of the Sub Decree No. 86.
8. Article 31 of the Sub Decree No. 86 on Construction Permits, dated 19

December 1997

9. Article 20 of the Sub Decree No. 86 on Construction Permits, dated 19

December 1997