C AROIL DAILY STATEMENT

Date: 8-juin-18
Client : ENI CONGO S.A. Rig : DP3
Contract : 5000117901/219 - Révision nr 01
au contrat 50001179/212
Daily Statement Address : B.P. 706
65 Effective date of contract : May 1st, 2015
DMR 125-126 Avenue Général de Gaulle
Pointe-Noire Field : Loango
République du Congo Well : DP 3 - P615
Rate A = Operating rate - Workover
Rate B = Stand-By Rate - Workover
Rate C = Moving Rate - Workover

OPERATIONS A B C
FROM TO TIME
00:00 06:00 6.0 Wait on daylight 6.0

06:00 07:00 1.0 Travel from HBS to DP3 1.0

07:00 08:00 1.0 Morning safety meeting - Open PTW's 1.0

08:00 17:00 9.0 General maintenance - Housekeeping & asset preservation - Wait on crane repair prior to move BOP skid - 9.0

17:00 24:00 7.0 'Travel from DP3 to HBS - Wait on daylight 7.0

EXTRA : NIGHT PUSHER x 1 Total = 24.0


24.0 0.0 0.0 24.0

CAROIL REPRESENTATIVE ENI COMPANY MAN


IMPERIALE ALAIN ANIAMABO SEMA B.