You are on page 1of 1

Republic of the Philippines

Province of Iloilo
Municipality of Lambunao
Office of the Mayor

Date ______________

NOTICE TO COMMENCE WORK


J & A CALIBRATION
Name of Claimant

Labor and Replacement of spareparts of DT 03, Lambunao, Iloilo


_________________________________________________________________
Name of Project and Location

The CONTRACT THEREFORE having been approved, a copy of which will


furnished, NOTICE is hereby given that the work on this project may be commenced
upon the effectively of the contract and will be counted three (3) days after the date
of this NOTICE.

EFFECTIVITY OF CONTRACT: ______________


CONTRACT TIME: ___________________

Recommended for Approval:

LEO S. LEONIDA
Municipal Engineer

Approved by:

REYNOR R. GONZALES
Municipal Mayor