You are on page 1of 4

Welded splices of

reinforcing bars
Both contractor and engineer must be aware of special requirements

BY DAVID P. GUSTAFSON
TECHNICAL DIRECTOR
CONCRETE REINFORCING STEEL INSTITUTE

roper splicing of reinforcing bars is crucial to Thus, if lap splices are not permitted or are impracti-

P the integrity of reinforced concrete. The ACI


Building Code1 states: “Splices of re i n f o rc e-
ment shall be made only as required or permit-
ted on the design drawings, in the specifications, or as
authorized by the engineer.” Great responsibility for de-
cal to use, mechanical connections or welded splices
must be used. Mechanical connections are made with
p ro p ri e t a ry splice devices. Pe rf o rmance information
and test data should be secured directly from manufac-
turers of the splice devices.
sign, specification and performance of splices rests with The purpose of this brief article is simply to answer
the engineer, and only the engineer who is familiar with some of the questions concerning welded splices. Al-
the structural analysis and design stress, probable con- though only welded splices are discussed here, it should
struction conditions and final conditions of service can not be construed that welded splices are being advocat-
properly evaluate the variables to select the most effi- ed. Each splice method has its advantages and suitabili-
cient and economical splice method. ty for particular applications. For projects of all sizes,
Three methods are used for splicing reinforcing bars: manual arc welding will usually be the most costly
method, due to direct and indirect costs of proper in-
• Lap splices spection.
• Mechanical connections Building code requirements for welded splices
• Welded splices The model building codes, which are the basis for
many statutory building codes, have some special re-
The traditional lap splice, when it will satisfy all re- quirements for welded splices. The Basic Building Code2
q u i re m e n t s, is generally the most economical splice, and the Standard Building Code3 adopt the ACI Building
and welded splices generally require the most expen- Code by re f e re n c e. Except for A706 bars, the Uniform
sive field labor. Howe ve r, lap splices cause congestion at Building Code4 prohibits welding unless the carbon
the splice locations, sometimes making their use impos- equivalent (explained below) is known. The UBC per-
sible. The location of construction joints, provision for mits the building official to waive this requirement for
future construction, and the particular method of con- minor details or repairs, provided the welding proce-
struction can also make lap splices impractical. In addi- dures are the same as those for a carbon equivalent ex-
tion, the ACI Building Code does not permit lap splices ceeding 0.75 percent.
in “tension tie members,” or in #14 and #18 bars except Some key items included in the ACI Building Code re-
for compression only, when spliced to smaller size foot- quirements for welded splices are: welding must con-
ing dowels. form to AWS D1.4-79;5 in a full welded splice, as re-
In column design, consideration must also be given to quired in a “tension tie member” or in compression, the
the fact that lapped offset bars may have to come inside bars have to be butted and the splice must develop at
of the bars above and therefore reduce the moment arm least 125 percent of the specified yield strength, fy, of the
in bending. When the amount of column vertical rein- bar. For tension splices where the area of the bars is
forcement is greater than 4 percent, and particularly in twice that required by structural analysis, the splices can
combination with large applied moments, the use of be designed for less than 125 percent fy of the bar. There
butt splices—either mechanical connections or welded are also rules for staggering the splices, and tack welding
splices—should be considered to reduce congestion, is not permitted unless authorized by the engineer. The
and to provide for greater design moment strength of basic welding requirements given in AWS D1.4-79,
the section at the splice locations. “St ru c t u ral Welding Code—Reinforcing Steel,” include
permissible stresses, both for the strength design Q: When or why would thermite welding be used?
method and the working stress method; splice details; A: Thermite welding has been used with success in mak-
workmanship; filler metal (electrodes) re q u i re m e n t s ; ing butt-welded joints in the large #14 and #18 bars. This
welding technique; welder qualification; and inspection. process has been successful in joining hard - t o - we l d
These are explained in the following series of questions steels, because it welds the entire cross section at the
and answers. same time and automatically provides preheat and slow
cooling.
Types of welded splices
Q: What types of welded splices are included in the AWS Q: Is thermite welding popular?
code?
A: Not so much in recent years for splicing rebars. It
A: Direct and indirect butt splices, and lap-welded seems to be extensively used in other applications such
splices. as continuously welded railroad rails; the suppliers of
the proprietary molds and other materials may be con-
Q: Is special end preparation of the bars required for direct centrating their attention on the other applications.
butt splices?
A: Yes, the particular end details—V-grooves or bevels— Q: The AWS code discusses filler metal (electrodes). What
depend upon whether the bars will be placed in a hori- kind of electrodes are required for arc welding?
zontal or vertical position. A: The electrodes should conform to AWS Specifications
A5.1 or A5.5. They should be of a classification and size
Q: What is an indirect butt splice? appropriate to the welding conditions and to the tensile
A: A splice where both bars are welded to a common strength and analysis of the bars to be welded. It is im-
splice member such as a plate, angle or other shape. portant that the coatings of low - h yd rogen-type elec-
The bars are nearly aligned; bar ends are separated no trodes such as Classes E70XX and E80XX be thoroughly
more than 3⁄4 inch; and the cross section of the bars is not dry when used. For example, E80XX electrodes taken
welded. from hermetically sealed packages must be used within
4 hours.
Q: What types of lap-welded splices are included in the
AWS code? Weldability and carbon equivalent
A: There are two types: direct and indirect. A direct type Q: When the subject of welding is discussed, the term
is one in which the bars are in contact and welded to- weldability is often mentioned. What is meant by weld -
gether; single or double lap joints can be used; they are ability?
suitable only for small bars, preferably #5 or smaller. A: A metallurgist defines weldability in terms of the
Double lap joints would be preferred if eccentricity of chemical composition of the steel; his measure is carbon
the splice is a consideration. In an indirect type, the bars equivalent content. A structural engineer probably
are welded to a common splice plate; there is a space be- thinks of weldability in terms of the strength achieved at
tween the bars. a splice, while a welder or contractor considers it in
terms of cost, welding method required, and amount of
Q: Where are fillet welds used? preheat. The AWS code defines weldability as “the ca-
A: An example would be connections of rebars to struc- pacity of a metal to be welded under the fabrication con-
tural steel members, provided sufficient stru c t u ra l ditions imposed into a specific suitably designed struc-
strength can be achieved. ture and to perform satisfactorily in the intended
service.”
Q: What welding processes does the AWS code cover?
Q: What is carbon equivalent?
A: Shielded metal arc, flux cored arc, pressure gas and
thermite welding processes. A: This is a quantitative measure of weldability. The car-
bon equivalent (C.E.) is based on the chemical composi-
tion of steel; it accounts for those chemical elements af-
Q: What is thermite welding?
fecting weldability, and it is a numerical value expressed
A: It is a process in which the ends of the bars are fusion as a percent. The AWS code and the ASTM A706 rebar
welded. Refractory molds are assembled on the bars and specification have the same formula for C.E.
sealed in place. Heat-generating powders are filled into a
separate cavity in the molds. The powders are ignited
%Mn %Cu %Ni %Cr %Mo %V
and burn with enough heat to form superheated molten C.E. = %C + ––––– + ––––– + ––––– + ––––– - ––––– - –––––
6 40 20 10 50 10
steel. The steel flows through the gap between the bars
and some flows into a second cavity beyond the bars,
preheating them. Subsequent flow completes the Note that fractions of the percentages of manganese
process. (Mn), copper (Cu), nickel (Ni) and chromium (Cr) are
added to the percentage of carbon (C). Fractions of the have to keep track of differing preheat temperatures for
percentages of alloying elements which enhance weld- each bar size or bar shipment.
ability, i.e., molybdenum (Mo) and vanadium (V) are
subtracted. Not all of these elements are necessarily pre- Q: What about projects which require some welding in
sent in any given heat of steel. important elements?
A: Project specifications should be open to include both
Q: How is the carbon equivalent value established? A706 and A615 bars. Specify mill test reports. The con-
A: From the chemical analyses in the mill test reports. tractor needs these reports to provide the required pre-
heat. Inspectors should be present whenever welding is
Q: Are chemical analyses routinely included in mill test done on important elements.
reports?
Q: What about small projects requiring little or only oc -
A: This depends on which steel is specified. Since the
casional welding in non-critical areas?
standard rebar specifications ASTM A615, A616 and
A617 specifically state that “weldability of the steel is A: Specify maximum preheat for an assumed carbon
not part of this specification,” there are no limits on the equivalent greater than 0.75 percent.
chemical elements included in the C.E. formula, nor is
there a limit on C.E. (the C.E. would typically exceed 0.55 Q: What about cooling the bars after the welding is com -
percent for these bars). The chemical composition pleted?
(A615) and carbon range (A617) are only provided upon A: The bars must be allowed to cool naturally; accelerat-
request. Of the chemical elements in the C.E. formula, ed cooling is prohibited.
only carbon and manganese will be reported for A615
bars unless special complete analyses are requested. Q: Is there a temperature restriction on field welding?
Howe ve r, A706 reinforcing bars are intended for weld-
A: AWS D1.4-79 prohibits manual arc welding when the
ing. In addition to restrictions on chemical composition
ambient temperature is less than 0° F.
including carbon, the C.E. is limited to 0.55 percent. The
chemical composition and C.E. must be reported.
Q: Little or no preheat is required for bars with lower
Q: How is the carbon equivalent used in the AWS code? ranges of carbon equivalent; are there requirements when
the ambient temperature is low?
A: The minimum preheat and interpass tempera t u re s
are based upon carbon equivalent. For instance, ASTM A: For bars which require no preheat at normal working
A706 rebars are limited to a C.E. of 0.55 percent, and the temperatures, if the temperature of the bars is below 32°
AWS code requires little or no preheat for bars at or be- F, they must be preheated to at least 70 degrees F and this
low this limit. temperature must be maintained during welding.
Some bars require little preheat at normal working
Q: What preheat is required for larger values of carbon t e m p e ra t u res; for example, #11 bars having a carbon
equivalent? equivalent from 0.46 to 0.55 percent require a preheat of
50° F. If these bars are at a temperature below 50°F they
A: The highest preheat, 500 degrees F, is required for all
must be preheated so that the temperature of the cross
bar sizes if the carbon equivalent is above 0.75 percent. If
section of the bar within 6 inches on each side of the
the chemical composition of the bars to be welded is not
joint is 50° F or greater.
known, the carbon equivalent is assumed to be above
0.75 percent.
Q: What is the tack welding which the ACI Code pro -
Specifying bars for welding hibits?
Q: What are some practical points that one should con - A: Connection of crossing rebars by small arc welds, such
sider when specifying welded splices? as in a column cage where the ties are welded to the lon-
A: This depends on the size of the project and the gitudinal bars. If tack welding is authorized by the engi-
amount and importance of the welding. There is an ex- neer, the welds should be made in conformance with all
cellent discussion in Reference 2. requirements of AWS D1.4-79. We do not recommend
this practice; wire ties should be used for assembly of
Q: Besides requiring all welding to conform to AWS D1.4- reinforcing steel.
79, what should be considered in a large, long term pro -
ject involving extensive welding in important structural Q: Why is tack welding a poor practice?
elements? A: For the column cage case, such welding can cause a
A: Consider use of A706 rebars; check availability before metallurgical “notch” effect in the big longitudinal bars,
specifying. Field inspection will be simplified since little reducing their original tensile strength and bendability.
or no preheat will be required, and inspectors will not Tack welding is particularly detrimental to impact resis-
tance and fatigue resistance. 2. Basic Building Code, 1981 Edition, Building Officials and
Code Administrators International, Inc., Homewood, Illinois.
Q: Are the harmful effects of tack welding well proven? 3. Standard Building Code, 1979 Edition, Southern Building
A: Yes, research reports are cited in Reference 7. See Ref- Code Congress International Inc., Birmingham, Alabama.
erence 8 also. 4. Uniform Building Code, 1979 Edition, International Con-
ference of Building Officials, Whittier, California.
Conclusions
5. “Structural Welding Code—Reinforcing Steel (D1.4-79),”
It is evident from these questions and answers that American Welding Society, 2501 N.W. 7th Street, Miami,
properly engineered and constructed welded splices re- Florida 33125.
quire more considerations than a simple statement in
the contract documents, “All welded splices shall con- 6. Rice, P. F. and Hoffman, E. S., Structural Design Guide to
the ACI Building Code, 2nd Edition, Van Nostrand Reinhold,
form to ‘St ru c t u ral Welding Co d e — Re i n f o rcing Steel’ 1979.
(AWS D1.4-79).” The welding code is a comprehensive
document. Howe ve r, other important items such as se- 7. Reinforcement Anchorage and Splices, Concrete Rein-
curing chemical properties of the rebars, field inspec- forcing Steel Institute, Chicago, 1980.
tion, supervision, and quality control are required for a 8. Firth, M. and Williams, W. M., “Avoid Martensite When
project with welded reinforcement. Welding Rebar,” Metal Progress, April 1979, pages 38-40.

References 9. ASTM standards referenced by number throughout text


are available from American Society for Testing and Materi-
1. “Building Code Requirements for Reinforced Concrete als, 1916 Race Street, Philadelphia, Pennsylvania 19103.
(ACI 318-77),” American Concrete Institute, Detroit, Michi-
gan, 1977.

PUBLICATION#C810807
Copyright © 1981, The Aberdeen Group
All rights reserved

You might also like