Professional Documents
Culture Documents
Hugh Rudnick
Seguridad de abastecimiento eléctrico
3
Large earthquakes in Chile
5
Large acceleration for long time
Peak acceleration of 0.65 g for one of the horizontal
records. Duration of strong shaking for 70 seconds
6
Its effects– structural collapses
7
Its effects– building collapses
8
Effects of the tsunami
9
Norms and standards in Chile
12
Evolution of electricity demand
13
Impact on operation
Severe impacts on country communication
systems. Basic systems (mobile networks,
emergency alert schemes, public order control),
electricity dependant, did not operate as desired
and caused additional harm.
Difficulties also arose in the communications
and telecontrol schemes of most electricity
installations, transmission substations and
generating plants, complicating plant and
system recovery and operation. No alternative
backup radio systems.
14
Impact on operation
System operator (CDEC-SIC) had additional
difficulties throughout the emergency as the
SCADA system in use (for over ten years), was
not able to provide information required for
system recovery (alarms could not be trusted as
they were often incorrect).
Traditional phone calls had to be used to learn
on local conditions and supervise actions for
equipment and system restoration.
15
Dispatched generation at event
4,522 MW dispatched
Immediate blackout
16
Damage in generation plants
Bocamina plant
17
But most remain available
950 MW
being built also
damaged
Cooling systems,
transformers,
communications,
lines, etc.
20
Damages in substations
21
But most remain available
Capacitor bank
without damage
22
But most remain available
Circuit breakers
with sufficient
damping
23
Transmission assesment
Damages concentrated in one transmission line
3 towers 154 kV line (1.6 km)
24
Transmission interconnection recovery
Recovery process of the interconnected system
25
Worse extended damage in distribution
26
Worse extended damage in distribution
27
Worse extended damage in distribution
28
But most remains standing
29
Distribution damage
4.5 million people were initially affected by the
extended blackout that took place because of the
earthquake and it took days, and even weeks in
some areas, to recover full electricity supply.
Most affected areas supplied by CGE, Emelectric
and Emelat. Chilectra also affected in Santiago.
80% of clients were without supply the day after
the earthquake and this reduced to 0.4% two
weeks after (related mainly to Concepcion and
Talcahuano, next to the earthquake epicenter).
30
Distribution damage
Some distribution networks were destroyed by
the effects of the earthquake, as houses fell over
street lines or simply were washed away by the
tsunamis (for example 40,000 houses were
destroyed out of 1.5 million supplied by CGE).
Besides those distribution installations directly
damaged, there was little damage elsewhere.
Distribution poles in Chile are mainly
compressed pre-stressed concrete poles, which
are well founded, and support important
mechanical stresses. Exceptions in overloaded
city poles.
31
Worse extended damage in distribution
32
Small percentage damage
34
Damage in distribution
Distribution aerial transformers are often placed
between two poles and a steel support, thus they also
withstand well an earthquake.
Main difficulties in restoring supply to houses took place
at the connection point between the low voltage lines
and the buildings.
Companies have equipment and human resources to
repair normal failures within one or two days. But when
several hundred thousand of those connections fail, as in
an earthquake, the problem is quite different.
Communication problems, difficult physical access to
locations, no resources to manage the huge number of
needed repairs. Companies involved human resources
brought from other regions.
35
Damage in distribution
Mobile generating sets brought to support recovery of
supply, particularly in more isolated areas.
36
Araneda, Juan Carlos
(Transelec), Rudnick,
Hugh (PUC), Mocarquer,
Sebastian (Systep), Miquel,
Pedro (Systep), "Lessons
from the 2010 Chilean
earthquake and its impact
on electricity supply", 2010
International Conference
on Power System
Technology (Powercon
2010), Hangzhou, China,
October 24-28, 2010
37
Balance y conclusiones
Experiencia internacional indica mayores daños
en transmisión y distribución
Altos estándares y códigos constructivos civiles
y en equipos eléctricos de generación
38
Balance y conclusiones
Balance negativo de capacidad de respuesta del
país y su institucionalidad de emergencia.
Inaceptables niveles de fallas de infraestructura
de comunicación
40
Agradecimientos
Transelec
CGE Distribución
CGE Transmisión
CDEC-SIC
Chilectra
American Society of Civil Engineers’ Post-
Disaster Assessment Teams (Dr. Anshel Schiff,
Stanford University)
41
Lecciones del terremoto de Chile 2010 y su
impacto en el suministro eléctrico
Hugh Rudnick