MEMBINA DAN MENYIAPKAN JALANRAYA SIMPANG PULAI - GUA MUSANG - KUALAN BERANG PAKEJ 4 - POS BLAU KE KG. KUALA BETIS TRANS RESOURCES CORPORATION SDN. BHD. PAKEJ 4B - DARI CH. 10.00M KE CH. 20.043M
16 + 800 16 + 825 2,609.25 0.05% 0 0 0 0.00
16 + 900 17 + 175 149,336.57 2.80% 85 0 85 2.38
3,510,786.28 65.77%
DESIGN AND BUILD WORKDONE PERCENTAGE ANALYSIS
ITEM : 2.2.1 SUITABLE CUT DATE : 21-Nov-01
Chainage Total Quantity Weightage Workdone Quantity %
Form To Cu.M Factor Previous Current Total Workdone Carried Forward 3,510,786.28 65.77% 35.58