You are on page 1of 1

Day 1 Look through the site plan, architectural plan and structural plans.

Site walk by following site supervisors (John, Shahril, Riduan)


Wear harness, helmet and boots
Day 2 Learn Pre RFI
Check and inspect the column formwork using plumb bob
Subcon meeting
18/ 6/ 2018 Clear water, check and inspect rebar for beams
19/ 6/ 2018 Look BQ, post RFI, supervise slab casting, clearing water
20 Check cracking, verticality, ask labours to fill up the cracks using
combextra, inspect beam rebar

Learn water tank, capacity and case study


21/ Subcon meeting
Check cracking
22/ Water clearance
23 Looking schedule of column
25 Water clearing
Housekeeping
Post RFI
Site Walk with Main Con
IJM Strong Mixed come check and discuss on cracking
Subcon meeting with concretor and carpenter
Environmental officer from IJM come inspect
Zoning for surveillance of mosquito breeding