C AROIL DAILY STATMENT

Date: 8-mars-18
Client : ENI CONGO S.A. Rig : DP3
Contract : 5000117901/219 - Révision nr 01
au contrat 50001179/212
Daily Statment: Address : B.P. 706
3 Effective date of contract : May 1st, 2015
DDR 125-126 Avenue Général de Gaulle
Pointe-Noire Field : Loango
République du Congo Well : DP 3 - P619
Rate A = Operating rate - Workover
Rate B = Stand-By Rate - Workover
Rate C = Moving Rate - Workover

OPERATIONS A B C
FROM TO TIME
00:00 07:00 7.0 Wait on crane to be repair, prior to continue with R/U halliburton and Maersk equipment 7.0
07:00 08:30 1.5 Crewchange, hold PJSM and open PTW. 1.5
08:30 14:00 5.5 Wait on crane to be repair, prior to continue with R/U halliburton and Maersk equipment 5.5
14:00 18:00 4.0 Afrimel mechanic work on cranewith no success. Meanwhile Caroil crew continue on Rig preparation 4.0
18:00 24:00 6.0 Mobilize crane specialist and equipment form town. 6.0

EXTRA : NIGHT PUSHER 1

24.0 0.0
Total = 24.0
24.0 0.0

CAROIL REPRESENTATIVE COMPANY MAN


MONROY WILLIAM BASSANI ALESSANDRO